There are currently no known outstanding effects for the The A57 Link Roads Development Consent Order 2022, SCHEDULE 4. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 15

SCHEDULE 4E+W+SPERMANENT STOPPING UP AND ALTERATION OF HIGHWAYS, STREETS AND PRIVATE MEANS OF ACCESS

PART 1E+W+SPUBLIC RIGHTS OF WAY AND HIGHWAYS TO BE STOPPED UP AND FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

Commencement Information

I1Sch. 4 Pt. 1 in force at 7.12.2022, see art. 1

(1)

Public right of way or highway to be stopped up

(2)

Extent of stopping up

(3)

New highway to be substituted/provided

Footpath LON/90/100For a distance of 60 metres between points 6/4 and 6/5 as shown on Sheet 6 of the streets, rights of way and access plansNew footpath heading south east from points 6/3 to 6/1 on Sheet 6 of the streets, rights of way and access plans.
Footpath LON/88/60For a distance of 210 metres between point 9/2 on Sheet 9 and point 5/2 on Sheet 5 of the streets, rights of way and access plansNew footpath from point 9/2 on Sheet 9 to point 5/2 on Sheet 5 of the streets, rights of way and access plans.
Footpath LON/87/10For a distance of 160 metres between points 4/14 on Sheet 4 and point 8/11 on Sheet 8 of the streets, rights of way and access plansProposed footpath will connect directly onto the new A57 Link Roads ‘Mottram Moor Junctions’ footway (south west corner) via points 4/19, 4/a and 4/18 to point 8/11.
Footpath LON/52/10For a distance of 230 metres between points 2/5 and 2/4 on Sheet 2 of the streets, rights of way and access plansNew footpath connection from points 2/5 to 2/8, new combined footway/cycleway with equestrian use between points 2/8 and 2/6 and new footpath between points 2/6 and 2/4 on Sheet 2 of the streets, rights of way and access plans.
Footpath LON/51/20For a distance of 100 metres between points 2/3 and 2/4 on Sheet 2 of the streets, rights of way and access plansNew combined footway/cycleway with equestrian use connecting points 2/3 to 2/6 and new footpath between points 2/6 and 2/4 on Sheet 2 of the streets, rights of way and access plans.
Footpath LON/50/10For a distance of 160 metres between points 1/42 and 1/44 on Sheet 1 of the streets, rights of way and access plans

New footpath link provided to new combined footway/cycleway with equestrian use between points 1/42 and 1/43.

The new combined footway/cycleway with equestrian use will connect points 1/43 and 1/7, a diversion will then use the new combined footway/cycleway provision at the M67 Junction 4, leaving at point 1/19 and then using the existing footway to reach point 1/8 of the new combined footway/cycleway with equestrian use, which then links back to point 1/44.

An alternative is to travel along the new bridleway between points 1/43 and 2/8 using the proposed Old Mill underpass and travelling past points 2/6 to 1/44.

Footpath LON/52/20For a distance of 380 metres between points 1/45 on Sheet 1 and point 2/4 on Sheet 2 of the streets, rights of way and access plansNew footpath link provided between points 2/7 and 2/6 with the new combined footway/cycleway with equestrian use connecting point 2/6 on Sheet 2, point 1/44 on Sheet 1 and point 1/8 on Sheet 1 of the streets, rights of way and access plans.
Footway along north eastern corner of the M67 Junction 4 roundaboutFor a distance of 135 metres between points 1/4 and 1/19 on Sheet 1 of the streets, rights of way and access plansNew combined footway/cycleway from point 1/4 to 1/1 to 1/26 to 1/25 to 1/24 to 1/23 to 1/21 and 1/19 on Sheet 1 of the streets, rights of way and access plans.
Footway/Shared User Path/crossing along the southern edge of the M67 Junction 4 roundaboutFor a distance of 49 metres between points 1/17 and 1/16 on Sheet 1 of the streets, rights of way and access plansNew combined footway/cycleway from points 1/15 to 1/14 on Sheet 1 of the streets, rights of way and access plans.
Footway/Shared User Path/crossing along the western edge of the M67 Junction 4 roundaboutFor a distance of 52 metres between points 1/38 and 1/37 on Sheet 1 of the streets, rights of way and access plansNew combined footway/cycleway from points 1/1 to 1/27 on Sheet 1 of the streets, rights of way and access plans.
Footway/crossingFor a distance of 25 metres between points 1/6 and 1/19 on Sheet 1 of the Street, Rights of Way and Access PlansNew combined footway/cycleway from point 1/20 to 1/21 to 1/19 on Sheet 1 of the streets, rights of way and access plans.
Footway/crossingFor a distance of 340 metres between point 4/15 on Sheet 4 and point 8/10 on Sheet 8 of the streets, rights of way and access plansNew combined footway/cycleway from point 4/21 to 4/22 to 4/23 on Sheet 4 of the streets, rights of way and access plans and new combined footway/cycleway with equestrian use from points 4/23 to 4/17 and then on combined footway cycleway from point 4/17 to point 8/10 on Sheet 8 of the streets, rights of way and access plans.
Footway/crossingFor a distance of 45 metres between points 4/13 to 4/12 on Sheet 4 of the streets, rights of way and access plansNew combined footway/cycleway from points 4/19 to point 4/9 on the streets, rights of way and access plans.

PART 2E+W+SPRIVATE MEANS OF ACCESS TO BE STOPPED UP AND FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

Commencement Information

I2Sch. 4 Pt. 2 in force at 7.12.2022, see art. 1

(1)

Private means of access to be stopped up

(2)

Extent of stopping up

(3)

New private means of access to be substituted

Carrhouse LaneFor a distance of 70 metres shown between points 5/3 and 5/4 on Sheet 5 on the Streets, Rights of Way and Access PlanWork No. 23
Informal field access off Edge LaneVehicular access point 2/4 on Sheet 2 on the Streets, Rights of Way and Access PlanWork No. 7(v)
Existing maintenance track (multi user)For a distance of 60 metres shown between points 6/4 and 6/5 on Sheet 6 on the Streets, Rights of Way and Access Plan.Work No. 25(i), 25(iii)
Field accessVehicular track access point close to point 1/9 on Sheet 1 on the Streets, Rights of Way and Access PlanWork number 7(i)

PART 3E+W+SALTERATIONS TO PRIVATE MEANS OF ACCESS

Commencement Information

I3Sch. 4 Pt. 3 in force at 7.12.2022, see art. 1

(1)

Private means of access to be altered

(2)

Extent of alteration

Realignment of existing private maintenance access to an electricity pylon from southern point of Edge Lane/ northern access of the M67 Junction 4As shown on Sheet 1 of the works plans, the extent of Work No. 7(i)
Realignment of existing private means of access into agricultural fieldsAs shown on Sheets 1 and 2 of the works plans, the extent of Work No. 7(i), 7(ii), 7(iii), 7(iv), 7(v), 9(i) and 9(ii)
Realignment of existing private means of access into agricultural fields and current ShowgroundAs shown on Sheet 3 of the works plans, the extent of Work No. 11(i) and 11(ii)
Realignment of existing private means of access into agricultural fieldsAs shown on Sheet 5 of the works plans, the extent of Work No. 24
Realignment of existing private means of access to Tara Brook FarmAs shown on Sheet 6 of the works plans, the extent of Work No. 25(iii)
Realignment of existing private means of access to Hope Farm to be created within farmer’s own landAs shown on the Sheet 6 of the works plans, the extent of Work No. 25(iv)
Provision of gated field access to land west of the River EtherowAs shown on Sheet 6 of the works plans the extent of Work No. 30(i)
Realignment of private means of access to Carrhouse Farm to be createdAs shown on Sheet 5 and 6 of the works plans the extent of Work No. 56

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill