Chwilio Deddfwriaeth

The Reservoirs Act 1975 (Capacity, Registration, Prescribed Forms, etc.) (England) Regulations 2013

Changes over time for: The Reservoirs Act 1975 (Capacity, Registration, Prescribed Forms, etc.) (England) Regulations 2013 (Schedules only)

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Reservoirs Act 1975 (Capacity, Registration, Prescribed Forms, etc.) (England) Regulations 2013. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to :

Regulations 4 and 6

SCHEDULE 1E+WInformation to be given in English registers of large raised reservoirs

1.  Name and situation of reservoir.E+W

Commencement Information

I1Sch. 1 para. 1 in force at 30.7.2013, see reg. 1(b)

2.  National grid reference of reservoir.E+W

Commencement Information

I2Sch. 1 para. 2 in force at 30.7.2013, see reg. 1(b)

3.  Name and address of undertakers.E+W

Commencement Information

I3Sch. 1 para. 3 in force at 30.7.2013, see reg. 1(b)

4.  A summary of the contents of all certificates or reports made under the 1975 Act, or the 1930 Act, including—E+W

(i)the name and address of the engineer giving the certificate or making the report;

(ii)the section of whichever Act the certificate is given under or the report is made;

(iii)where no final certificate has been given under the 1975 Act, a statement of that fact;

(iv)where no final certificate was given under the 1930 Act because the construction or alteration of the reservoir was completed before the commencement of that Act, a statement of that fact.

Commencement Information

I4Sch. 1 para. 4 in force at 30.7.2013, see reg. 1(b)

5.  The following information if it is revealed by any certificate, report or statement—E+W

(i)the category of the reservoir (whether impounding or non-impounding);

(ii)year(s) in which the dam(s), reservoir walls or embankments(s) were completed;

(iii)the construction of the dam(s), reservoir walls or embankments(s) (i.e. whether constructed of earth, rockfill, gravity, buttress or by other means);

(iv)the level of the top of the dam(s), reservoir walls or embankments(s) of the reservoir with reference to Ordnance Datum;

(v)the top water level of the reservoir with reference to Ordnance Datum;

(vi)the maximum height of the dam(s), reservoir walls or embankments(s) measured in metres from the lowest natural level of the surrounding land, to the top of the dam(s), reservoir walls or embankments, excluding the height of the wave wall;

(vii)the capacity of the reservoir;

(viii)the water surface area of the reservoir at top water level (in square metres or square kilometres).

Commencement Information

I5Sch. 1 para. 5 in force at 30.7.2013, see reg. 1(b)

6.  Name and business address of the supervising engineer or, if the reservoir is under the supervision of the construction engineer, of that engineer.E+W

Commencement Information

I6Sch. 1 para. 6 in force at 30.7.2013, see reg. 1(b)

7.  Date when the next inspection is due under the 1975 Act or any date recommended for the next inspection under the 1975 Act by the supervising or inspecting engineer.E+W

Commencement Information

I7Sch. 1 para. 7 in force at 30.7.2013, see reg. 1(b)

8.  Particulars of any appointment made by the Agency under section 15 of the 1975 Act.E+W

Commencement Information

I8Sch. 1 para. 8 in force at 30.7.2013, see reg. 1(b)

9.  Particulars of any appointment made by the Agency under section 16 of the 1975 Act, including the date on which they were taken.E+W

Commencement Information

I9Sch. 1 para. 9 in force at 30.7.2013, see reg. 1(b)

10.  Whether the large raised reservoir is designated as high-risk.E+W

Commencement Information

I10Sch. 1 para. 10 in force at 30.7.2013, see reg. 1(b)

Regulation 9

SCHEDULE 2E+WPrescribed form of record for a high-risk reservoir

Commencement Information

I11Sch. 2 in force at 30.7.2013, see reg. 1(b)

Regulation 9

SCHEDULE 3E+WPrescribed matters relating to high-risk reservoirs of which an undertaker is to keep a record

InterpretationE+W

1.  In this Schedule “fetch” means the effective length of the reservoir over which wind can build up waves.

Commencement Information

I12Sch. 3 para. 1 in force at 30.7.2013, see reg. 1(b)

Prescribed mattersE+W

2.  An undertaker of a high-risk reservoir must keep a record of the following matters—

(1) persons having, in relation to the reservoir, a function provided for by the 1975 Act;

(2) flood plan details;

(3) means of access to the reservoir;

(4) category of the reservoir (i.e. whether impounding or non-impounding), its use, the certified level up to which it may store water, its surface water area, capacity and fetch;

(5) structural character of the dam(s), reservoir walls or embankments, their date of completion, height, level of the top of the dam(s), reservoir walls or embankments and of the wave wall above Ordnance Datum;

(6) details of draw off works, bottom outlets, or any other means of lowering the water level, together with their maximum rates of discharge;

(7) physical characteristics of direct and indirect catchment areas of the reservoir and method of filling from indirect catchment area;

(8) standard average annual rainfall on direct and indirect catchment areas of the reservoir;

(9) spillway works, their type, location and level and the safety provisions made in connection with their operation;

(10) measures taken in the interests of safety on the recommendation of a qualified civil engineer;

(11) supervising engineer directions and recommendations;

(12) unusual events which could affect the safety of the reservoir;

(13) certificates given under the 1975 Act or under the 1930 Act;

(14) reports made under the 1975 Act or under the 1930 Act;

(15) directions made under the 1975 Act;

(16) appointment of referees under the 1975 Act;

(17) re-use, abandonment and discontinuance;

(18) drawing register;

(19) instrumentation at the reservoir;

(20) records of extent of opening of valves, gates and penstocks, related information and directions by an engineer.

Commencement Information

I13Sch. 3 para. 2 in force at 30.7.2013, see reg. 1(b)

Regulation 10

SCHEDULE 4E+WCertificates

Commencement Information

I14Sch. 4 in force at 30.7.2013, see reg. 1(b)

The italicised letters in the forms of certificates in this Schedule indicate the information to be included as follows—

(a)name of engineer;

(b)address of engineer;

(c)name of panel to which engineer is appointed;

(d)name of undertakers;

(e)name of reservoir;

(f)situation of reservoir, with sufficient detail to identify it (including the National Grid Reference of the approximate centre of the reservoir);

(g)level above Ordnance Datum to which water may be filled, excluding the allowance made for flood conditions;

(h)level above Ordnance Datum to which water may be stored, excluding the allowance made for flood storage;

(i)date of preliminary or interim certificate as appropriate;

(j)conditions subject to which the reservoir may be filled with water or water may be stored up to the level specified;

(k)date of report, certificate, direction, as appropriate;

(l)date of completion of works;

(m)period recommended in the report within which the next inspection should be made;

(n)date of inspecting engineer’s report;

(o)name of inspecting engineer;

(p)name of referee;

(q)address of referee;

(r)date of referee’s decision;

(s)name of person appointing referee;

(t)volume of water that makes a reservoir a “large raised reservoir” under the Act;

(u)the time by which the water level must be reduced.

In these forms of certificates, square brackets and the words within them are not to be included where they are inappropriate.

Regulation 11

SCHEDULE 5E+WReports

Commencement Information

I15Sch. 5 in force at 30.7.2013, see reg. 1(b)

In this Schedule references to an engineer’s findings and recommendations include—

(i)when appropriate, findings as to whether undertakers are complying with their obligations under section 11 of the 1975 Act (recording of water levels etc.);

(ii)particulars of any directions given by the engineer as to the intervals at which, or the manner in which information is to be recorded under section 11 of the 1975 Act;

(iii)details of any recommendations involving alterations or additions to works or the installation of instruments or gauges for measuring leakage, deflections, settlement, uplift, pore pressures or similar matters;

(iv)details of any movement of the surrounding land observed which might affect the stability of the reservoir;

(v)findings as to the adequacy and condition of the waste weir or overflow and any channels connected with it;

(vi)a statement of any alterations the engineer has observed which affect the level to which water may be stored or to the level of the overflow sills since construction or since last inspection;

(vii)a statement as to the adequacy of the margin between dam(s), reservoir walls or embankments level and overflow level;

(viii)findings as to the efficiency of the scour pipe or discharge culvert or other means of lowering the level of the water in, and any means of controlling the inflow of water to, the reservoir.

In these forms of reports, square brackets and the words within them are not to be included where they are inappropriate.

Regulation 12

SCHEDULE 6E+WDirections

Commencement Information

I16Sch. 6 in force at 30.7.2013, see reg. 1(b)

The italicised letters in the forms of directions in this Schedule indicate the information to be included as follows—

(a)name of engineer;

(b)address of engineer;

(c)name of panel to which engineer is appointed;

(d)name of undertakers;

(e)name of reservoir;

(f)situation of reservoir, with sufficient detail to identify it (including the National Grid Reference of the approximate centre of the reservoir);

(g)level above Ordnance Datum to which water may be filled, excluding the allowance made for flood conditions;

(h)level above Ordnance Datum to which water may be stored, excluding the allowance made for flood storage;

(i)date of preliminary or interim certificate as appropriate;

(j)conditions subject to which the reservoir may be filled with water or water may be stored up to the level specified;

(k)date of report, certificate, direction as appropriate;

(l)date of completion of works;

(m)period recommended in the report within which the next inspection should be made;

(n)date of inspecting engineer’s report;

(o)name of inspecting engineer;

(p)name of referee;

(q)address of referee;

(r)date of referee’s decision;

(s)name of person appointing referee;

(t)volume of water that makes a reservoir a large raised reservoir under the 1975 Act.

In these forms of directions, square brackets and the words within them are not to be included where they are inappropriate.

Regulation 13

SCHEDULE 7E+WInformation to be given in a notice under section 21(1) of the 1975 Act

1.  Name and address of undertakers serving notice.E+W

Commencement Information

I17Sch. 7 para. 1 in force at 30.7.2013, see reg. 1(b)

2.  Name and situation of reservoir.E+W

Commencement Information

I18Sch. 7 para. 2 in force at 30.7.2013, see reg. 1(b)

3.  National grid reference of approximate centre of the reservoir.E+W

Commencement Information

I19Sch. 7 para. 3 in force at 30.7.2013, see reg. 1(b)

4.  Whether the undertakers intend—E+W

(a)to construct a new large raised reservoir; or

(b)to bring a large raised reservoir back into use after that use has been abandoned.

Commencement Information

I20Sch. 7 para. 4 in force at 30.7.2013, see reg. 1(b)

5.  The date when it is intended that construction will commence or the date when it is intended the reservoir will be brought back into use, as the case may be.E+W

Commencement Information

I21Sch. 7 para. 5 in force at 30.7.2013, see reg. 1(b)

6.  Name and address of the construction engineer or, in the case of re-use, of the engineer appointed for the purposes of section 9 of the 1975 Act.E+W

Commencement Information

I22Sch. 7 para. 6 in force at 30.7.2013, see reg. 1(b)

7.  The following information about the reservoir as it will be when constructed, or brought back into use as proposed—E+W

(a)category (i.e. whether impounding or non-impounding);

(b)date(s) or approximate date(s) of completion of the dam(s), reservoir walls or embankments(s);

(c)construction of the dam(s), reservoir walls or embankments(s) (i.e. whether constructed of earth, rockfill, gravity, buttress or by other means);

(d)maximum height of the dam(s), reservoir walls or embankment(s) (in metres), measured from the lowest natural level of the surrounding land adjacent to it, to the top of the dam(s), reservoir walls or embankments, excluding the height of the wave wall;

(e)the height of the dam(s), reservoir walls or embankment(s) (in metres) measured from the lowest natural level of the surrounding land adjacent to it to top water level;

(f)capacity (in cubic metres), measured from the lowest natural level of the surrounding land adjacent to it to top water level;

(g)the water surface area at top water level (in square metres or square kilometres).

Commencement Information

I23Sch. 7 para. 7 in force at 30.7.2013, see reg. 1(b)

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill