Construction Programme

22.—(1) At least 56 days prior to the commencement of the authorised development the undertaker must consult with ScottishPower Renewables on a detailed construction programme and traffic management plan which must clearly set out the access arrangements for the Wind Farm in respect of all types of vehicles for all stages of construction of the authorised development.

(2) ScottishPower Renewables must notify the undertaker within 28 days of receipt of the documents referred to in sub-paragraph (1) where it considers that either or both of the construction programme and the traffic management plan have the potential to affect access to the Wind Farm and/or the commercial operation of the Wind Farm.

(3) If the undertaker does not receive notification from ScottishPower Renewables in accordance with sub-paragraph (2) then ScottishPower Renewables shall be deemed to be satisfied with the documents and the undertaker shall be at liberty to proceed with the authorised development.

(4) The undertaker must make reasonable attempts to agree a resolution to any concerns raised by ScottishPower Renewables in accordance with sub-paragraph (2) prior to commencing the relevant part of the authorised development.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources