Chwilio Deddfwriaeth

The Electricity (Applications for Licences, Modifications of an Area and Extensions and Restrictions of Licences) Regulations 2019

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

Changes over time for: The Electricity (Applications for Licences, Modifications of an Area and Extensions and Restrictions of Licences) Regulations 2019 (without Schedules)

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The Electricity (Applications for Licences, Modifications of an Area and Extensions and Restrictions of Licences) Regulations 2019. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Citation, commencement and revocationE+W+S

1.—(1) These Regulations may be cited as the Electricity (Applications for Licences, Modifications of an Area and Extensions and Restrictions of Licences) Regulations 2019 and come into force on 5th July 2019.

(2) The Electricity (Applications for Licences, Modifications of an Area and Extensions and Restrictions of Licences) Regulations 2010(1) (“the 2010 Regulations”) are revoked.

Commencement Information

I1Reg. 1 in force at 5.7.2019, see reg. 1(1)

Transitional provisionsE+W+S

2.—(1) Where an application has been made under the 2010 Regulations but at the date upon which these Regulations come into force the application has neither been granted nor refused, the application shall be treated thereafter as having been made under these Regulations.

(2) In relation to an application to which paragraph (1) applies, the Authority, where necessary, will require applicants to supplement their application with additional information to meet the requirements of these Regulations.

(3) Where, in relation to an application to which paragraph (1) applies, the applicant, before the coming into force of these Regulations, published a notice of the application in accordance with the 2010 Regulations, the requirements of these Regulations as regards publication shall be taken to have been met.

Commencement Information

I2Reg. 2 in force at 5.7.2019, see reg. 1(1)

InterpretationE+W+S

3.—(1) In these Regulations—

“the 2000 Act” means the Utilities Act 2000(2);

“the 2004 Act” means the Energy Act 2004(3);

“the Act” means the Electricity Act 1989;

“application” means an application for a licence or for a modification of a licence under the Act and references to an application in respect of a licence shall be construed accordingly;

“the Authority” means the Gas and Electricity Markets Authority established by section 1 of the 2000 Act;

“distribution licence” means a licence granted or to be granted under section 6(1)(c) of the Act(4);

“domestic premises” means premises used wholly or mainly for domestic purposes;

“extension”, in relation to a supply licence, means an extension of the licence under section 6(4) of the Act and, in relation to a distribution licence, means an extension of the licence under section 6(6) of the Act;

“generation licence” means a licence granted or to be granted under section 6(1)(a) of the Act;

“interconnector licence” means a licence granted or to be granted under section 6(1)(e) of the Act(5);

“modification of an area” in relation to a transmission licence, means a modification of an area of the licence under section 6(6B) of the Act(6);

“principal undertaking” means an undertaking within the meaning of section 1161 of the Companies Act 2006(7);

“related person” means

(a)

in relation to an applicant who is the principal undertaking, a parent or subsidiary undertaking of the principal undertaking or a subsidiary undertaking of the parent undertaking of the principal undertaking, in each case within the meaning of section 1162 and Schedule 7 of the Companies Act 2006, and

(b)

in relation to any applicant (including such an undertaking), a connected person of the applicant within the meaning of section 286 of the Taxation of Chargeable Gains Act 1992(8);

“restriction”, in relation to a supply licence, means a restriction of the licence under section 6(4) of the Act and, in relation to a distribution licence, means a restriction of the licence under section 6(6) of the Act, and, in relation to a transmission licence, means a modification of an area of the licence under section 6(6B) of the Act by a restriction of the area of the licence;

“shares”, in relation to an applicant with share capital, means allotted shares; in relation to an applicant with capital but no share capital, means rights to share in the capital of the applicant; and in relation to an applicant without share capital, means interests (i) conferring any right to share in the profits or liability to contribute to the losses of the applicant; and (ii) giving rise to an obligation to contribute to the debts or expenses of the applicant in the event of winding up;

“signed” includes signed in a manner which would for the purposes of section 7 of the Electronic Communications Act 2000(9) be an electronic signature;

“significant managerial responsibility or influence” means where a person plays a role in—

(a)

the making of decisions about how the whole or a substantial part of an undertaking’s activities are to be managed or organised, or

(b)

the actual managing or organising of the whole or a substantial part of those activities;

“Supplier of Last Resort event” means when a direction is issued by the Authority pursuant to standard condition 8 of either a gas supply licence granted under section 7A(1) of the Gas Act 1986(10) or an electricity supply licence granted under section 6(1)(d) of the Act;

“supply licence” means a licence granted or to be granted under section 6(1)(d) of the Act;

“transmission licence” means a licence granted or to be granted under section 6(1)(b) of the Act(11); and

“ultimate holding company” means a holding company (within the meaning of sections 1159 and 1160 of the Companies Act 2006(12)) of the applicant which is not itself a subsidiary of another company, which is in the position to control, or exercise significant influence over, a policy of the applicant by virtue of rights under contractual arrangements or rights of ownership which are held by the company or of which the company is a beneficiary.

(2) In these Regulations, unless the context otherwise requires, a reference to a standard condition is a reference, —

(a)in relation to a distribution licence, a generation licence, a supply licence or a transmission licence, to a standard condition which is determined under section 33(1) of the 2000 Act(13) or section 137(1) of the 2004 Act; or

(b)in relation to an interconnector licence, to a standard condition which is determined under section 146(1) of the 2004 Act,

subject to any modifications of the standard conditions made under Part I of the Act, the 2000 Act, or the 2004 Act, after the determination under those sections.

(3) In these Regulations —

(a)any reference to the Schedule is a reference to the Schedule of these Regulations; and

(b)any reference to a numbered paragraph is a reference to the paragraph bearing that number in the regulation in which the reference occurs.

[F1(4) These Regulations do not apply to applications in respect of—

(a)an “offshore transmission licence” as defined in section 64 of the Act;

(b)an “electricity system operator licence” as defined in section 6(1)(da) of the Act;

(c)a “smart meter communication licence” as defined in section 6(1)(f) of the Act; or

(d)a “code manager licence” as defined in section 6(1)(g) of the Act.]

Textual Amendments

Commencement Information

I3Reg. 3 in force at 5.7.2019, see reg. 1(1)

Manner of ApplicationE+W+S

4.  An application shall be:

(a)made in writing, addressed to the Authority and delivered or sent by prepaid post to the Authority at its principal address or sent by electronic mail to an address specified by the Authority;

(b)signed and dated by or on behalf of the applicant, stating, where signed on behalf of the applicant, the capacity of the signatory; and

(c)accompanied by the prescribed fee referred to in regulation 7 of these Regulations.

Commencement Information

I4Reg. 4 in force at 5.7.2019, see reg. 1(1)

Form of applicationE+W+S

5.—(1) An application shall be made by completing in full the form shown in the Schedule.

(2) The application may not be considered by the Authority unless it is made in accordance with this regulation 5.

(3) The Authority may make further enquiries of the applicant about any matter connected with the application and may request additional information or documentation as set out in the form in the Schedule.

Commencement Information

I5Reg. 5 in force at 5.7.2019, see reg. 1(1)

Additional information and documents to accompany applicationE+W+S

6.—(1) Subject to paragraphs (2), (3) and (4)—

(a)an application in respect of a transmission licence shall be accompanied by the information and documents specified for that licence in the form in the Schedule;

(b)an application in respect of a distribution licence shall be accompanied by the information and documents specified for that licence in the form in the Schedule;

(c)an application in respect of a supply licence shall be accompanied by the information and documents specified for that licence in the form in the Schedule; and

(d)an application in respect of an interconnector licence shall be accompanied by the information and documents specified for that licence in the form in the Schedule.

(2) The obligation imposed by paragraph (1) shall, to the extent that information and documents are specified in the Schedule by reference to, or in relation to, a standard condition, apply—

(a)subject to paragraph (3), in the case of an application for a licence, as if the standard condition in question were to be included and have effect in any licence granted as a result of the application; and

(b)in the case of an application for a modification of an area, or for an extension or restriction of a licence, in relation to such of the standard conditions in question as have been included and have effect in that licence.

(3) Where a modification to any standard condition is requested in an application made in accordance with these Regulations, the obligation imposed by paragraph (2)(a) shall be modified accordingly.

(4) The obligation imposed by paragraph (1)(a), (b) and (c) in relation to an application for an extension or restriction of a licence shall only apply to the extent that the information and documents differ from or add to the most recent information and documents provided in relation to an application made in accordance with these Regulations or in pursuance of a condition of the applicant’s licence.

Commencement Information

I6Reg. 6 in force at 5.7.2019, see reg. 1(1)

Application FeesE+W+S

7.—(1) Subject to paragraph (2), the prescribed fee in relation to an application of the description specified in the first column of the Table in the form in the Schedule shall be the corresponding fee specified in the second column of that Table.

(2) Where more than one fee would, but for this paragraph, be payable in respect of a particular application, the prescribed fee shall be the higher or highest such fee.

Commencement Information

I7Reg. 7 in force at 5.7.2019, see reg. 1(1)

Publication of notice of applicationE+W+S

8.—(1) The period prescribed for the purpose of section 6A(3) of the Act(14) (notice of applications) is ten working days from the date the applicant is notified by the Authority that the application is duly made (“the prescribed period”).

(2) The prescribed manner of publication for that purpose shall be either by—

(a)requesting the Authority to place the notice on the website address of the Authority (at “www.ofgem.gov.uk” or such other website address as may be notified to the applicant by the Authority in writing); or

(b)publishing the notice on the website address of the applicant and requesting the Authority to place a link to the applicant’s website address on the website address of the Authority (at “www.ofgem.gov.uk” or such other website address as may be notified to the applicant by the Authority in writing).

(3) Where an application is for the restriction of a licence, the applicant shall also ensure that notice of application is published within the prescribed period in such newspapers as are calculated to ensure that the notice is circulated throughout the area to which the proposed restriction relates.

(4) In this regulation “working day” shall have the same meaning as in section 64 of the Electricity Act 1989(15).

Commencement Information

I8Reg. 8 in force at 5.7.2019, see reg. 1(1)

The seal of the Gas and Electricity Markets Authority here affixed is authenticated by the signature of

Legal seal

Mary Starks

A member of the Authority

For and by the Gas and Electricity Markets Authority

13th June 2019

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill