  1. Introductory Text

  2. 1.Citation and commencement

  3. 2.Interpretation

  4. 3.Development consent etc granted by the Order

  5. 4.Power to maintain authorised project

  6. 5.Operation of electricity generating station

  7. 6.Benefit of the Order

  8. 7.Public rights of navigation

  9. 8.Abatement of works abandoned or decayed

  10. 9.Deemed marine licences under the Marine and Coastal Access Act 2009

  11. 10.Saving for Trinity House

  12. 11.Crown rights

  13. 12.Certification of plans etc

  14. 13.Arbitration

  15. Signature

    1. SCHEDULE 1

      Authorised project

      1. PART 1 Authorised development

        1. 1.A nationally significant infrastructure project as defined in sections 14...

        2. 2.The grid coordinates for the Order limits are specified below—...

      2. PART 2 Ancillary works

      3. PART 3 Requirements

        1. 1.Time limits

        2. 2.Detailed design parameters

        3. 3.(1) Subject to sub-paragraph (2), no wind turbine generator forming...

        4. 4.(1) The total number of offshore substations forming part of...

        5. 5.The total length of the cables comprising Work No. 1(b)...

        6. 6.(1) Each steel monopile foundation forming part of the authorised...

        7. 7.Lighting

        8. 8.Decommissioning

        9. 9.Navigational radar scheme at the Port of Liverpool

        10. 10.Air traffic services at Warton Aerodrome

        11. 11.Primary surveillance radars at Lytham St Annes and Great Dun Fell

        12. 12.Air traffic services at Liverpool John Lennon Airport

        13. 13.Community liaison

    2. SCHEDULE 2

      Deemed marine licence under the Marine and Coastal Access Act 2009 – generation assets

      1. PART 1 Licensed marine activities

        1. 1.(1) In this licence— “the 2004 Act” means the Energy...

        2. 2.Details of licensed marine activities

        3. 3.The grid coordinates for the authorised scheme are specified below—...

        4. 4.This licence shall remain in force until the authorised scheme...

        5. 5.The provisions of section 72 of the 2009 Act shall...

        6. 6.Where the words ‘unless otherwise agreed’ or ‘unless otherwise stated’...

      2. PART 2 Conditions

        1. 1.Design parameters

        2. 2.The total length of the cables comprising Work No. 1(b)...

        3. 3.(1) Each steel monopile foundation forming part of the authorised...

        4. 4.Notifications and inspections

        5. 5.Navigational practice, safety and emergency response

        6. 6.Aids to navigation

        7. 7.(1) The undertaker must colour all structures yellow from at...

        8. 8.Chemicals, drilling and debris

        9. 9.Force majeure

        10. 10.Pre-construction plans and documentation

        11. 11.(1) Each programme, statement, plan, protocol or scheme required to...

        12. 12.Reporting of engaged agents, contractors and vessels

        13. 13.Equipment and operation of vessels engaged in licensed activities

        14. 14.Pre-construction monitoring

        15. 15.Construction monitoring

        16. 16.Post construction surveys

        17. 17.Piling restrictions

    3. SCHEDULE 3

      Deemed marine licence under the Marine and Coastal Access Act 2009 – transmission assets

      1. PART 1 Licensed marine activities

        1. 1.(1) In this licence— “the 2004 Act” means the Energy...

        2. 2.Details of licensed marine activities

        3. 3.The grid coordinates for the authorised scheme are specified below—...

        4. 4.This licence shall remain in force until the authorised scheme...

        5. 5.The provisions of section 72 of the 2009 Act shall...

        6. 6.Where the words ‘unless otherwise agreed’ or ‘unless otherwise stated’...

      2. PART 2 Conditions

        1. 1.Design parameters

        2. 2.The total length of the cables comprising Work No. 3...

        3. 3.(1) Each steel monopile foundation forming part of the authorised...

        4. 4.Notifications and inspections

        5. 5.Navigational practice, safety and emergency response

        6. 6.Aids to navigation

        7. 7.The undertaker must colour all structures yellow from at least...

        8. 8.Chemicals, drilling and debris

        9. 9.Force majeure

        10. 10.Pre-construction plans and documentation

        11. 11.(1) Each programme, statement, plan, protocol or scheme required to...

        12. 12.Reporting of engaged agents, contractors and vessels

        13. 13.Equipment and operation of vessels engaged in licensed activities

        14. 14.Pre-construction monitoring

        15. 15.Construction monitoring

        16. 16.Post construction surveys

        17. 17.Piling restrictions

  16. Explanatory Note

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill