Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
12.Conditions of permits: specific conditions for all installations and mobile plant
13.Conditions of permits: specific conditions for Part A installations and Part A mobile plant
14.Conditions of permits: specific conditions for Part B and C installations and mobile plant
15.Conditions of permits: Department’s notice in relation to emissions into water
18.Proposed change in the operation of an installation or mobile plant
22.Surrender of a permit for a Part A installation or Part A mobile plant
23.Surrender of a permit for a Part B or Part C installation or Part B or Part C mobile plant
SCHEDULES
ACTIVITIES, INSTALLATIONS AND MOBILE PLANT
PART 2 INTERPRETATION OF PART 1
1.The following rules apply for the interpretation of Part 1...
2.(1) Subject to sub-paragraph (2), an activity shall not be...
5.References in Part 1 to related activities are references to...
6.(1) This paragraph applies for the purpose of determining whether...
7.(1) Where an activity falls within a description in Part...
8.In Part 1— “background quantity” means, in relation to the...
11.(1) References to a substance listed in this paragraph are...
PART 3 INTERPRETATION OF “PART A INSTALLATION” ETC.
12.For the purpose of these Regulations— “Part A installation” means...
13.For the purpose of these Regulations— “Part A mobile plant”...
14.A Part B installation where an activity falling within paragraph...
15.A Part B installation where an activity falling within paragraph...
17.Where an installation is a Part A installation, a Part...
18.Where an installation is authorised by a permit granted under...
19.In this Part, “Part A activity”, “Part B activity” and...
PART 1 APPLICATIONS FOR PERMITS
1.(1) An application to an enforcing authority for a permit...
1A.Paragraph 1(1) applies in relation to an application for a...
2.An application for a permit to operate a waste incineration...
3.An application for a landfill permit, where an activity falling...
4.(1) An application for a permit to operate an installation...
5.Paragraph 1(1) applies in relation to an application for a...
6.The enforcing authority may, by notice in writing, require the...
7.Subject to paragraph 30, the applicant shall, within the period...
11.Paragraph 7 shall not apply in relation to an application...
PART 2 DETERMINATION OF APPLICATIONS
13.Paragraph 12 does not apply in relation to an application...
14.(1) If the enforcing authority proposes to grant a permit...
15.(1) Any representations made by any persons within the period...
17.(1) The Department may give directions to the enforcing authority...
19.(1) The enforcing authority shall— (a) within a period of...
21.If the enforcing authority fails to give notice of its...
22.Where the Department is aware that the operation of an...
23.(1) Where an application is forwarded to another Member State...
24.Any representations on the draft determination made in the Member...
12.Substances and mixtures which have been proved to possess carcinogenic...
13.Polychlorinated dibenzodioxins and polychlorinated dibenzofurans.
4.Substances and mixtures which have been proved to possess carcinogenic...
5.Persistent hydrocarbons and persistent and bioaccumulable organic toxic substances.
11.Substances which contribute to eutrophication (in particular, nitrates and phosphates)....
12.Substances which have an unfavourable influence on the oxygen balance...
COMPENSATION IN RELATION TO OFF-SITE CONDITIONS
3.Subject to paragraph 6(3) and (5)(b), compensation shall be payable...
4.(1) Subject to sub-paragraph (2), an entitlement to compensation under...
5.(1) An application for compensation under this Schedule shall be...
7.(1) Compensation payable under this Schedule in respect of an...
8.(1) Compensation payable under this Schedule shall carry interest at...
PART 1 APPLICATIONS FOR VARIATION OF CONDITIONS
1.An application under regulation 19(2) for the variation of the...
3.An application under regulation 19(2) for the variation of the...
4.The enforcing authority may, by notice in writing to the...
5.(1) Subject to sub-paragraph (2), this paragraph shall apply where...
6.(1) Subject to paragraph 24(b), an operator notified under paragraph...
7.(1) The Department may give directions to the enforcing authority...
8.(1) Except in a case where an application under regulation...
9.(1) The enforcing authority shall give notice of their draft...
11.If the enforcing authority fails to give notice of its...
12.(1) Subject to paragraph (2), this paragraph applies where the...
13.The chief inspector shall notify the operator of a Part...
14.(1) Subject to paragraph 24(b), an operator notified under paragraph...
15.(1) If the enforcing authority proposes to serve a variation...
16.(1) In the case of a proposed variation notice affecting...
PART 3 TRANSBOUNDARY NOTIFICATION
17.Where the Department is aware that an application or a...
18.Where an application or proposal to serve a variation notice...
19.In determining an application or before serving a variation notice...
20.Any representations on the draft determination made in the Member...
21.(1) For the purposes of this Schedule “working day” means...
4.An operator of an installation, carrying out an activity with...
5.The application for a variation of the conditions of the...
6.An application to an enforcing authority under regulation 10 for...
7.An operator of an installation with a total net thermal...
8.The application for a variation of the conditions of the...
9.An application to an enforcing authority under regulation 10 for...
10.An operator of an installation with a total net thermal...
11.The application for a variation in the conditions of the...
13.Where the exemption specified in paragraph 12(1) applies, the enforcing...
14.Paragraphs 6 to 11 shall not apply to individual installations:...
15.For the purposes of paragraph 14, “connection distance” means—
16.From 31st December 2015, when considering permit applications and applications...
17.Subject to paragraph 19, where a cost-benefit analysis, required pursuant...
18.Subject to paragraph 19, where a cost-benefit analysis required pursuant...
20.The provisions of this Schedule apply to installations covered by...
The Whole Rule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Rule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Rule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Rule and provides information about its policy objective and policy implications. They aim to make the Statutory Rule accessible to readers who are not legally qualified and accompany any Northern Ireland Statutory Rule or Draft Northern Ireland Statutory Rule laid before the UK Parliament during the suspension of the Northern Ireland Assembly.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: