Chwilio Deddfwriaeth

The Network Rail (Norton Bridge Area Improvements) Order 2014

 Help about what version

Pa Fersiwn

  • Y Diweddaraf sydd Ar Gael (Diwygiedig)
  • Gwreiddiol (a wnaed Fel)

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol). This item of legislation is currently only available in its original format.

SCHEDULES

Article 2

SCHEDULE 1AUTHORISED DEVELOPMENT

A nationally significant infrastructure project as defined in sections 14 and 25 of the 2008 Act comprising—

  • In the county of Staffordshire and the Borough of Stafford

    • Work No. 1 — A two track railway commencing at a junction with the existing West Coast Main Line railway at Little Bridgeford Junction, crossing over the diverted River Sow by means of Underbridge 1 (which is to be widened), continuing on embankment adjacent to a culvert proposed to be infilled under the existing West Coast Main Line (Underbridge 1A), then continuing on embankment over the diverted Meece Brook (Work No. 6) by means of Underbridge 2 and then passing into deep cutting to Searchlight Lane Junction, including cess and crest drainage outfalls into the diverted River Sow from the south and north (at Underbridge 1) and the diverted Meece Brook from the north (at Underbridge 2); an attenuation pond at Underbridge 2 including outfall headwall structure and parallel overflow spillway; passing under Work No. 7 at Overbridge 3; mitigation earthworks bunds; and diversion and alteration works to two distribution electricity services; then a single track railway running in cutting, passing under Work No. 11 at Overbridge 10A, then running onto embankment and crossing the diverted Meece Brook (Work No. 13) at Underbridge 11 (including cess and crest drainage from the south and outfalls into the diverted Meece Brook via an attenuation pond including outfall headwall structure and parallel overflow spillway) then in cutting past a further attenuation pool and outfalls into Meece Brook from the north, and terminating at a junction with the West Coast Main Line adjacent to Heamies Bridge at the northern end of the works including mitigation earthwork bunds along the alignment and all associated items that comprise a railway including track, cess drainage, combined troughing and walking route, overhead line electrification (new and alteration to existing), signalling, telecommunications and cutting or embankment earthworks, maintenance access track, crest drainage (where on sidelong ground) and boundary fencing;

    • Work No. 8 — A two track railway commencing at a junction with Work No. 1 (Searchlight Lane Junction) and terminating at the Yarnfield Junction with the Norton Bridge to Stone branch railway line, initially in cutting, then on embankment, crossing the West Coast Main Line by means of Intersection Bridge 5 and the diverted Meece Brook (Work No. 15) by means of Underbridge 6, then in cutting passing under the diverted Meece Road (Work No. 12) by means of Overbridge 7, including a widening of existing Underbridge 8 the replacement of the existing foot crossing at Mid Norton (Chebsey Footpath 10) with a new footbridge (FB9) including track, cess drainage, combined troughing and walking route, overhead line electrification (new and alteration to existing), signalling, telecommunications, cutting and embankment earthworks, a maintenance access track, crest drainage (where on sidelong ground) and boundary fencing; and cess drainage outfalls into the diverted Meece Brook from the east and west, via attenuation ponds including outfall headwall structure and parallel overflow spillways, adjacent to the Underbridges 6 and 6A river diversion, with access tracks to both attenuation ponds from the existing B5026; and cess drainage outfalls into the unnamed watercourse at Underbridge 8, from the east; and mitigation earthwork bunds along the alignment;

Associated development comprising—

  • In the county of Staffordshire and the Borough of Stafford

    • Work No. 2 — The formation of a right hand turn lane on the A5013, north of Great Bridgeford, and the re-modelling of its junction with Chebsey Lane, including the diversion and protection of telecommunications cables;

    • Work No. 3 — The remodelling of the junction of the A5013 with Chebsey Lane, including a widening of Chebsey Lane up to the bellmouth entrance to the temporary construction compound, a passing place and the diversion and protection of telecommunications cables, followed by a reinstatement to the existing width of the widened lane and remodelled junction;

    • Work No. 4 — A compacted stone access track with passing places from Chebsey Lane to a fenced compound adjacent to the new railway (Work No. 1) at Little Bridgeford Junction, with parking facilities, including the diversion/protection of a water main in the area of the fenced compound;

    • Work No. 5 — A diversion of the River Sow and a widening of the existing West Coast Main Line bridge (Underbridge 1), including earthworks on the southern side and cutting back the existing river cliff;

    • Work No. 6 — A diversion of the Meece Brook to provide a perpendicular crossing of the proposed railway by means of Underbridge 2;

    • Work No. 7 — A diversion of Searchlight Lane with the diverted road being carried over the proposed railway cutting, including new highway drainage, passing places and the diversion of existing telecommunications and water services along the new alignment, the stopping up of the old alignment where no longer required, the provision of access to adjacent land on both sides of the diverted road to the west of Overbridge 3 including parking facilities and the provision of access to adjacent land on the south side of the diverted road to the east of Overbridge 3;

    • Work No. 9 — A surfaced access track commencing at a compound adjacent to the new railway (Work No. 1) at Searchlight Lane junction and terminating near the diverted B5026 (Work No. 11). The compound will include a new Distribution Network Operator power supply, welfare facilities, parking facilities and water supply, a principal supply point and relocatable equipment building;

    • Work No. 10 — A remodelling of the junction of Scamnell Lane with the diverted B5026 (Work No. 11), including new highway drainage and diversion of an existing water main and a new field access on the east side of Scamnell Lane;

    • Work No. 11 — A diversion of the existing B5026 passing above existing ground level, in a false cutting formed by mitigation earthworks bunds, over Work No. 1 by means of Overbridge 10A, continuing east over the existing West Coast Main Line by means of railway Overbridge 5A, then running on embankment, shared with the railway, over the diverted Meece Brook (Work No. 15) by means of Underbridge 6A, then continuing on embankment, with mitigation earthwork bunds, again forming a cutting, and terminating at a new roundabout junction with the diverted Meece Road (Work No. 12), including access to adjacent land on the north side, to the west of bridge 10A, access to adjacent land on the north side of the road to the west of the West Coast Main Line Overbridge 5A (opposite the new access road junction to Searchlight Lane Junction compound (Work No. 9) and access to adjacent land in the south verge on the approach to Meece Road, the diversion to include new highway drainage and partial diversion of existing electricity, telecommunications and water services, and a stopping up of the old alignment where no longer required;

    • Work No. 12 — A diversion of the existing Meece Road including Overbridge 7 carrying the new highway over the proposed cutting and new highway drainage and diversion of an existing telecommunications service along the new alignment and a stopping up of the old alignment where no longer required. Access to adjacent land will also be provided in the western verge between Overbridge 7 and the existing Meece Road roundabout;

    • Work No. 13 — A diversion of the existing Meece Brook to provide a perpendicular crossing of the proposed railway (Work No. 1) at Underbridge 11 and to move the current channel away from the toe of the proposed railway embankment on the west side;

    • Work No. 14 — A diversion of Chebsey Footpath 11 to follow the proposed boundary on the west side of Work No 1 to include a new pedestrian bridge over Meece Brook, passing onto Network Rail property continuing along the access track for the attenuation pond; then passing onto the proposed B5026 (Work No. 11), crossing bridge 10A before leaving the highway alignment turning down the Searchlight Lane maintenance compound access road and crossing over, running along the crest of a mitigation bund and then running parallel to the West Coast Main Line Intersection Bridge 5 before tying back into the existing alignment on the existing B5026 opposite the end of Station Road;

    • Work No. 15 — A diversion of the existing Meece Brook to provide a perpendicular crossing of the proposed railway at Underbridges 6 and 6A;

    • Work No. 16 — A compacted stone access track with passing places, running from the existing layby on the B5026 to a fenced compound adjacent to the new railway (Work No 8) at Yarnfield Junction, to include a new Distribution Network Operator supply;

