2024 No. 958

Infrastructure Planning

The National Grid (Bramford to Twinstead Reinforcement) Order 2024

Made

12th September 2024

Coming into force

4th October 2024

An application under section 37 of the Planning Act 2008(1) (the “2008 Act”) and in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009(2) has been made to the Secretary of State for an Order granting development consent.

The application has been examined by a panel of four members (“the Panel”), appointed pursuant to Chapter 2 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010(3).

The Panel, having examined the application with the documents that accompanied the application, and the representations made and not withdrawn, has, in accordance with section 74(2) of the 2008 Act, submitted a report and recommendation to the Secretary of State.

The Secretary of State, having considered the report and recommendation of the Panel, has taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017(4) and has had regard to the documents and matters referred to in section 104(2) of the 2008 Act.

The Secretary of State is satisfied that the special category land within the Order limits, when burdened with the rights imposed by this Order, will be no less advantageous than it was before to the persons in whom it is vested, other persons, if any, entitled to rights of common or other rights, and to the public; and that, accordingly, section 132(3) of the 2008 Act applies.

The Secretary of State, having decided the application, has determined to make an Order granting development consent for the development described in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.

Accordingly, the Secretary of State, in exercise of the powers in sections 114, 115, 117, 120, 122 and 123 of the 2008 Act, makes the following Order: