Construction Programme

22.—(1) At least 56 days prior to the commencement of the authorised development the undertaker must consult with ScottishPower Renewables on a detailed construction programme and traffic management plan which must clearly set out the access arrangements for the Wind Farm in respect of all types of vehicles for all stages of construction of the authorised development.

(2) ScottishPower Renewables must notify the undertaker within 28 days of receipt of the documents referred to in sub-paragraph (1) where it considers that either or both of the construction programme and the traffic management plan have the potential to affect access to the Wind Farm and/or the commercial operation of the Wind Farm.

(3) If the undertaker does not receive notification from ScottishPower Renewables in accordance with sub-paragraph (2) then ScottishPower Renewables shall be deemed to be satisfied with the documents and the undertaker shall be at liberty to proceed with the authorised development.

(4) The undertaker must make reasonable attempts to agree a resolution to any concerns raised by ScottishPower Renewables in accordance with sub-paragraph (2) prior to commencing the relevant part of the authorised development.