    • Work No. 17 — Diversion (approximately 610 metres in length) of high pressure gas pipe-line (Feeder No. 21), beneath the railway cutting to the south of Searchlight Lane;

    • Work No. 18 — Diversion (approximately 266 metres in length) of high pressure gas pipe-line (Feeder No. 21), parallel to the railway cutting to the north of Searchlight Lane;

    • Work No. 19A — Diversion (approximately 488 metres in length) of high pressure gas pipeline (Feeder No. 4) by horizontal directional drilling beneath the railway in cutting in the vicinity of Searchlight Lane Junction;

    • Work No. 19B —Diversion (approximately 426 metres in length) of high pressure gas pipeline (Feeder No.4) by opencut or microtunnelling beneath the railway in cutting in the vicinity of Searchlight Lane Junction;

    • Work No. 20 — Diversion (approximately 680 metres in length) of fuel pipe-line beneath the railway in cutting in the vicinity of Searchlight Lane Junction,

    • and such further associated development within Order limits as may be necessary or expedient for the purposes of or in connection with the construction of those works or any of them consisting of—

      (a)

      demolition, site clearance, devegetation, remediation, the erection of contractors’ works compounds, the erection of site offices and the erection of fencing to site boundaries;

      (b)

      electrical equipment and signalling works;

      (c)

      ramps, means of access, footpaths and bridleways;

      (d)

      embankments, viaducts, aprons, abutments, shafts, foundations, retaining walls, drainage, wing walls, fencing and culverts;

      (e)

      works to alter the position of apparatus, including mains, sewers, drains and cables;

      (f)

      works to alter the course of, or that otherwise interfere with, a watercourse other than a navigable watercourse;

      (g)

      landscaping and habitat replacement (including replacement bat accommodation) and other works to mitigate any adverse effects of the construction, maintenance or operation of the authorised development;

      (h)

      works for the benefit or protection of land affected by the authorised development;

      (i)

      works required for the strengthening, improvement, maintenance, or reconstruction of any streets and the grubbing up of any former street;

      (j)

      working sites and works of demolition; and

      (k)

      such other work as may be necessary or expedient for the purposes of or in connection with the construction of those works and which falls within the scope of the environmental impact assessment recorded in the Environmental Statement.

Article 4

SCHEDULE 2REQUIREMENTS

Interpretation

1.  In this Schedule—

“CEMP” means the Construction Environmental Management Plan to be submitted to and approved by the relevant planning authority, a draft of which is included in Appendix 6, Volume 2 (Folder 2) of the Environmental Statement; and

“Staffordshire Alliance” means the alliance formed by Network Rail with its contractors to progress and implement the works authorised by this Order.

In accordance with approved details

2.  The authorised development must be carried out in accordance with the design drawings subject to such non-material amendments as are approved in writing by the relevant planning authority; provided that such approval is not given except where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the Environmental Statement.

Construction Environmental Management Plan

3.—(1) The authorised development must not be commenced until the following aspects of the CEMP have been submitted to and approved by the relevant planning authority.

(2) The CEMP must incorporate the findings and recommendations of the Environmental Statement and the design brief.

(3) The authorised development must be carried out in accordance with the CEMP.

(4) The CEMP must incorporate the following plans and programmes—

(a)External Communications Management Plan—

(i)External communications programme;

(ii)External complaints procedure;

(b)Pollution Incident Prevention and Control Plan—

(i)Identification of potential pollution source, pathway and receptors;

(ii)Control measures to prevent pollution release to water, ground and air (including detail of the surface/ground water management plan);

(iii)Control measures for encountering potential contaminated land;

(iv)Monitoring regime;

(v)Emergency environmental incident response plan;

(vi)Incident investigation and reporting;

(vii)Review/change management and stakeholder consultation;

(c)Site Waste Management Plan—

(i)Management of excavated material and other waste arising;

(ii)Waste minimisation;

(iii)Material re-use;

(d)Materials Management Plan—

(i)Material classification;

(ii)On site re-use criteria and measures;

(iii)Hazardous waste management;

(iv)Disposal measures;

(e)Traffic Management Plan—

(i)Roles and responsibilities;

(ii)Permitted and banned construction traffic routes and the mechanisms to be put in place by Network Rail and its contractors to enforce their compliance;

(iii)Procedures for working on the highway;

(iv)Road signage plans;

(v)Monitoring and reporting measures;

(vi)Access strategy and traffic management at the access off the roadside lay-by (off the B5026 between the roundabout and Stone);

(vii)The interfaces between the haul road and public highway (the crossing points at Searchlight Lane and the B5026);

(f)Travel Plan—

(i)Measures to manage contractor travel to the site compounds such as on-site or remote car parking management, car sharing, works shuttle bus etc.;

(ii)Mechanisms for reviewing and monitoring;

(g)Nuisance Management Plan (Noise, Vibration, Dust, Air Pollution and Lighting)—

(i)Roles and responsibilities;

(ii)Specific risk assessment – identification of sensitive receptors and predicted impacts;

(iii)Standards and codes of practice;

(iv)Specific control and mitigation measures;

(v)Details of any section 61 consent;

(vi)Monitoring regime – dust and noise;

(vii)Review/change management and stakeholder consultation;

(viii)Notification of working hours;

(h)Landscape and Ecology Management Plan (“LEMP”)—

(i)Roles and responsibilities;

(ii)Protection controls for retained landscape features, habitats and species;

(iii)Controls for protection of Doxey and Tillington Marshes SSSI;

(iv)Detailed mitigation for Meece Brook and Yelds Rough SBI;

(v)Detailed plans and specifications for ecological and landscape mitigation;

(vi)5 year establishment, maintenance and monitoring plans for planting, ecology and geomorphology;

(vii)Aftercare and maintenance plans for habitats on Network Rail land (post 5 years);

(viii)Aftercare and maintenance guidelines for habitats on Staffordshire County Council highways land (post 5 years);

(ix)Aftercare and maintenance guidelines for habitats on other land (post 5 years);

(x)Habitat and protected species monitoring plans (to include scope, methods and reporting mechanism);

(xi)Bat roost replacement plans;

(xii)Soil Management Plan interface strategy;

(xiii)Change control, review and consultation processes;

(xiv)Tree survey validation and tree protection plan in accordance with BS 5837: 2012 (trees in relation to design, demolition and construction);

(i)Archaeological management plan—

(i)Roles and responsibilities;

(ii)Review/change management and stakeholder consultation protocols;

(iii)Procedures for dealing with unexpected significant archaeological discoveries;

(iv)Programme of archaeological mitigation;

(v)Post excavation reporting and archiving;

(j)Soil Management Plan—

(i)Soil resource survey;

(ii)Soil resource plan – including protection of in situ soils, handling and storage codes of practice;

(iii)On site re-use criteria and measures;

(iv)Hazardous waste management;

(v)Strategy for interface with LEMP.

(5) The CEMP must require—

(a)adherence to the relevant Environment Agency Pollution Prevention Guidelines PPG1, PPG5, PPG6, PPG21 and PPG22; and

(b)adherence to working hours of 7am to 7pm on Mondays to Fridays and 7am to 1pm on Saturdays except that:

(i)work on or adjacent to the operational railway may be carried out at other times if it would otherwise interfere with the operation of the railway; and

(ii)work may be carried out on Sundays, Bank Holidays and Public Holidays and after 1pm on Saturdays after prior notification to the relevant planning authority and affected residents in accordance with a notification procedure agreed by the relevant planning authority.

Landscaping and habitat replacement

4.—(1) No authorised development may commence in any geographical area, those areas to be identified on a plan previously submitted to the relevant planning authority, unless and until a written landscaping and habitat replacement scheme for that area has been submitted to and approved by the relevant planning authority.

(2) The submitted scheme must incorporate—

(a)the mitigation measures described in section 8 (Mitigation) of Technical Appendix Report 8 (Landscape and Visual Technical Report) to Volume 3 of the Environmental Statement and in the design brief; and

(b)details of—

(i)location, number, species, size, planting density and planting method and protection of any proposed planting;

(ii)cultivation, other amelioration where appropriate, importing of materials and other operations to ensure plant establishment;

(iii)implementation timetables for all landscaping and habitat replacement;

(iv)temporary fencing that complies with best practice to protect trees and hedgerows adjacent to the works; and

(v)a 5 year aftercare programme including weed control and pruning, if required, to promote establishment and timely rectification of defects.

Implementation and maintenance of landscaping and habitat replacement

5.—(1) All landscaping and habitat replacement work must be carried out in accordance with the scheme and implementation timetable approved under requirement 4.

(2) Any tree or shrub or other habitat replacement planted as part of an approved landscaping and habitat replacement scheme or ecological management plan that, within a period of 5 years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, or has failed to become established, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless the relevant planning authority gives consent to any variation.

Highway works

6.  Prior to and during the carrying out of any highway work and during any defects period applicable to that work, Network Rail must afford the highway authority the opportunity to inspect, monitor, survey, and comment upon the carrying out of the work and the remedying of any defects resulting from the work and to approve the standard to which such work (including the remedying of any defects) is carried out, by—

(a)using the quality processes of the Staffordshire Alliance, as agreed from time to time by Network Rail, including inspection and test plans for all elements of the works under which the highway authority is to be an inspection authority;

(b)providing shared working facilities, including access to welfare and office facilities, for the highway authority at the Chebsey Lane works compound and the B5026/Meece Road works compound;

(c)giving the highway authority access to the documents in the Staffordshire Alliance’s electronic document management system that relate to the highway works authorised by this Order; and

(d)allowing the highway authority such access to any highway work as it may reasonably require.

7.  Network Rail must carry out stage 2, 3 and 4 road safety audits of the highway works authorised by this Order in accordance with the Standard HD 19/03 of the Department for Transport’s Design Manual for Roads and Bridges or in accordance with any standard that supersedes that Standard and must remedy to the reasonable satisfaction of the highway authority any defects identified in any such road safety audits.

Alteration, reconstruction or replacement of buildings or bridges

8.  No alteration, reconstruction or replacement of a building or bridge is to be carried out under article 5 (maintenance of authorised development) except in accordance with plans and specifications approved by the relevant planning authority.

Amendments to approved details

9.  With respect to any requirement which requires the authorised development to be carried out in accordance with details approved by the relevant planning authority, the approved details are taken to include any amendments that may subsequently be approved in writing by the relevant planning authority.

Article 8

SCHEDULE 3STREETS SUBJECT TO ALTERATION OF LAYOUT

In the County of Staffordshire and the Borough of Stafford

(1)

Street subject to alteration of layout

(2)

Description of alteration

B5026Construction of turning head where B5026 is to be stopped up at point W on the street plans
Station Road/B5026Change in road markings/right of way designation between points X and Y on the street plans

Article 9

SCHEDULE 4STREETS SUBJECT TO STREET WORKS

(1)

Area

(2)

Street subject to street works

County of Staffordshire, Borough of Stafford

Eccleshall Road A5013

Chebsey Lane

Worston Lane

Searchlight Lane

Station Road

Scamnell Lane

Stone Road B5026

Eccleshall Road B5026

Meece Road

Article 11

SCHEDULE 5STREETS TO BE STOPPED UP

(1)

Area

(2)

Street to be stopped up

(3)

Extent of stopping up

(4)

New street to be substituted

County of Staffordshire, Borough of StaffordB5026 (Stone Road)Stopping up of highway between points R and S and V and WProvision of new highway between points M and Q
County of Staffordshire, Borough of StaffordSearchlight LaneStopping up of Searchlight Lane between points H and KProvision of new access over highway between points H and L
County of Staffordshire, Borough of StaffordMeece RoadStopping up of Meece Road between points AA and Z and BA and CAProvision of new access over highway between points AA and EA
County of Staffordshire, Borough of StaffordFootpath 11Stopping up of Chebsey Footpath 11 between points 1 and 8New footpath to be created between points 1 and 8 via points 9A to 22
County of Staffordshire, Borough of StaffordFootpath 10Stopping up of Chebsey Footpath 10 between points 26, 27, 28 and 29New footpath to be created between points 26 to 29 via point 30, then over new footbridge and then via point 31

Article 17

SCHEDULE 6REPLACEMENT AND CLOSURE OF LEVEL CROSSING

(1)

Area

(2)

Level crossing to be discontinued

(3)

Street to be stopped up

(4)

New street to be substituted

County of Staffordshire, Borough of StaffordFootpath 10 across the Stone railway line at Mid NortonBetween points 27 and 28 on the street plansA new footbridge 15 metres from existing level crossing

Article 22

SCHEDULE 7LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED

PART 1NETWORK RAIL

(1)

Number of land shown on land plans

(2)

Purpose for which rights may be acquired

11a, 29a, 30a, 42, 52a, 55, 130a, 141, 156a, 170, 174, 175, 178a and 211Vehicular access
210a and 212Vehicular access and power supply

PART 2NATIONAL GRID

(1)

Number of land shown on land plans

(2)

Purpose for which rights may be acquired

30, 30a, 33, 34, 37, 38, 56, 58, 59, 61, 65, 67 and 71Construction and maintenance of pipe-line

Article 22

SCHEDULE 8MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

Compensation enactments

1.  The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right, and in the case of the imposition of a restrictive covenant, as they apply as respects compensation on the compulsory purchase of land and interests in land.

2.—(1) Without limitation on the scope of paragraph 1, the 1973 Act has effect subject to the modifications set out in sub-paragraphs (2) and (3).

(2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 4—

(a)for the words “land is acquired or taken” there are substituted the words “a right or restrictive covenant over land is purchased from or imposed on”; and

(b)for the words “acquired or taken from him” there are substituted the words “over which the right is exercisable or the restrictive covenant enforceable”.

(3) In section 58(1) (determination of material detriment where part of house etc. proposed for compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted by paragraph 5—

(a)for the word “part” in paragraphs (a) and (b) there are substituted the words “a right over or restrictive covenant affecting land consisting”;

(b)for the word “severance” there are substituted the words “right or restrictive covenant over or affecting the whole of the house, building or manufactory or of the house and the park or garden”;

(c)for the words “part proposed” there are substituted the words “right or restrictive covenant proposed”; and

(d)for the words “part is” there are substituted the words “right or restrictive covenant is”.

Application of the 1965 Act

3.—(1) The 1965 Act has effect with the modifications necessary to make it apply to the compulsory acquisition under this Order of a right by the creation of a new right, or to the imposition under this Order of a restrictive covenant, as it applies to the compulsory acquisition under this Order of land, so that, in appropriate contexts, references in that Act to land are read (according to the requirements of the particular context) as referring to, or as including references to—

(a)the right acquired or to be acquired or the restrictive covenant imposed or to be imposed; or

(b)the land over which the right is or is to be exercisable.

(2) Without limitation on the scope of sub-paragraph (1), Part 1 of the 1965 Act applies in relation to the compulsory acquisition under this Order of a right by the creation of a new right or in relation to the imposition of a restrictive covenant with the modifications specified in the following provisions of this Schedule.

4.  For section 7 of the 1965 Act (measure of compensation) there is substituted the following section—

7.  In assessing the compensation to be paid by the acquiring authority under this Act, regard is to be had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right or the imposition of the covenant but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act..

5.  For section 8 of the 1965 Act (provisions as to divided land) there is substituted the following section—

8.(1) Where in consequence of the service on a person under section 5 of this Act of a notice to treat in respect of a right over land consisting of a house, building or manufactory or of a park or garden belonging to a house (“the relevant land”)—

(a)a question of disputed compensation in respect of the purchase of the right or the imposition of the restrictive covenant would apart from this section fall to be determined by the Upper Tribunal (“the tribunal”); and

(b)before the tribunal has determined that question the tribunal is satisfied that the person has an interest in the whole of the relevant land and is able and willing to sell that interest and—

(i)where that land consists of a house, building or manufactory, that the right cannot be purchased or the restrictive covenant imposed without material detriment to that land; or

(ii)where that land consists of such a park or garden, that the right cannot be purchased or the restrictive covenant imposed without seriously affecting the amenity or convenience of the house to which that land belongs,

the Network Rail (Norton Bridge Area Improvements) Order 2014(1) (“the Order”), in relation to that person, ceases to authorise the purchase of the right and is deemed to authorise the purchase of that person’s interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice is deemed to have been served in respect of that interest on such date as the tribunal directs.

(2) Any question as to the extent of the land in which the Order is deemed to authorise the purchase of an interest by virtue of subsection (1) of this section is to be determined by the tribunal.

(3) Where in consequence of a determination of the tribunal that it is satisfied as mentioned in subsection (1) of this section the Order is deemed by virtue of that subsection to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of 6 weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the authority to withdraw the notice..

6.  The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—

(a)section 9(4) (failure by owners to convey);

(b)paragraph 10(3) of Schedule 1 (owners under incapacity);

(c)paragraph 2(3) of Schedule 2 (absent and untraced owners); and

(d)paragraphs 2(3) and 7(2) of Schedule 4 (common land);

are modified so as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.

7.  Section 11 of the 1965 Act (powers of entry) is modified so as to secure that, as from the date on which the acquiring authority has served notice to treat in respect of any right it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant (which is deemed for this purpose to have been created on the date of service of the notice); and sections 12 (penalty for unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act are modified correspondingly.

8.  Section 20 of the 1965 Act (protection for interests of tenants at will, etc.) applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.

9.  Section 22 of the 1965 Act (interests omitted from purchase) is modified so as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired or to enforce the restrictive covenant imposed, subject to compliance with that section as respects compensation.

Articles 28 and 29

SCHEDULE 9LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

PART 1NETWORK RAIL

In the County of Staffordshire and the Borough of Stafford

(1)

Number of land shown on land plans

(2)

Purpose for which temporary possession may be taken

(3)

Relevant part of the authorised development

(4)

Element of Work in respect of which land is not required to be re-instated

1

A5013 signage

Access to works

Work No.2

Work Nos. 17, 18, 19A and 19B

2

A5013 improvement

Access to works

Work No.2

Work Nos. 17, 18, 19A and 19B

4Storage and overspill parkingWork Nos. 2 and 3
5Road wideningWork No.3
6Access to worksWork No.3
7

Vehicle passing place

Access to works

Work No.3

Work Nos. 17, 18, 19A and 19B

8

Works compound

Access to works

Work Nos. 3 and 4

Work Nos. 17, 18, 19A and 19B

9For West Coast Main Line connectionWork No.1
11a

Part of compound

Access to works

Work No.4

Work Nos. 17, 18, 19A and 19B

Access for maintenance vehicles
12, 14, 21River diversionWork No.5Diverted river and earthworks
13

Works compound

Access to works

Work Nos. 4 and 5

Work Nos. 17, 18, 19A and 19B

15Access to worksWork Nos. 3 and 4
16Part of compoundWork Nos. 1 and 3
19

Access to works

Access to works

Work No.1

Work Nos. 17, 18, 19A and 19B

20Part of compoundWork Nos. 1 and 3
22, 47Access to worksWork No.1
24, 28River diversionWork No.6Diverted river and earthworks
29Access to worksWork Nos. 1 and 6
29aAccess to worksWork No.1Access track
30

Access to works

Access to works

Work No.1

Work Nos. 17, 18, 19A and 19B

30aAccess to worksWork Nos. 1, 17, 18, 19A and 19BAccess track and backfill of marl pit to support access track
33, 34, 38Construction and maintenance of pipe-lineWork No.17Pipe-line
34a, 36Tree plantingWork No.1Replacement woodland
35Working area for tree plantingWork No.1
37a

Works compound

Access to works

Work No. 1

Work Nos. 17, 18, 19A and 19B

40Access to worksWork No.1Access track and fencing
42

Access to works

Access to works

Work No.1

Work Nos. 17, 18, 19A and 19B

Access track
43, 51Road worksWork No.7Roadway
52

Road works

Access to works

Work No.7

Work Nos. 17, 18, 19A and 19B

52aAccess to worksWork Nos.17, 18, 19A and 19BAccess track
53, 55

Access to works

Access to works

Work No.7

Work Nos. 17, 18, 19A and 19B

56Works compound and construction of pipe-lineWork Nos. 1, 18, 19A and 19BPipe-line and access road
57Grub up highwayWork No.7Removal of road surface
59Access to worksWork Nos. 1, 18, 19A and 19BPipe-line
61, 65, 67Construction of pipe-lineWork Nos. 19A and 19BPipe-line
62, 63Access to WorksWork No.1
64Environmental mitigationWork No.1Replacement newt habitat
71Access to worksWork No.19A
72, 73, 82, 82a, 84Access to worksWork No.20
77Access to worksWork Nos. 1, 19A and 19B
78, 83, 103, 107, 107a, 108EarthworksWork No.1Earthworks and landscaping
85, 91, 92EarthworksWork Nos. 1 and 8Earthworks and landscaping
94, 116, 121, 122Works compoundWork Nos. 1, 8 and 9Earthworks and landscaping
97, 99, 176, 201Access to worksWork No.8
98EarthworksWork No.1Earthworks, landscaping and replacement bat accommodation
102Drainage worksWork No.1Drainage
105, 105aJunction remodellingWork No.10Roadway
110Remodel B5026Work No.8Roadway and turning head
114, 120Grub up highwayWork Nos. 1 and 8Removal of road surface
115Works compoundWork Nos. 1, 8 and 9
127Grub up highwayWork No.11Removal of road surface
128RoadworksWork No.11Roadway
130a, 141Access to worksWork No.1Access track
131, 132Works compoundWork No.1Earthworks and landscaping
133, 136Access to worksWork Nos. 1 and 13
134Mitigation work and river diversionWork Nos. 1 and 13Fen and swamp habitat replacement and diverted river
140, 142Access to worksWork No.1
143Access to worksWork Nos. 1, 13 and 14
144, 145Working area for earthworksWork Nos. 8 and 11
149Remodel Station Road junctionWork No.8Roadway
151Road worksWork Nos. 8 and 11
152Works to utilitiesWork Nos. 8 and 11Landscaping
153, 154Access to compounds and worksWork No.8
155Works compoundWork No.8Landscaping
156aAccess to worksWork No.8Access track
162, 163Access to worksWork Nos. 11 and 15Habitat creation
164Access to works and river diversionWork Nos. 11 and 15Diverted river and habitat creation
170, 171Access to worksWork Nos. 8 and 15Access
172, 173Access to worksWork Nos. 8 and 15
174, 175, 178aAccess to worksWork No.8Access track
177Works compound and formation of accessWork Nos. 8 and 11Earthworks landscaping, access and access track
179Access to worksWork Nos. 8, 11 and 15
180, 182EarthworksWork Nos. 8 and 11Earthworks and landscaping
181Works to utilitiesWork Nos. 8 and 11
184, 193, 194, 195Road worksWork No.12Roadway
186Works compoundWork No.12
187Grub up highwayWork No.12Removal of road surface
189EarthworksWork Nos. 8, 11 and 12Earthworks and landscaping
192, 196, 199EarthworksWork No.12Earthworks and landscaping
198Access to severed landWork No.12Access to severed land
203FencingWork Nos. 8 and 12
204, 206, 208Access to worksWork No.8
209Access to worksWork No.16
210a, 212Access to works and installation of power supplyWork No.16Power cables
211Access to worksWork No.16Access track

PART 2NATIONAL GRID

In the County of Staffordshire and the Borough of Stafford

(1)

Number of land shown on land plans

(2)

Purpose for which temporary possession may be taken

(3)

Relevant part of the authorised development

1, 2, 3, 5, 7, 8, 11, 11a, 13, 19, 30, 30a, 37a, 42, 49, 50, 54, 55Worksites and access to worksWork Nos. 17, 18, 19A and 19B
33, 34, 37, 38Construction and maintenance of pipe-lineWork No.17
34a (part)Construction of pipe-lineWork No.17
52, 52aWorksites and access to worksWork Nos. 17, 18, 19A and 19B
56Construction of pipe-lineWork Nos. 18, 19A and 19B
57Worksites and access to worksWork Nos. 18, 19A and 19B
58, 59, 65, 67Construction of pipe-lineWork Nos. 19A and 19B
61, 66, 77Worksites and access to worksWork Nos. 19A and 19B
71Construction of pipe-lineWork No.19A
76, 80, 87, 90, 96Worksites and access to worksWork Nos. 18, 19A and 19B

Article 39

SCHEDULE 10PROTECTIVE PROVISIONS

PART 1PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS

1.  For the protection of the undertakers referred to in this Part of this Schedule the following provisions, unless otherwise agreed in writing between Network Rail and the undertaker concerned, have effect.

2.  In this Part of this Schedule—

“alternative apparatus” means alternative apparatus adequate to enable the undertaker in question to fulfil its statutory functions in a manner no less efficient than previously;

“apparatus” means—

(a)

in the case of an electricity undertaker, electric lines or electrical plant (as defined in the Electricity Act 1989(2)), belonging to or maintained by that undertaker;

(b)

in the case of a gas undertaker, any mains, pipes or other apparatus belonging to or maintained by a gas transporter for the purposes of gas supply;

(c)

in the case of a water undertaker, mains, pipes or other apparatus belonging to or maintained by that undertaker for the purposes of water supply; and

(d)

in the case of a sewerage undertaker—

(i)

any drain or works vested in the undertaker under the Water Industry Act 1991(3); and

(ii)

any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4) of that Act or an agreement to adopt made under section 104 of that Act,

and includes a sludge main, disposal main (within the meaning of section 219 of that Act) or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works,

and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;

“functions” includes powers and duties;

“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land; and

“undertaker” means—

(a)

any licence holder within the meaning of Part 1 of the Electricity Act 1989;

(b)

a gas transporter within the meaning of Part 1 of the Gas Act 1986(4);

(c)

a water undertaker within the meaning of the Water Industry Act 1991;

(d)

a sewerage undertaker within the meaning of Part 1 of the Water Industry Act 1991; and

(e)

UKOP,

for the area of the authorised development, and in relation to any apparatus, means the undertaker to whom it belongs or by whom it is maintained.

3.  This Part of this Schedule does not apply to apparatus in respect of which the relations between Network Rail and the undertaker are regulated by the provisions of Part 3 of the 1991 Act.

4.  Regardless of any provision in this Order or anything shown on the land plans, Network Rail must not acquire any apparatus otherwise than by agreement.

5.—(1) If, in the exercise of the powers conferred by this Order, Network Rail acquires any interest in any land in which any apparatus is placed, that apparatus must not be removed under this Part of this Schedule and any right of an undertaker to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of the undertaker in question.

(2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, Network Rail requires the removal of any apparatus placed in that land, it must give to the undertaker in question written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order an undertaker reasonably needs to remove any of its apparatus) Network Rail must, subject to sub-paragraph (3), afford to the undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of Network Rail and subsequently for the maintenance of that apparatus.

(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of Network Rail, or Network Rail is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, the undertaker in question must, on receipt of a written notice to that effect from Network Rail, as soon as reasonably possible use its best endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.

(4) Any alternative apparatus to be constructed in land of Network Rail under this Part of this Schedule is to be constructed in such manner and in such line or situation as may be agreed between the undertaker in question and Network Rail or in default of agreement settled by arbitration in accordance with article 43 (arbitration).

(5) The undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 43, and after the grant to the undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by Network Rail to be removed under the provisions of this Part of this Schedule.

(6) Regardless of anything in sub-paragraph (5), if Network Rail gives notice in writing to the undertaker in question that it desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land of Network Rail, that work, instead of being executed by the undertaker, must be executed by Network Rail without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of the undertaker.

(7) Nothing in sub-paragraph (6) authorises Network Rail to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within 300 millimetres of the apparatus.

6.—(1) Where, in accordance with the provisions of this Part of this Schedule, Network Rail affords to an undertaker facilities and rights for the construction and maintenance in land of Network Rail of alternative apparatus in substitution for apparatus to be removed, those facilities and rights are to be granted upon such terms and conditions as may be agreed between Network Rail and the undertaker in question or in default of agreement settled by arbitration in accordance with article 43 (arbitration).

(2) In settling those terms and conditions in respect of alternative apparatus to be constructed in or along any railway of Network Rail, the arbitrator must—

(a)give effect to all reasonable requirements of Network Rail for ensuring the safety and efficient operation of the railway and for securing any subsequent alterations or adaptations of the alternative apparatus which may be required to prevent interference with any proposed works of Network Rail or the traffic on the railway; and

(b)so far as it may be reasonable and practicable to do so in the circumstances of the particular case, give effect to the terms and conditions, if any, applicable to the apparatus constructed in or along the railway for which the alternative apparatus is to be substituted.

(3) If the facilities and rights to be afforded by Network Rail in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to the undertaker in question than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by Network Rail to that undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.

7.—(1) Not less than 28 days before starting the execution of any works of the type referred to in paragraph 5(2) that are near to, or will or may affect, any apparatus the removal of which has not been required by Network Rail under paragraph 5(2), Network Rail must submit to the undertaker in question a plan, section and description of the works to be executed.

(2) Those works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the undertaker is entitled to watch and inspect the execution of those works.

(3) Any requirements made by an undertaker under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted to it.

(4) If an undertaker in accordance with sub-paragraph (3) and in consequence of the works proposed by Network Rail, reasonably requires the removal of any apparatus and gives written notice to Network Rail of that requirement, paragraphs 1 to 6 apply as if the removal of the apparatus had been required by Network Rail under paragraph 5(2).

(5) Nothing in this paragraph precludes Network Rail from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.

(6) Network Rail is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to the undertaker in question notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.

8.—(1) Subject to the following provisions of this paragraph, Network Rail must repay to an undertaker the reasonable expenses incurred by that undertaker in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus (including costs or compensation payable in connection with the acquisition of land for that purpose) which may be required in consequence of the execution of any such works as are referred to in paragraph 5(2).

(2) The value of any apparatus removed under the provisions of this Part of this Schedule is to be deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.

(3) If in accordance with the provisions of this Part of this Schedule—

(a)apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by Network Rail or, in default of agreement, is not determined by arbitration in accordance with article 43 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the undertaker in question by virtue of sub-paragraph (1) is to be reduced by the amount of that excess.

(4) For the purposes of sub-paragraph (3)—

(a)an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.

(5) An amount which apart from this sub-paragraph would be payable to an undertaker in respect of works under sub-paragraph (1) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

9.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works referred to in paragraph 5(2), any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of an undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any undertaker, Network Rail must—

(a)bear and pay the cost reasonably incurred by that undertaker in making good such damage or restoring the supply; and

(b)make reasonable compensation to that undertaker for any other expenses, loss, damages, penalty or costs incurred by the undertaker,

by reason or in consequence of any such damage or interruption.

(2) Nothing in sub-paragraph (1) imposes any liability on Network Rail with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an undertaker, its officers, servants, contractors or agents.

(3) An undertaker must give Network Rail reasonable notice of any such claim or demand and no settlement or compromise may be made without the consent of Network Rail which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.

10.  Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between Network Rail and an undertaker in respect of any apparatus laid or erected in land belonging to Network Rail on the date on which this Order is made.

PART 2PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS

11.—(1) For the protection of any operator, the following provisions, unless otherwise agreed in writing between Network Rail and the operator, have effect.

(2) In this Part of this Schedule—

“conduit system” has the same meaning as in the electronic communications code and references to providing a conduit system are to be construed in accordance with paragraph 1(3A) of that code;

“electronic communications apparatus” has the same meaning as in the electronic communications code;

“the electronic communications code” has the same meaning as in Chapter 1 of Part 2 of the 2003 Act(5);

“electronic communications code network” means—

(a)

so much of an electronic communications network or conduit system provided by an electronic communications code operator as is not excluded from the application of the electronic communications code by a direction under section 106 of the 2003 Act; and

(b)

an electronic communications network which the Secretary of State is providing or proposing to provide;

“electronic communications code operator” means a person in whose case the electronic communications code is applied by a direction under section 106 of the 2003 Act; and

“operator” means the operator of an electronic communications code network.

12.  The exercise of the powers conferred by article 31 (statutory undertakers) is subject to paragraph 23 of Schedule 2 to the Telecommunications Act 1984(6).

13.—(1) Subject to sub-paragraphs (2) to (4), if as the result of the authorised development or its construction, or of any subsidence resulting from any of the works comprised in the authorised development—

(a)any damage is caused to any electronic communications apparatus belonging to an operator (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purpose of the authorised development) or other property of an operator; or

(b)there is any interruption in the supply of the service provided by an operator,

Network Rail must bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and must—

(i)make reasonable compensation to an operator for loss sustained by it; and

(ii)indemnify an operator against claims, demands, proceedings, costs, damages and expenses which may be made or taken against, or recovered from, or incurred by, an operator by reason, or in consequence of, any such damage or interruption.

(2) Nothing in sub-paragraph (1) imposes any liability on Network Rail with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an operator, its officers, servants, contractors or agents.

(3) The operator must give Network Rail reasonable notice of any such claim or demand and no settlement or compromise of the claim or demand must be made without the consent of Network Rail which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.

(4) Any difference arising between Network Rail and the operator under this paragraph must be referred to and settled by arbitration under article 43 (arbitration).

14.  This Part of this Schedule does not apply to—

(a)any apparatus in respect of which the relations between Network Rail and an operator are regulated by the provisions of Part 3 of the 1991 Act; or

(b)any damage, or any interruption, caused by electro-magnetic interference arising from the construction or use of the authorised development.

15.  Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between Network Rail and an operator in respect of any apparatus laid or erected in land belonging to Network Rail on the date on which this Order is made.

Article 2

SCHEDULE 11PLANS AND DRAWINGS

Note:

In this Schedule a reference to a Regulation is to the quoted Regulation in the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009(7).

PART 1DESIGN DRAWINGS

Drawing TitleDrawing NumberRevision
Design Drawings [Regulation 5(2)(o)] Key Plan124130-EMF-DRG-ATK-910001A01
Design Drawings [Regulation 5(2)(o)] Works Overview Sheet 1 of 4124130-EMF-DRG-ATK-910002A02
Design Drawings [Regulation 5(2)(o)] Works Overview Sheet 2 of 4124130-EMF-DRG-ATK-910003A02
Design Drawings [Regulation 5(2)(o)] Works Overview Sheet 3 of 4124130-EMF-DRG-ATK-910004A03
Design Drawings [Regulation 5(2)(o)] Works Overview Sheet 4 of 4124130-EMF-DRG-ATK-910005A02
Design Drawings [Regulation 5(2)(o)] Track Longitudinal Sections Down Slow124130-EMF-DRG-ATK-910006A01
Design Drawings [Regulation 5(2)(o)] Track Longitudinal Section Up Norton Bridge124130-EMF-DRG-ATK-910007A01
Design Drawings [Regulation 5(2)(o)] Highways Longitudinal Sections124130-EMF-DRG-ATK-910008A01
Design Drawings [Regulation 5(2)(o)] Highways Longitudinal Sections124130-EMF-DRG-ATK-910014A01
Design Drawings [Regulation 5(2)(o)] Footpath Longitudinal Sections124130-EMF-DRG-ATK-910009A02
Design Drawings [Regulation 5(2)(o)] Typical Earthworks Cross Sections Sheet 1 of 4124130-EMF-DRG-ATK-910010A01
Design Drawings [Regulation 5(2)(o)] Typical Earthworks Cross Sections Sheet 2 of 4124130-EMF-DRG-ATK-910011A01
Design Drawings [Regulation 5(2)(o)] Typical Earthworks Cross Sections Sheet 3 of 4124130-EMF-DRG-ATK-910012A01
Design Drawings [Regulation 5(2)(o)] Typical Earthworks Cross Sections Sheet 4 of 4124130-EMF-DRG-ATK-910013A01
Design Drawings [Regulation 5(2)(o)] Underbridge 1 – LEC4 / 13 Widening Plans and Elevations124130-EMF-DRG-ATK-910015A02
Design Drawings [Regulation 5(2)(o)] Underbridge 1A Plans and Elevations124130-EMF-DRG-ATK-910016A01
Design Drawings [Regulation 5(2)(o)] Underbridge 2 – Meece Brook South Plans and Elevations124130-EMF-DRG-ATK-910017A02
Design Drawings [Regulation 5(2)(o)] Overbridge 3 – Searchlight Lane Plans and Elevations124130-EMF-DRG-ATK-910018A02
Design Drawings [Regulation 5(2)(o)] Intersection Bridge 5, WCML Plans and Elevations124130-EMF-DRG-ATK-910020A02
Design Drawings [Regulation 5(2)(o)] Overbridge 5A – WCML / B5026 Plans and Elevations124130-EMF-DRG-ATK-910021A02
Design Drawings [Regulation 5(2)(o)] Underbridges 6 & 6A – Meece Brook North Plan124130-EMF-DRG-ATK-910022A02
Design Drawings [Regulation 5(2)(o)] Underbridges 6 & 6A – Meece Brook North Sections and Elevations124130-EMF-DRG-ATK-910023A02
Design Drawings [Regulation 5(2)(o)] Overbridge 7 – Meece Road Plans and Elevations124130-EMF-DRG-ATK-910024A02
Design Drawings [Regulation 5(2)(o)] Underbridge 8 – NBS/9 Widening Plans and Elevations124130-EMF-DRG-ATK-910025A01
Design Drawings [Regulation 5(2)(o)] Footbridge 9 – Mid Norton Plans and Elevations124130-EMF-DRG-ATK-910026A01
Design Drawings [Regulation 5(2)(o)] Overbridge 10A – B5026 West Plans and Elevations124130-EMF-DRG-ATK-910027A02
Design Drawings [Regulation 5(2)(o)] Underbridge 11 – Meece Brook West Plans and Elevations124130-EMF-DRG-ATK-910028A02
Design Drawings [Regulation 5(2)(o)] Earthworks Cross Sections Sheet 1 of 5124130-EMF-DRG-ATK-910115A01
Design Drawings [Regulation 5(2)(o)] Earthworks Cross Sections Sheet 2 of 5124130-EMF-DRG-ATK-910116A01
Design Drawings [Regulation 5(2)(o)] Earthworks Cross Sections Sheet 3 of 5124130-EMF-DRG-ATK-910117A01
Design Drawings [Regulation 5(2)(o)] Earthworks Cross Sections Sheet 4 of 5124130-EMF-DRG-ATK-910118A01
Design Drawings [Regulation 5(2)(o)] Earthworks Cross Sections Sheet 5 of 5124130-EMF-DRG-ATK-910119A01
Highway Diversion and Maintenance Access Key Plan124130-ECV-DRG-ATK-038101B03
B5026 Diversion Plan and Longsection Sheet 1 of 8124130-ECV-DRG-ATK-038311B03
B5026 Diversion Plan Sheet 2 of 8124130-ECV-DRG-ATK-038312B03
B5026 Diversion Plan Sheet 3 of 8124130-ECV-DRG-ATK-038313B03
B5026 Long Section Sheet 4 of 8124130-ECV-DRG-ATK-038314

B03

B5026 Diversion Plan and Long Section Sheet 5 of 8124130-ECV-DRG-ATK-038315B03
B5026 Diversion Plan and Long Section Sheet 6 of 8124130-ECV-DRG-ATK-038316B03
B5026 Diversion Plan and Long Section Sheet 7 of 8124130-ECV-DRG-ATK-038317B03
B5026 Diversion Plan and Long Section Sheet 8 of 8124130-ECV-DRG-ATK-038318B04
Searchlight Lane Diversion Plan and Long Section Sheet 1 of 2124130-ECV-DRG-ATK-038319B04
Searchlight Lane Diversion Plan and Long Section Sheet 2 of 2124130-ECV-DRG-ATK-038320B04
Searchlight Lane Junction Maintenance Compound General Arrangement124130-ECV-DRG-ATK-038386B03
Yarnfield Junction Maintenance Compound General Arrangement124130-ECV-DRG-ATK-038387B03
Little Bridgeford Maintenance Compound General Arrangement124130-ECV-DRG-ATK-038388B03
Highway Standard Details124130-ECV-DRG-ATK-038001B03
B5026 Diversion Fencing and Road Restraint Systems124130-ECV-DRG-ATK-038341B03
B5026 Diversion Fencing and Road Restraint Systems124130-ECV-DRG-ATK-038342B03
B5026 Diversion Fencing and Road Restraint Systems124130-ECV-DRG-ATK-038343B03
B5026 Diversion Fencing and Road Restraint Systems124130-ECV-DRG-ATK-038344B03
Searchlight Lane Fencing and Road Restraint Systems124130-ECV-DRG-ATK-038345B04
B5026 Diversion Pavement, Footways and Paved Areas Sheet 1 of 4124130-ECV-DRG-ATK-038351B03
B5026 Diversion Pavement, Footways and Paved Areas Sheet 2 of 4124130-ECV-DRG-ATK-038352B03
B5026 Diversion Pavement, Footways and Paved Areas Sheet 3 of 4124130-ECV-DRG-ATK-038353B03
B5026 Diversion Pavement, Footways and Paved Areas Sheet 4 of 4124130-ECV-DRG-ATK-038354B03
Searchlight Lane Diversion Pavement, Footways and Paved Areas124130-ECV-DRG-ATK-038355B04
B5026 Diversion Kerbs Sheet 1 of 4124130-ECV-DRG-ATK-038361B03
B5026 Diversion Kerbs Sheet 2 of 4124130-ECV-DRG-ATK-038362B03
B5026 Diversion Kerbs Sheet 3 of 4124130-ECV-DRG-ATK-038363B03
B5026 Diversion Kerbs Sheet 4 of 4124130-ECV-DRG-ATK-038364B03
Searchlight Lane Kerbs124130-ECV-DRG-ATK-038365B04
B5026 Diversion Traffic Signs & Road Markings124130-ECV-DRG-ATK-038371B03
B5026 Diversion Traffic Signs & Road Markings124130-ECV-DRG-ATK-038372B03
B5026 Diversion Traffic Signs & Road Markings124130-ECV-DRG-ATK-038373B03
Searchlight Lane Traffic Signs & Road Markings124130-ECV-DRG-ATK-038375B04
B5026 Diversion Traffic Signs Details124130-ECV-DRG-ATK-038003B03
B5026 Diversion Traffic Signs Details124130-ECV-DRG-ATK-038004B03
B5026 Diversion Traffic Signs Details124130-ECV-DRG-ATK-038005B03
B5026 Diversion Traffic Signs Details124130-ECV-DRG-ATK-038006B03
B5026 Diversion Traffic Signs Details124130-ECV-DRG-ATK-038007B03
B5026 Diversion Proposed Street Lighting Layout124130-ECV-DRG-ATK-038381B03
B5026 Diversion Proposed Street Lighting Wiring Diagram124130-ECV-DRG-ATK-038382B03
Scamnell Lane Sections124130-ECV-DRG-ATK-038395B03
Drainage Key Plan124130-ECV-DRG-ATK-020100B03
Drainage Network Layout Sheet 1 of 2124130-ECV-DRG-ATK-020150B03
Drainage Network Layout Sheet 2 of 2124130-ECV-DRG-ATK-020151B03
B5026 Diversion Drainage Sheet 1 of 4124130-ECV-DRG-ATK-028311B03
B5026 Diversion Drainage Sheet 2 of 4124130-ECV-DRG-ATK-028312B03
B5026 Diversion Drainage Sheet 3 of 4124130-ECV-DRG-ATK-028313B03
B5026 Diversion Drainage Sheet 4 of 4124130-ECV-DRG-ATK-028314B03
Searchlight Lane Drainage124130-ECV-DRG-ATK-028315B04
Chebsey Lane General Arrangement (Temporary Situation)NBSAIP-ASA-DRG-EHW-035310B01
Chebsey Lane Fencing, Pavement & Kerbs (Temporary Situation)NBSAIP-ASA-DRG-EHW-035311B01
Chebsey Lane Lighting (Temporary Situation)NBSAIP-ASA-DRG-EHW-035312B01
Chebsey Lane DrainageNBSAIP-ASA-DRG-EHW-035313B01
Chebsey Lane Traffic Signs, Road Markings & Signals (Temporary Situation)NBSAIP-ASA-DRG-EHW-035314B01
Chebsey Lane Extent of Temporary 40 mph Speed Limit (TRO)NBSAIP-ASA-DRG-EHW-035315B01
Chebsey Lane General Arrangement (Permanent Situation)NBSAIP-ASA-DRG-EHW-035320B01
Chebsey Lane Pavement And Kerbing (Permanent Situation)NBSAIP-ASA-DRG-EHW-035321B01
Chebsey Lane Traffic Signs, Road Markings & Signals (Permanent Situation)NBSAIP-ASA-DRG-EHW-035323B01
Chebsey Lane Traffic Signals Layout (Temporary Situation)NBSAIP-ASA-DRG-EHW-035354B01
Chebsey Lane Traffic Signals Ducting Layout (Temporary Situation)NBSAIP-ASA-DRG-EHW-035355B01
Lighting and Electrical Standard Details Sheet 1 of 2 (Chebsey Lane / A5013 Eccleshall Road Junction)124130-ECV-DRG-ATK-038385B03
Lighting and Electrical Standard Details Sheet 2 of 2 (Chesbey Lane / A5013 Eccleshall Road Junction)124130-ECV-DRG-ATK-038394B03

PART 2LAND PLANS

Drawing TitleReference
Land Plans
Key Plan30 August 2013 (Revision B)
Sheet 129 November 2012
Sheet 229 November 2012
Sheet 329 November 2012
Sheet 429 November 2012
Sheet 529 November 2012
Sheet 629 November 2012
Sheet 730 August 2013 (Revision C)
Sheet 829 November 2012
Sheet 929 November 2012
Sheet 1029 November 2012
Sheet 1129 November 2012
Land Affected Plans
Key Plan124130-EMF-DRG-ATK-910125 (Rev: A02) (20 September 2013)
Sheet 1124130-EMF-DRG-ATK-910126 (Rev: A01) (23 November 2012)
Sheet 2124130-EMF-DRG-ATK-910127 (Rev: A02) (20 September 2013)
Sheet 3124130-EMF-DRG-ATK-910128 (Rev: A02) (20 September 2013)
Sheet 4124130-EMF-DRG-ATK-910129 (Rev: A01) (23 November 2012)

PART 3STREET PLANS

Drawing TitleDrawing NumberRevision
Street Plans [Regulation 5(2)(k)] Key Plan124130-EMF-DRG-ATK-910045A01
Street Plans [Regulation 5(2)(k)] Sheet 1 of 4124130-EMF-DRG-ATK-910046A01
Street Plans [Regulation 5(2)(k)] Sheet 2 of 4124130-EMF-DRG-ATK-910047A01
Street Plans [Regulation 5(2)(k)] Sheet 3 of 4124130-EMF-DRG-ATK-910048A02
Street Plans [Regulation 5(2)(k)] Sheet 4 of 4124130-EMF-DRG-ATK-910049A01

PART 4WORKS PLANS

Drawing TitleDrawing NumberRevision
Works Plans [Regulation 5(2)(j)] Key Plan 1:10000124130-EMF-DRG-ATK-910030A01
Works Plans [Regulation 5(2)(j)] 1:2500 Plan Sheet 1 of 4124130-EMF-DRG-ATK-910031A01
Works Plans [Regulation 5(2)(j)] 1:2500 Plan Sheet 2 of 4124130-EMF-DRG-ATK-910032A01
Works Plans [Regulation 5(2)(j)] 1:2500 Plan Sheet 3 of 4124130-EMF-DRG-ATK-910033A02
Works Plans [Regulation 5(2)(j)] 1:2500 Plan Sheet 4 of 4124130-EMF-DRG-ATK-910034A01
Works Plans [Regulation 6(2)] Track Longitudinal Sections Work No.1 – Down Slow124130-EMF-DRG-ATK-910035A01
Works Plans [Regulation 6(2)] Track Longitudinal Section Work No.8 – Up Norton Bridge124130-EMF-DRG-ATK-910036A01
Works Plans [Regulation 6(2)] Highways Longitudinal Sections124130-EMF-DRG-ATK-910037A01
Works Plans [Regulation 6(2)] Footpath Longitudinal Sections124130-EMF-DRG-ATK-910038A02
Works Plans [Regulation 6(2)] Highways Longitudinal Sections124130-EMF-DRG-ATK-910039A01
Works Plans [Regulation 6(2)] Rivers Longitudinal Sections124130-EMF-DRG-ATK-910040A01
Fuel Pipeline Diversion Long Section (Regulation 5(2)(o)) Sheet 1 of 5BPA-7385-X-MAP1
Fuel Pipeline Diversion Long Section (Regulation 5(2)(o)) Sheet 2 of 5BPA-7386-X-MAPA
Fuel Pipeline Diversion Long Section (Regulation 5(2)(o)) Sheet 3 of 5BPA-7387-X-MAPA
Fuel Pipeline Diversion Long Section (Regulation 5(2)(o)) Sheet 4 of 5BPA-7388-X-MAPA
Fuel Pipeline Diversion Long Section (Regulation 5(2)(o)) Sheet 5 of 5BPA-7389-X-MAPA
Gas Pipeline Diversion, Long Sections [Regulation 5(2)(o)]B1086521/9020A
Works Plans [Regulation 6(2)] Earthworks Cross Sections 1 of 5124130-EMF-DRG-ATK-910120A01
Works Plans [Regulation 6(2)] Earthworks Cross Sections 2 of 5124130-EMF-DRG-ATK-910121A01
Works Plans [Regulation 6(2)] Earthworks Cross Sections 3 of 5124130-EMF-DRG-ATK-910122A01
Works Plans [Regulation 6(2)] Earthworks Cross Sections 4 of 5124130-EMF-DRG-ATK-910123A01
Works Plans [Regulation 6(2)] Earthworks Cross Sections 5 of 5124130-EMF-DRG-ATK-910124A01
Works Plans [Regulation 6(2)] Underbridge 1 – LEC4 / 13 Widening Plans and Elevations124130-EMF-DRG-ATK-910050A02
Works Plans [Regulation 6(2)] Underbridge 1A – Plans and Elevations124130-EMF-DRG-ATK-910051A01
Works Plans [Regulation 6(2)] Underbridge 2 – Meece Brook South Plans and Elevations124130-EMF-DRG-ATK-910052A02
Works Plans [Regulation 6(2)] Overbridge 3 – Searchlight Lane Plans and Elevations124130-EMF-DRG-ATK-910053A02
Works Plans [Regulation 6(2)] Intersection Bridge 5, WCML Plans and Elevations124130-EMF-DRG-ATK-910054A02
Works Plans [Regulation 6(2)] Overbridge 5A – WCML / B5026 Plans and Elevations124130-EMF-DRG-ATK-910055A02
Works Plans [Regulation 6(2)] Underbridges 6 & 6A – Meece Brook North Plan124130-EMF-DRG-ATK-910056A02
Works Plans [Regulation 6(2)] Underbridges 6 & 6A – Meece Brook North Sections and Elevations124130-EMF-DRG-ATK-910057A02
Works Plans [Regulation 6(2)] Overbridge 7 – Meece Road Plans and Elevations124130-EMF-DRG-ATK-910058A02
Works Plans [Regulation 6(2)] Underbridge 8 – NBS9 Widening Plans and Elevations124130-EMF-DRG-ATK-910059A01
Works Plans [Regulation 6(2)] Footbridge 9 – Mid Norton Plans and Elevations124130-EMF-DRG-ATK-910060A01
Works Plans [Regulation 6(2)] Overbridge 10A – B5026 West Plans and Elevations124130-EMF-DRG-ATK-910061A02
Works Plans [Regulation 6(2)] Underbridge 11 – Meece Brook West Plans and Elevations124130-EMF-DRG-ATK-910062A02
Works Plans [Regulation 5(2)(j)] National Grid 1:2500 Plan Sheet 1 of 2124130-EMF-DRG-ATK-910100A01
Works Plans [Regulation 5(2)(j)] National Grid 1:2500 Plan Sheet 2 of 2124130-EMF-DRG-ATK-910101A01
Gas Pipeline Diversion, Long Sections [Regulation 5(2)(o)]B1086521/9020A

PART 5TRAFFIC REGULATION ORDER PLANS

Drawing TitleDrawing NumberRevision
Chebsey Lane Extent of Temporary 40 mph Speed Limit (TRO)NBSAIP-ASA-DRG-EHW-035315B01
B5026 and Meece Road TRO PlanNBSAIP-ASA-DRG-EHW-035360A01
B5026 and Meece Road TRO PlanNBSAIP-ASA-DRG-EHW-035361A01
B5026 and Meece Road TRO PlanNBSAIP-ASA-DRG-EHW-035362A01
B5026 and Meece Road TRO PlanNBSAIP-ASA-DRG-EHW-035363A01

Article 38

SCHEDULE 12TRAFFIC REGULATION

Imposition of speed limit

(1)

Road

(2)

Speed limit (miles per hour (mph))

(3)

Extent

A501340 mphThe area hatched red on the traffic regulation order plan NBSAIP-ASA-DRG-EHW-035315 (Rev. B01)
Chebsey Lane40 mphThe area hatched red on the traffic regulation order plan NBSAIP-ASA-DRG-EHW-035315 (Rev. B01)
Worston Lane40 mphThe area hatched red on the traffic regulation order plan NBSAIP-ASA-DRG-EHW-035315 (Rev. B01)
B502650 mphThe area hatched red on the traffic regulation order plans NBSAIP-ASA-DRG-EHW-035360 (Rev. A01) to NBSAIP-ASA-DRG-EHW-035363 (Rev. A01)
Meece Road50 mphThe area hatched red on the traffic regulation order plans NBSAIP-ASA-DRG-EHW-035360 (Rev. A01) to NBSAIP-ASA-DRG-EHW-035363 (Rev. A01)
(4)

1986 c. 44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c. 45), and was further amended by section 76 of the Utilities Act 2000 (c. 27).

(5)

See section 106.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill