- Latest available (Revised)
- Original (As made)
There are multiple versions of this provision on screen. These apply to different geographical extents.
The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents. Insertions and repeals of text do not give rise to such multiple versions.
There are currently no known outstanding effects for the The Community Infrastructure Levy Regulations 2010, Section 9.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
9.—(1) The chargeable development is the development for which planning permission is granted.
(2) Paragraph (1) is subject to the following provisions of this regulation.
(3) Where planning permission is granted by way of a general consent, the chargeable development is the development identified in a notice of chargeable development submitted to the collecting authority in accordance with regulation 64 [F1, or prepared by the collecting authority in accordance with regulation 64A].
(4) In the case of a grant of [F2phased planning permission], each phase of the development is a separate chargeable development.
[F3(5) In Wales, where the effect of a planning permission granted under section 73 of TCPA 1990 is only to change a condition subject to which a previous planning permission was granted by extending the time within which development must be commenced, the chargeable development is the development for which permission was granted by the previous permission as if that development was commenced.
[F4(6) Where a planning permission is granted under section 73 of TCPA 1990, the chargeable development is the most recently commenced or re-commenced chargeable development.]
F4(7) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F4(8) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(9) For the purposes of [F5paragraph (6)], chargeable development is re-commenced where—
(a)the chargeable development (“the earlier development”) was commenced;
(b)work on the earlier development was halted and a different chargeable development (“the later development”) that was granted planning permission under section 73 of TCPA 1990 was commenced on the relevant land; and
(c)the later development was subsequently halted and the earlier development is continued.]
Extent Information
E1This version of this provision applies to England only; a separate version has been created for Wales only
Textual Amendments
F1Words in reg. 9(3) inserted (6.4.2011) by The Community Infrastructure Levy (Amendment) Regulations 2011 (S.I. 2011/987), regs. 1, 4(3)
F2Words in reg. 9(4) substituted (24.2.2014) by The Community Infrastructure Levy (Amendment) Regulations 2014 (S.I. 2014/385), regs. 1, 4(2) (with reg. 14(1)(7))
F3Reg. 9(5)-(9) substituted for reg. 9(5) (29.11.2012) by The Community Infrastructure Levy (Amendment) Regulations 2012 (S.I. 2012/2975), regs. 1, 3(2) (with reg. 10(1))
F4Reg. 9(6) substituted for reg. 9(6)-(8) (E.) (1.9.2019) by The Community Infrastructure Levy (Amendment) (England) (No. 2) Regulations 2019 (S.I. 2019/1103), regs. 1, 5(1)(a) (with regs. 1(3), 13)
F5Words in reg. 9(9) substituted (E.) (1.9.2019) by The Community Infrastructure Levy (Amendment) (England) (No. 2) Regulations 2019 (S.I. 2019/1103), regs. 1, 5(1)(b) (with regs. 1(3), 13)
Commencement Information
I1Reg. 9 in force at 6.4.2010, see reg. 1
9.—(1) The chargeable development is the development for which planning permission is granted.
(2) Paragraph (1) is subject to the following provisions of this regulation.
(3) Where planning permission is granted by way of a general consent, the chargeable development is the development identified in a notice of chargeable development submitted to the collecting authority in accordance with regulation 64 [F6, or prepared by the collecting authority in accordance with regulation 64A].
(4) In the case of a grant of [F7phased planning permission], each phase of the development is a separate chargeable development.
[F8(5) In Wales, where the effect of a planning permission granted under section 73 of TCPA 1990 is only to change a condition subject to which a previous planning permission was granted by extending the time within which development must be commenced, the chargeable development is the development for which permission was granted by the previous permission as if that development was commenced.
(6) Where the effect of a planning permission granted under section 73 of TCPA 1990 is to change a condition subject to which a previous planning permission was granted so that the amount of CIL payable calculated under regulation 40 (as modified by paragraph (8)) would not change, the chargeable development is the development for which planning permission was granted by the previous permission as if that development was commenced.
(7) Where the effect of the planning permission granted under section 73 of TCPA 1990 is to change a condition subject to which a previous planning permission was granted so that the amount of CIL payable under regulation 40 (as modified by paragraph (8)) would change, the chargeable development is the most recently commenced or re-commenced chargeable development.
(8) For the purposes of paragraphs (6) and (7), the liability to CIL under regulation 40 should be calculated in relation to an application made under section 73 of TCPA 1990 as if the date on which the planning permission granted under that application first permits development was the same as that for the application for planning permission to which the application under section 73 of TCPA 1990 relates.
(9) For the purposes of paragraph (7), chargeable development is re-commenced where—
(a)the chargeable development (“the earlier development”) was commenced;
(b)work on the earlier development was halted and a different chargeable development (“the later development”) that was granted planning permission under section 73 of TCPA 1990 was commenced on the relevant land; and
(c)the later development was subsequently halted and the earlier development is continued.]
Extent Information
E2This version of this provision applies to Wales only; a separate version has been created for England only
Textual Amendments
F6Words in reg. 9(3) inserted (6.4.2011) by The Community Infrastructure Levy (Amendment) Regulations 2011 (S.I. 2011/987), regs. 1, 4(3)
F7Words in reg. 9(4) substituted (24.2.2014) by The Community Infrastructure Levy (Amendment) Regulations 2014 (S.I. 2014/385), regs. 1, 4(2) (with reg. 14(1)(7))
F8Reg. 9(5)-(9) substituted for reg. 9(5) (29.11.2012) by The Community Infrastructure Levy (Amendment) Regulations 2012 (S.I. 2012/2975), regs. 1, 3(2) (with reg. 10(1))
Commencement Information
I2Reg. 9 in force at 6.4.2010, see reg. 1
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: