Article 2

SCHEDULECorrectable Errors

(1) Where correction is to be made(2) How correction is to be made(3) Text to be substituted, inserted or omitted (if any)
Article 2(1), definition of “outline offshore operations and maintenance plan”For “the Order”, substitute“this Order”
Article 2(1), definition of “works plan”For “the Order”, substitute“this Order”
Article 6(1)Article 6(1) is renumbered as Article 6
Article 9(1)Article 9(1) is renumbered as Article 9
Article 23(5)For “land which temporary possession is taken”, substitute“land of which temporary possession is taken”
Article 32(1)(t)For “the In principle East Anglia Three Project Southern North Sea pSAC Site Integrity Plan (December 2016)”, substitute“the in principle East Anglia Three Project Southern North Sea pSAC Site Integrity Plan (December 2016, Revision B)”
Article 34(1)For “the requirements numbered 11 to 31 and 36”, substitute“the requirements numbered 11 to 31 and 36 to 37”
Schedule 1, Part 1, paragraph 1, “Work No. 16”For “in north westerly direction to the east side of The Thicket”, substitute“in a north westerly direction to the east side of The Thicket”
Schedule 1, Part 3, paragraph 2(2)For “The number of turbines with a draught height of less than 24m from MHWS comprised in the authorised project must not exceed 52 turbines”, substitute“The number of wind turbine generators with a draught height of less than 24m from MHWS comprised in the authorised project must not exceed 52.”
Schedule 1, Part 3, heading to paragraph 19For “Contaminated land and ground water”, substitute“Contaminated land and groundwater”
Schedule 1, Part 3, paragraph 22(1)For “relevant local planning authority”, substitute“relevant planning authority”
Schedule 1, Part 3, paragraph 27(1)For “relevant local planning authority”, substitute“relevant planning authority”
Schedule 1, Part 3, paragraph 30For “with such details the relevant planning authority in consultation with the relevant highway authority may approve, as soon as reasonably practicable and in any event within twelve months of completion of the relevant stage of the connection works, save that if approved by the relevant local planning authority”, substitute“with such details as the relevant planning authority in consultation with the relevant highway authority may approve, as soon as reasonably practicable and in any event within twelve months of completion of the relevant stage of the connection works, save that if approved by the relevant planning authority”
Schedule 1, Part 3, paragraph 37

For “in writing to the relevant planning authority of its intention to carry out such works and investigations and:

(i) the relevant planning authority has provided a written determination that the notified works and investigations can take place; or

(ii) no response has been received by the undertaker within 15 working days of the date of notification of such works and investigations.”, substitute

“in writing to the relevant planning authority of its intention to carry out such works or investigations and:

(a) the relevant planning authority has provided a written determination that the notified works or investigations can take place; or

(b) no response has been received by the undertaker within 15 working days of the date of notification of such works or investigations.”

Schedule 8, Part 3, paragraph 26(9)For “paragraph 15(1)”, substitute“paragraph 30(1)”
Schedule 8, Part 4, paragraph 45For “paragraphs 4 to 6 and 8”, substitute“paragraphs 40 to 42 and 44”
Schedule 8, Part 4, paragraph 46For “paragraph (9)”, substitute“paragraph 45”
Schedule 8, Part 5, paragraph 49(1), definition of “specified works”Immediately after ““Specification for safe working in the vicinity of National Grid, High pressure Gas pipelines and associated installation or requirements for third parties T/SP/SSW/22””, insert“)”
Schedule 8, Part 5, paragraph 49(2)For “the Order”, substitute“this Order”
Schedule 8, Part 5, paragraph 50(1)For “the Order”, substitute“this Order”
Schedule 8, Part 5, paragraph 51(1)For “the Order”, substitute“this Order”
Schedule 8, Part 5, paragraph 57(2)For “(subject to sub-paragraph (3), excuse the undertaker from liability under the provisions of this sub-paragraph (1)).”, substitute“(subject to sub-paragraph (3)), excuse the undertaker from liability under the provisions of this sub-paragraph (1).”
Schedule 8, Part 5, paragraph 59(1)For “paragraphs54 and 55”, substitute“paragraphs 54 and 55”
Schedule 8, Part 5, paragraph 59(2)For “approval to is required”, substitute“approval is required”
Schedule 8, Part 5, paragraph 61For “paragraph 52(2), 52(4), 53(1), 54, 55 and 57(5)”, substitute“paragraph 52(2), 52(4), 53(1), 54, and 55”
Schedule 8, Part 6, paragraph 64For “the Order.”, substitute“this Order.”
Schedule 8, Part 6, paragraph 65.For “the Order” in each place where it appears, substitute“this Order”
Schedule 8, Part 6, paragraph 66(2)For “the Order” in each place where it appears, substitute“this Order”
Schedule 8, Part 6, paragraph 68(1)For “the Order”, substitute“this Order”
Schedule 8, Part 6, paragraph 68(6)For “the Order”, substitute“this Order”
Schedule 8, Part 6, paragraph 68(7)For “the Order”, substitute“this Order”
Schedule 8, Part 6, paragraph 69(3)(b).For “the Order”, substitute“this Order”
Schedule 8, Part 6, paragraph 71For “the Order”, substitute“this Order”
Schedule 8, Part 6, paragraph 73For “the Order”, substitute“this Order”
Schedule 8, Part 7 (Protection for oil and gas licensees), paragraph 84 (ix) and (x).For “the Order” in each place where it occurs, substitute“this Order”

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill