Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
28.—(1) The revenue collection counterparty must exercise its functions in the manner best calculated to ensure the collection of all amounts which are required to be paid or provided by electricity suppliers under these Regulations.
(2) If the revenue collection counterparty considers it may be, or become, unable to fulfil its functions, it must promptly notify the Secretary of State and must provide such further details as the Secretary of State may request.
(3) In paragraphs (1) and (2) “functions” includes—
(a)any function conferred by these Regulations;
(b)the recovery of any sum as a civil debt by virtue of section 19 of the Act; and
(c)any duties or obligations of the revenue collection counterparty under any revenue collection contract.
(4) The revenue collection counterparty must take such steps as it considers necessary to ensure that electricity suppliers are—
(a)informed of their liabilities under these Regulations; and
(b)provided with information about liabilities which they may incur under these Regulations.
(5) Where the revenue collection counterparty writes-off any debt owed to it by an electricity supplier, it must issue a notice of that fact to every electricity supplier who was required to make a payment under regulation 17(6) in relation to that debt.
(6) The revenue collection counterparty must publish information which relates to its estimates of the liabilities of electricity suppliers arising during three consecutive quarterly obligation periods (“the projection period”).
(7) The revenue collection counterparty must publish information under paragraph (6)—
(a)no later than 30 days before the start of the first quarterly obligation period to which that information relates; or
(b)where the revenue collection counterparty reasonably believes that it has received insufficient information from the Authority for the purpose of publishing information under paragraph (6), as soon as reasonably practicable following the receipt of the information the revenue collection counterparty requires.
(8) The information published under paragraph (6) must include—
(a)an estimate of the interim levy rate (see regulation 5(1)) that would apply to each quarterly obligation period during the projection period; and
(b)an estimate of the total reserve amount for each quarterly obligation period during the projection period.
Commencement Information
I1Reg. 28 in force at 23.3.2023, see reg. 1(2)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: