Chwilio Deddfwriaeth

The Feed-in Tariffs Order 2012

Changes over time for: The Feed-in Tariffs Order 2012 (Schedules only)

 Help about opening options

Version Superseded: 01/02/2019

Status:

Point in time view as at 20/03/2017.

Changes to legislation:

There are currently no known outstanding effects for the The Feed-in Tariffs Order 2012. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 2(1)

[F1SCHEDULE A1E+W+SMCS-certified installations

Textual Amendments

1.  An eligible installation is an MCS-certified installation if it is certified under—E+W+S

(a)the MCS and installed in accordance with the relevant installation standard in the scheme; or

(b)a scheme where—

(i)installers are certified to that scheme’s standards by an organisation accredited to EN 45011(2) or EN ISO/IEC 17065:2012(3);

(ii)the plant is installed in accordance with the installation standards applicable to the plant under that scheme on the plant’s first commissioning date and which are equivalent to a relevant installation standard; and

(iii)that scheme is equivalent to the Microgeneration Certification Scheme.

2.  In paragraph 1, “relevant installation standard” means—E+W+S

(a)if the commissioning date for the installation is on or after 15th January 2016, if the installation is—

(i)a solar photovoltaic installation, version 3.3 of the document entitled Microgeneration Installation Standard: MIS 3002 requirements for MCS contractors undertaking the supply, design, installation, set to work commissioning and handover of solar-photovoltaic (PV) microgeneration systems,

(ii)a wind installation, version 3.4 of the document entitled Microgeneration Installation Standard: MIS 3003 requirements for MCS contractors undertaking the supply, design, installation, set to work commissioning and handover of micro and small wind turbine systems,

(iii)a heat-led combined heat and power installation, version 3.2 of the document entitled Microgeneration Installation Standard: MIS 3007 requirements for MCS contractors undertaking the design, supply, installation, set to work, commissioning and handover of a heating system containing and micro-cogeneration package; or

(iv)an electricity-led combined heat and power installation, version 2.3 of the document entitled Microgeneration Installation Standard: MIS 3007-2 requirements for MCS contractors undertaking the design, supply, installation, set to work, commissioning and handover of a domestic hot water system combining an electricity led micro-cogeneration package; or

(b)if the commissioning date for the installation is before the 15th January 2016, any installation requirements applicable to the installation under the MCS on the installation’s commissioning date.

3.  When exercising any functions under this Order, the Authority may treat the certification of an eligible installation in accordance with this Schedule as evidence that the installation is installed in accordance with a relevant installation standard or a standard which is equivalent to a relevant installation standard.E+W+S

4.  In this Schedule, “MCS” means the Microgeneration Certification Scheme. ]E+W+S

Article 21

SCHEDULE 1E+W+SThe central FIT register

1.—(1) The central FIT register must contain sufficient information to identify each accredited FIT installation.E+W+S

(2) Information under paragraph (1) must include, in respect of each accredited FIT installation—

(a)the tariff code assigned under article 13;

(b)the unique identifier assigned under article 14;

(c)the site of the installation determined under article 15;

(d)the confirmation date;

(e)whether or not the installation has been extended;

(f)whether or not the installation has been modified (other than by way of an extension which falls within Part 4);

(g)if applicable, the number of the MCS certificate;

(h)the eligible low carbon energy source used;

(i)the total installed capacity;

(j)details of the FIT generator and, if applicable, details of the FIT generator's nominated recipient;

(k)whether or not an export payment is paid and how that export payment is determined;

(l)the date of the statement of FIT terms;

(m)details of the generation and, if applicable, export meters which apply to the accredited FIT installation, including meter point administration numbers.

2.  The central FIT register must contain sufficient information to identify, in respect of each accredited FIT installation—E+W+S

(a)the FIT licensee responsible for making FIT payments;

(b)the FIT generator and any nominated recipient to which the FIT licensee makes FIT payments.

Article 8B

[F2SCHEDULE 1AE+W+SLimit of aggregate capacity of eligible installations

Textual Amendments

Table 1: Limit of aggregate total installed capacity of eligible installations (in megawatts) applied for in respect of eligible installations of a particular description for a particular tariff period

8th February to 31st March 20161st April to 30th June 20161st July to 30th September 20161st October to 31st December 20161st January to 31st March 20171st April to 30th June 20171st July to 30th September 20171st October to 31st December 20171st January to 31st March 20181st April to 30th June 20181st July to 30th September 20181st October to 31st December 20181st January to 31st March 2019
Anaerobic digestion installations5.85.05.05.05.05.05.05.05.05.05.05.05.0
Hydro generating stations with total installed capacity of 100 kW or less1.11.11.21.21.21.31.31.31.31.31.41.41.4
Hydro generating stations with total installed capacity greater than 100 kW6.16.26.36.36.46.46.46.46.46.46.46.36.3
Solar photovoltaic (other than stand-alone) with total installed capacity of 10 kW or less48.449.650.651.752.853.854.255.957.058.059.160.161.1
Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10 kW but not exceeding 50 kW16.517.017.417.818.218.618.719.419.820.320.721.121.5
Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50 kW14.114.514.915.415.816.216.417.117.618.018.519.019.4
Stand-alone solar photovoltaic5.05.05.05.05.05.05.05.05.05.05.05.05.0
Wind with total installed capacity of 50 kW or less5.65.65.55.55.65.55.55.45.55.45.45.35.4
Wind with total installed capacity greater than 50 kW but not exceeding 100 kW0.30.30.30.30.30.30.30.30.30.30.30.30.3
Wind with total installed capacity greater than 100 kW but not exceeding 1500 kW6.86.76.66.56.46.36.26.16.15.95.85.75.7
Wind with total installed capacity greater than 1500 kW5.05.05.05.05.05.05.05.05.05.05.05.05.0]

[F3Table 2

Limit of aggregate installed capacity of eligible installations (in megawatts) applied for in respect of eligible combined heat and power installations for a particular tariff period

1st April to 30th September 20171st October 2017 to 31st March 20181st April to 30th September 20181st October 2018 to 31st March 2019
Combined heat and power installation with total installed capacity of 2 kilowatts or less5.05.05.05.0]

Textual Amendments

Article 35A

[F4SCHEDULE 2E+W+SFIT applications data

Textual Amendments

1.  Within the first 5 working days of each tariff period, the Authority must determine and publish the data set out in paragraph 2.E+W+S

2.  The data referred to in paragraph 1 are—E+W+S

(a)the aggregate total installed capacities of anaerobic digestion installations applied for within the deployment period;

[F5(aa)the aggregate total installed capacities of combined heat and power installations (each with total installed capacity of 2 kilowatts or less) applied for within the deployment period;]

(b)the aggregate total installed capacities of hydro generating stations with total installed capacity of 100 kilowatts or less, applied for within the deployment period;

(c)the aggregate total installed capacity of hydro generating stations with total installed capacity greater than 100 kilowatts applied for within the deployment period;

(d)the aggregate total installed capacities of solar photovoltaic (other than stand-alone), with total installed capacity of 10 kilowatts or less, which were registered on the MCS database within the deployment period;

(e)the aggregate total installed capacities of solar photovoltaic (other than stand-alone), with total installed capacity greater than 10 kilowatts but not exceeding 50 kilowatts, which were registered on the MCS database within the deployment period;

(f)the aggregate total installed capacities of solar photovoltaic installations (other than stand-alone), with total installed capacity greater than 50 kilowatts applied for within the deployment period;

(g)the aggregate total installed capacities of stand-alone solar photovoltaic installations applied for within the deployment period, including those which were registered on the MCS database within the deployment period;

(h)the aggregate total installed capacities of wind installations, with total installed capacity of 50 kilowatts or less, which were registered on the MCS database within the deployment period;

(i)the aggregate total installed capacities of wind installations, with total installed capacity greater than 50 kilowatts but not exceeding 100 kilowatts applied for within the deployment period;

(j)the aggregate total installed capacities of wind installations, with total installed capacity greater than 100 kilowatts but not exceeding 1500 kilowatts, applied for within the deployment period; and

(k)the aggregate total installed capacity of wind installations, with total installed capacity greater than 1500 kilowatts, applied for within the deployment period.

3.  In this Schedule—E+W+S

“applied for” refers to an application for accreditation or preliminary accreditation made in respect of a relevant installation;

“the deployment period” in relation to a tariff period in which data is required to be determined and published, means the period of three months immediately preceding that tariff period;

“MCS database” means the database maintained by the Microgeneration Certification Scheme that records the details of MCS-certified installations; and

“relevant installation” has the meaning given in article 8B(4)(b).]

Articles 38D and 38J

[F6SCHEDULE 2AE+W+SGreenhouse gas criteria

PART 1E+W+SGreenhouse gas criteria

The greenhouse gas criteriaE+W+S

1.  The biogas used to generate electricity at a relevant installation meets the greenhouse gas criteria if the greenhouse gas emissions from each consignment of biomass used to make the biogas are equal to, or less than, the relevant target.

Calculating the greenhouse gas emissionsE+W+S

2.  For the purposes of paragraph 1, and subject to paragraphs 3 and 4, the greenhouse gas emissions from the use of biomass to make the biogas are to be calculated using the actual value method or the default value method.

3.  The default value method must not be used to calculate greenhouse gas emissions from the use of biomass unless—

(a)the biomass was used in a generating station with a total installed capacity of less than 1 megawatt;

(b)the biomass is described in the first column of the table in Part 2; and

(c)in relation to biomass, the result of the calculation in paragraph 7 of Part C of Annex 5 to the Renewables Directive is equal to, or less than, zero.

4.  For the purposes of paragraph 3(c), paragraph 7 of Part C of Annex 5 to the Renewables Directive is to be read as if—

(a)for each reference to “biofuel” there was substituted “biomass”; and

(b)the words “or bioliquid” were omitted in each place in which those words occur.

InterpretationE+W+S

5.  In this Schedule—

“actual value method” means the calculation method provided for in paragraphs 6 and 7 of Part 2 of Schedule 2 to the RO Order and all references to “the month” in paragraph 7 are to be read as references to “the quarterly reporting period”;

“default value method” means the calculation method provided for in paragraphs 8 and 9 of Part 3 of Schedule 2 to the RO Order and the reference in paragraph 9 of that Part to “the table in Part 4” is to be read as a reference to the table in Part 2 of this Schedule;

“relevant target” means—

(a)

in relation to biogas used to generate electricity before 1st April 2020, 66.7 grams per megajoule of electricity;

(b)

in relation to biogas used to generate electricity on or after 1st April 2020 and before 1st April 2025, 55.6 grams per megajoule of electricity; and

(c)

in relation to biogas used to generate electricity on or after 1st April 2025, 50 grams per megajoule of electricity;

“the Renewables Directive” means Directive 2009/28/EC of the European Parliament and of the Council on the promotion of the use of energy from renewable sources;

“the RO Order” means the Renewables Obligation Order 2015.

PART 2E+W+SDefault greenhouse gas emissions from the production of biomass

BiomassDefault greenhouse gas emissions from the production of biomass (in grams)
Bagasse briquettes where the process to produce the briquettes was fuelled by wood17
Bagasse bales20
Palm kernel27
Rice husk briquettes28
Biogas produced from wheat, where the whole plant was used to produce the biogas21
Wheat straw2
Biogas produced from straw21
Biogas produced from organic maize, where the whole plant was used to produce the biogas19]

Article 40

SCHEDULE 3E+W+SRevocations

Orders revokedReferences
The Feed-in Tariffs (Specified Maximum Capacity and Functions) Order 2010S.I. 2010/678
The Feed-in Tariffs (Specified Maximum Capacity and Functions) (Amendment) Order 2011S.I. 2011/1181
The Feed-in Tariffs (Specified Maximum Capacity and Functions) (Amendment No. 2) Order 2011S.I. 2011/1655
The Feed-in Tariffs (Specified Maximum Capacity and Functions) (Amendment No. 3) Order 2011S.I. 2011/2364
The Feed-in Tariffs (Specified Maximum Capacity and Functions) (Amendment) Order 2012S.I. 2012/671
The Feed-in Tariffs (Specified Maximum Capacity and Functions) (Amendment No. 2) Order 2012S.I. 2012/1393
The Feed-in Tariffs (Specified Maximum Capacity and Functions) (Amendment No. 3) Order 2012S.I. 2012/2268

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill