1.  In this Schedule—

“environmental statement” means the statement submitted under regulation 5(2)(a) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009(1), together with the shadow Habitats Regulations Assessment report, statements of common ground concluded with Natural England, the MMO and the Environment Agency and the following documents submitted by the undertaker and certified under article 55 (certification of plans etc)—

ReferenceTitle
EX 3.1Able Humber Port Northern Area Planning Committee Meeting Notes Feb 2012
EX 7.7AMEP Material Management Plan
EX 7.8Able Marine Energy Park Dredging Strategy
EX 8.5Validation of 3D Flow and Sediment Models used for Assessment of Impacts of AMEP on Fine Sediment Transport
EX 8.6Maintenance Dredge Variability
EX 8.7AModelling of Final Quay Design (Supplement to Annex 8.1 of the ES)
EX 8.8Update to Longer Term Morphology Predictions in the Region of the Centrica and E.ON intakes and outfalls
EX 8.9Historical Review of Morphological Change North of HIT (2001–2010)
EX 8.10Long-term Morphological Change at Embayment South of Quay
EX 8.11Water Framework Directive – Compensation Site
EX 8.12Water Framework Directive – Project Wide
EX 8.12AWater Framework Directive
EX 8.13IOTA Dredge Appropriate Assessment
EX 8.14Hydraulic & Sediment Regime – Piled Structures
EX 8.15Effect of Moored Vessels on Flows
EX 8.16Chapter 8 Signposting Document
EX 9.7Assessment of the effects of relocations of the E.ON and Centrica outfalls on thermal recirculation
EX 10.4Effect of Dredged Material Disposal on 1) Subtidal and Intertidal Features and 2) Aquatic Ecology
EX 10.5Supporting Information on Harbour Porpoises in the Humber Estuary
EX 10.6Impact of Berthing Pocket Construction
EX 10.7Soft Start and Seals
EX 10.8Disposal Site Characterisation and Impact Assessment
EX 10.9Environmental Management and Monitoring Plan: 1. Marine Works (Draft)
EX 11.14Biotopes of the Intertidal and Subtidal Sediments around the AMEP site, in the Humber Estuary
EX 11.16Assessment Update for Breeding Birds
EX 11.17AMEP Vascular Plant Surveys
EX 11.18Sensitive Months for Birds Using Intertidal
EX 11.19AMEP Bat Surveys Supplementary Note
EX 11.20Draft Great Crested Newts Licence Application – acknowledgement of receipt
EX 11.22The Impact of SPMTs and Cranes on the Operational Buffer
EX 11.23Immediate Habitat Losses Within the Designated Site
EX 11.24Medium and Long Term Losses Within the Designated Site
EX 11.26Pumping Station
EX 11.26AWater Vole Mitigation
EX 11.27Killingholme Phase 2 Survey
EX 11.27ABreeding Bird Mitigation
EX 11.28Great Crested Newt Survey (2006)
EX 11.29Water Vole Survey (2009)
EX 11.30Location of Replacement Ponds for Great Crested Newts
EX 11.31M456 Invertebrate Survey
EX 11.32Draft Environmental Monitoring and Management Plan: 2. Terrestrial Habitat – Killingholme
EX 11.33In combination Effects on Curlew
EX 13.2Addendum to Flood Risk Assessment
EX 14.4Simulation Videos and Stills
EX 15.3A160 Killingholme Humber Port Access, Stage 1 Road Safety Audit
EX 15.4A160 Killingholme Humber Port Access, Stage 1 Road Safety Audit Designer’s Response
EX 15.5Additional Junction RSA
EX 19.1Lighting Lux Plans
EX 20.3Additional Landscape Masterplan
EX 28.1Compensation Site Interim Report on Detailed Design
EX 28.2Old Little Humber Farm: Wet Grassland Creation, Management and Monitoring Plan
EX 28.3Final Compensation Proposals, Parts 1–10
EX 31.5Re-Use of In Situ Material at CCS (Inc. Cherry Cobb Sands Phase 2 Site Investigation)
EX 31.5AFactual Report on Geo–Environmental Ground Investigation, Cherry Cobb Sands
EX 34.2An Assessment of Temporal Variation of Benthic Invertebrate Communities in the Humber Estuary
EX 35.12Farmland Disturbance at Cherry Cobb Sands
EX 35.13Badger Bait–Marking Survey
EX 35.14Cherry Cobb Sands Compensation Site: Bird Survey Results August 2010 to April 2011
EX 36.2North Bank Flood Defence Crest Height
EX 36.3Residual Flood Risk to Property on North Bank
EX 36.4Embankment Inspection and Maintenance Report
EX 44.1Supplementary In-Combination Assessment
EX 44.2Addendum to EX 44.1

; and

“the water framework directive” means Directive 2000/60/EC of the European Parliament and of the Council of 23rd October 2010 establishing a framework for Community action in the field of water policy(2).

(2)

O.J. No L327, 22.12.2000, p. 1-73.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill