Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
17.—(1) Where an electricity supplier (“the defaulting supplier”) fails to make a relevant payment the revenue collection counterparty may, subject to paragraph (5), require non-defaulting suppliers to pay a share of an amount equal to the amount which was not paid by issuing a notice (“a mutualisation notice”) to each non-defaulting supplier who supplied electricity during the reference period.
(2) For the purposes of this regulation a “non-defaulting supplier” in relation to a mutualisation notice means an electricity supplier who has—
(a)not failed to make any relevant payment within the time limit for making the payment under these Regulations;
(b)failed to make one or more relevant payments all of which have subsequently been paid to the revenue collection counterparty by the time the defaulting supplier was required to make the relevant payment referred to in paragraph (1); or
(c)failed to make one or more relevant payments not all of which have subsequently been paid to the revenue collection counterparty by the time the defaulting supplier was required to make the relevant payment referred to in paragraph (1), but the revenue collection counterparty is of the opinion that it will hold some collateral provided by that supplier by the 5th working day after the day on which the revenue collection counterparty intends to issue that mutualisation notice.
(3) A mutualisation notice must state—
(a)the amount which the defaulting supplier failed to pay;
(b)the date by which the defaulting supplier should have paid that amount;
(c)the amount (“the mutualisation amount”) which the non-defaulting supplier to whom the notice is issued must pay, calculated in accordance with paragraph (7);
(d)the date (“the mutualisation date”) by which the mutualisation amount must be paid, which must be—
(i)in the case of a mutualisation notice issued in respect of a relevant payment which the defaulting supplier was required to make by virtue of regulation 7(1) or 8(2), no earlier than 5 working days after the date on which the notice was issued; or
(ii)in the case of a mutualisation notice issued in respect of any other relevant payment which the defaulting supplier was required to make, no earlier than 30 days after the date on which the notice was issued.
(4) A mutualisation date must be the same for each mutualisation notice issued in respect of a relevant payment which a defaulting supplier failed to pay.
(5) A mutualisation notice may only be issued where the revenue collection counterparty is of the opinion that it will not hold any collateral provided by the defaulting supplier by the 5th working day after the day on which the revenue collection counterparty intends to issue that notice.
(6) Where the revenue collection counterparty has issued a mutualisation notice to an electricity supplier, that supplier must pay the mutualisation amount specified in the notice by the date specified in the notice.
(7) Where an electricity supplier fails to pay all or part of a mutualisation payment in accordance with paragraph (6), that supplier must pay the revenue collection counterparty simple interest on any unpaid amount at the rate specified in regulation 36(1) from the day after the day on which the payment should have been made.
(8) The mutualisation amount to be stated in a mutualisation notice to be issued to a non-defaulting supplier is the amount given by—
where—
DA is the amount which the defaulting supplier failed to pay;
SRES is the amount of electricity supplied by the non-defaulting supplier in the reference period as determined immediately before the notice is issued;
EXE is the amount of EII excluded electricity supplied by the non-defaulting supplier in the reference period as determined immediately before the notice is issued;
NDPE is the total amount of electricity supplied by all non-defaulting suppliers in the reference period as determined immediately before the notice is issued; and
AXE is the total amount of EII excluded electricity supplied by all non-defaulting suppliers in the reference period as determined immediately before the notice is issued.
(9) In this regulation—
(a)“collateral” is to be construed in accordance with regulation 19(7);
(b)“relevant payment” means any payment which an electricity supplier is required to make by virtue of regulation 7(1), 8(2), 10(1), 13(3), 16(3)(a) or 17(6);
(c)the reference period is the most recent period, occurring before the mutualisation notice (to which the reference period relates) has been issued, of 30 consecutive days in respect of which the BSCCo has carried out an Initial Volume Allocation Run; and
(d)the amount of electricity supplied by an electricity supplier in a reference period is the amount of electricity which the BSCCo determines, on the basis of the most recent BSC volume allocation run which the BSCCo has carried out in relation to each day in that period, as the amount of electricity supplied by that supplier in that reference period.
Commencement Information
I1Reg. 17 in force at 23.3.2023, see reg. 1(2)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: