Council Directive 96/48/EC (repealed)Show full title

Council Directive 96/48/EC of 23 July 1996 on the interoperability of the trans-European high-speed rail system (repealed)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes over time for: Council Directive 96/48/EC (repealed) (without Annexes)

 Help about opening options

Version Superseded: 19/07/2010

Status:

EU Directives are published on this site to aid cross referencing from UK legislation. Since IP completion day (31 December 2020 11.00 p.m.) no amendments have been applied to this version.

CHAPTER IU.K.General provisions

[F1Article 1 U.K.

1. The aim of this Directive is to establish the conditions to be met to achieve interoperability within Community territory of the trans-European high-speed rail system as described in Annex I.

These conditions concern the design, construction, placing in service, upgrading, renewal, operation and maintenance of the parts of this system placed in service after  30 April 2004 , as well as the qualifications and health and safety conditions of the staff who contribute to its operation.

2. The pursuit of this objective must lead to the definition of an optimal level of technical harmonisation and make it possible to:

(a) facilitate, improve and develop international rail transport services within Community territory and with third countries;

(b) contribute to the gradual creation of the internal market in equipment and services for the construction, operation, renewal and upgrading of the trans-European high-speed rail system;

(c) contribute to the interoperability of the trans-European high-speed rail system.]

Article 2U.K.

For the purposes of this Directive:

(a)

trans-European high-speed rail system means the structure described in Annex I, composed of the railway infrastructures comprising lines and fixed installations, of the trans-European transport network, constructed or upgraded to be travelled on at high speeds, and rolling stock designed for travelling on those infrastructures;

(b)

interoperability means the ability of the trans-European high-speed rail system to allow the safe and uninterrupted movement of high-speed trains which accomplish the specified levels of performance. This ability rests on all the regulatory, technical and operational conditions which must be met in order to satisfy essential requirements;

(c)

subsystems means that the trans-European high-speed rail system is subdivided, as described in Annex II, into structural or functional subsystems for which essential requirements must be laid down;

(d)

interoperability constituents means any elementary component, group of components, subassembly or complete assembly of equipment incorporated or intended to be incorporated into a subsystem, upon which the interoperability of the trans-European high-speed rail system depends either directly or indirectly;

(e)

essential requirements means all the conditions set out in Annex III which must be met by the trans-European high-speed rail system, subsystems and their interoperability constituents;

(f)

European specification means a common technical specification, a European technical approval or a national standard implementing a European standard, as defined in points 8 to 12 of Article 1 of Directive 93/38/EEC;

(g)

technical specifications for interoperability (hereinafter TSIs) means the specifications by which each subsystem is covered in order to meet the essential requirements by establishing the necessary reciprocal functional relations between the subsystems of the trans-European high-speed rail system and by ensuring the latter's compatibility;

(h)

[F2. . . . .]

(i)

notified bodies means the bodies which are responsible for assessing the conformity or suitability for use of the interoperability constituents or for appraising the EC procedure for verification of the subsystems[F1;]

(j)

[F3basic parameter means any regulatory, technical or operational condition which is critical to interoperability and requires a decision or recommendation in accordance with the procedure laid down in Article 21(2) before any development of complete draft TSIs;

(k)

specific case means any part of the trans-European high-speed rail system which needs special provisions in the TSIs, either temporary or definitive, because of geographical, topographical or urban environment constraints or those affecting compatibility with the existing system. This may include in particular railway lines and networks isolated from the rest of the Community territory, the loading gauge, the track gauge or space between the tracks;

(l)

upgrading means any major modification work on a subsystem or part subsystem which improves the overall performance of the subsystem;

(m)

substitution in the framework of maintenance means any replacement of components by parts of identical function and performance in the framework of preventive or corrective maintenance;

(n)

renewal means any major substitution work on a subsystem or part subsystem which does not change the overall performance of the subsystem;

(o)

existing rail system means the structure composed of the railway infrastructures, comprising lines and fixed installations of the existing rail system plus the existing rolling stock of all categories and origin travelling on that infrastructure;

(p)

placing in service means all the operations by which a subsystem is put into its design operating state.]

Article 3U.K.

1.This Directive applies to the provisions concerning, for each subsystem, the parameters, interoperability constituents, interfaces and procedures as well as the conditions for the overall compatibility of the trans-European high-speed rail system required to achieve its interoperability.

2.The provisions of this Directive shall apply without prejudice to other Community provisions. However, in the case of interoperability constituents, compliance with the essential requirements of this Directive may require the use of the individual European specifications drawn up for that purpose.

Article 4U.K.

1.The trans-European high-speed rail system, subsystems and their interoperability constituents must meet the relevant essential requirements.

2.The further technical specification referred to in Article 18 (4) of Directive 93/38/EEC, which are necessary to supplement European specifications or other standards in use within the Community, must not conflict with the essential requirements.

CHAPTER IIU.K.Technical specifications for interoperability

Article 5U.K.

[F11. Each of the subsystems shall be covered by one TSI. Where necessary, a subsystem may be covered by several TSIs and one TSI may cover several subsystems. The decision to develop and/or to review a TSI and the choice of its technical and geographical scope requires a mandate in accordance with Article 6(1).]

2.The subsystems must conform to the TSIs; this conformity must be permanently maintained while each subsystem is in use.

[F13. To the extent necessary in order to achieve the objectives referred to in Article 1, each TSI shall:

(a) indicate its intended scope (part of network or rolling stock referred to in Annex I, subsystem or part of subsystem referred to in Annex II);

(b) lay down essential requirements for each subsystem concerned and its interfaces vis-à-vis other subsystems;

(c) establish the functional and technical specifications to be met by the subsystem and its interfaces vis-à-vis other subsystems. If need be, these specifications may vary according to the use of the subsystem, for example according to the categories of line and/or rolling stock provided for in Annex I;

(d) determine the interoperability constituents and interfaces which must be covered by European specifications, including European standards, which are necessary to achieve interoperability within the trans-European high speed rail system;

(e) state, in each case under consideration, which procedures are to be used in order to assess the conformity or the suitability for use of the interoperability constituents, on the one hand, or the EC verification of the subsystems, on the other hand. These procedures shall be based on the modules defined in Decision 93/465/EEC;

(f) indicate the strategy for implementing the TSIs. In particular, it is necessary to specify the stages to be completed in order to make a gradual transition from the existing situation to the final situation in which compliance with the TSIs shall be the norm;

(g) indicate, for the staff concerned, the professional competences and health and safety conditions at work required for the operation and maintenance of the subsystem, as well as for the implementation of the TSIs.]

4.The TSIs shall not be an impediment to decisions by the Member States concerning the use of new or upgraded infrastructures for running other trains.

5.Compliance with all the TSIs shall enable a compatible trans-European high-speed rail system to be set up that will preserve, as appropriate, the compatibility of each Member State's existing rail network.

[F36. TSIs may make an explicit, clearly identified reference to European standards or specifications where this is strictly necessary in order to achieve the objectives of this Directive. In such case, these European standards or specifications (or the relevant parts thereof) shall be regarded as annexes to the TSI concerned and shall become mandatory from the moment the TSI is applicable. In the absence of European standards or specifications and pending their development, reference may be made to other clearly identified normative documents; in such case, this shall concern documents that are easily accessible and in the public domain.]

[F1Article 6 U.K.

1. Draft TSIs and subsequent amendments to TSIs shall be drafted under a mandate from the Commission in accordance with the procedure set out in Article 21(2). They shall be drafted under the responsibility of the Agency in accordance with Articles 3 and 12 of Regulation (EC) No 2004/881/EC of the European Parliament and of the Council of 29 April 2004 establishing a European Railway Agency (Agency Regulation) (1) and in cooperation with the Working Parties mentioned in those Articles.

TSIs shall be adopted and reviewed in accordance with the procedure set out in Article 21(2). They shall be published by the Commission in the Official Journal of the European Union.

2. The Agency shall be responsible for preparing the review and updating of TSIs and making any recommendations to the Committee referred to in Article 21 in order to take account of developments in technology or social requirements.

3. Each draft TSI shall be drawn up in two stages.

First of all, the Agency shall identify the basic parameters for the TSI as well as the interfaces with the other subsystems and any other specific cases that may be necessary. The most viable alternative solutions accompanied by technical and economic justification shall be put forward for each of these parameters and interfaces. A decision shall be taken in accordance with the procedure set out in Article 21(2); if necessary, specific cases shall be cited.

The Agency shall then draw up the draft TSI on the basis of these basic parameters. Where appropriate, the Agency shall take account of technical progress, of standardisation work already carried out, of working parties already in place and of acknowledged research work. An overall assessment of the estimated costs and benefits of the implementation of the TSIs shall be attached to the draft TSI; this assessment shall indicate the likely impact for all the operators and economic agents involved.

4. The drafting, adoption and review of each TSI (including the basic parameters) shall take account of the estimated costs and benefits of all the technical solutions considered, together with the interfaces between them, so as to establish and implement the most viable solutions. The Member States shall participate in this assessment by providing the requisite data.

5. The Committee referred to in Article 21 shall be kept regularly informed of the preparatory work on the TSIs. During this work the Committee may formulate any terms of reference or useful recommendations concerning the design of the TSIs and the cost-benefit analysis. In particular, the Committee may, at the request of a Member State, require that alternative solutions be examined and that the assessment of the cost and benefits of these alternative solutions be set out in the report annexed to the draft TSI.

6. On the adoption of each TSI, the date of entry into force of that TSI shall be established in accordance with the procedure set out in Article 21(2). Where different subsystems have to be placed in service simultaneously for reasons of technical compatibility, the dates of entry into force of the corresponding TSIs shall be the same.

7. The drafting, adoption and review of the TSIs shall take account of the opinion of users, as regards the characteristics which have a direct impact on the conditions in which they use the subsystems. To that end the Agency shall consult associations and bodies representing users during the drafting and review phases of the TSIs. They shall enclose with the draft TSI a report on the results of this consultation.

The list of associations and bodies to be consulted shall be finalised by the Committee referred to in Article 21 before it adopts the mandate to review the TSIs and may be re-examined and updated at the request of a Member State or the Commission.

8. The drafting, adoption and review of the TSIs shall take account of the opinion of the social partners as regards the conditions referred to in Article 5(3)(g).

To this end, the social partners shall be consulted before the draft TSI is submitted, for adoption or review, to the Committee referred to in Article 21.

The social partners shall be consulted in the context of the sectoral dialogue committee set up in accordance with Commission Decision 98/500/EC (2) The social partners shall issue their opinion within three months.]

[F1Article 7 U.K.

A Member State need not apply one or more TSIs, including those relating to rolling stock, in the following cases and circumstances:

(a)

for a proposed new line, for the renewal or upgrading of an existing line, or for any element referred to Article 1(1) at an advanced stage of development or the subject of a contract in course of performance when these TSIs are published;

(b)

for any project concerning the renewal or upgrading of an existing line where the loading gauge, track gauge, space between the tracks, or electrification voltage in these TSIs is not compatible with those of the existing line;

(c)

for a proposed new line or for the proposed renewal or upgrading of an existing line in the territory of that Member State when its rail network is separated or isolated by the sea from the rail network of the rest of the Community territory;

(d)

for any proposed renewal, extension or upgrading of an existing line, when the application of these TSIs would compromise the economic viability of the project and/or the compatibility of the rail system in the Member State;

(e)

where, following an accident or a natural disaster, the conditions for the rapid restoration of the network do not economically or technically allow for partial or total application of the relevant TSIs.

In all cases, the Member State concerned shall serve prior notice of its intended derogation to the Commission and shall forward to it a file setting out the TSIs or the parts of TSIs that it does not wish to be applied as well as the corresponding specifications that it does wish to apply. The Commission shall analyse the measures envisaged by the Member State. In cases (b) and (d), the Commission shall take a decision in accordance with the procedure set out in Article 21(2). Where necessary, a recommendation shall be drawn up concerning the specifications to be applied. Nevertheless, in the case of (b) the Commission's decision shall not refer to the loading gauge and the track gauge.]

CHAPTER IIIU.K.Interoperability constituents

Article 8U.K.

Member States shall take all necessary steps to ensure that interoperability constituents:

  • are placed on the market only if they enable interoperability to be achieved within the trans-European high-speed rail system while at the same time meeting the essential requirements;

  • are used in their area of use as intended and are suitably installed and maintained.

These provisions do not exclude the placing on the market of these constituents for other purposes, nor their use for conventional railway lines.

Article 9U.K.

Member States may not, in their territory and on grounds of this Directive, prohibit, restrict or hinder the placing on the market of interoperability constituents for use on the trans-European high-speed rail system if they comply with the Directive.

[F3In particular, they may not require checks which have already been carried out as part of the procedure leading to the EC declaration of conformity or suitability for use.]

Article 10U.K.

1.Member States shall consider as complying with the essential requirements of this Directive applying to them those interoperability constituents which bear the EC declaration of conformity or suitability for use, the components of which are set out in Annex IV.

[F12. All interoperability constituents shall be subject to the procedure for assessing conformity and suitability for the use indicated in the respective TSI and be accompanied by the corresponding certificate.]

[F13. Member States shall consider that an interoperability constituent meets the essential requirements if it complies with the conditions laid down by the corresponding TSI or the European specifications developed to comply with these conditions.]

F24.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F25.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

[F1Article 11 U.K.

Where it appears to a Member State or the Commission that European specifications used directly or indirectly for the purposes of this Directive do not meet the essential requirements, partial or total withdrawal of the specifications concerned from the publications containing them, or their amendment, may be decided upon in accordance with the procedure set out in Article 21(2) after consultation of the Committee set up under Directive 98/34/EC of the European Parliament and of the Council of 22 June 1998 laying down a procedure for the provision of information in the field of technical standards and regulations and of rules on information society services (3) .]

Article 12U.K.

1.Where a Member State confirms that an interoperability constituent covered by the EC declaration of conformity or suitability for use, and placed on the market is likely, when used as intended, not to meet the essential requirements, it shall take all necessary steps to restrict its area of application, prohibit its use or withdraw it from the market. That Member State shall forthwith inform the Commission of the measures taken and shall give the reasons for its decision, stating in particular whether the failure to conform is due to:

  • failure to meet the essential requirements;

  • incorrect application of the European specifications where application of the specifications is invoked;

  • inadequacy of the European specifications.

2.The Commission shall consult the parties concerned as quickly as possible. Where, following that consultation, the Commission establishes that the measure is justified, it shall forthwith so inform the Member State that has taken the initiative and the other Member States. Where, following that consultation, the Commission establishes that the measure is unjustified, it shall forthwith so inform the Member State that has taken the initiative and the manufacturer or his authorized representative established within the Community. Where the decision referred to in paragraph 1 is justified by the existence of a gap in the European specifications, the procedure defined in Article 11 shall apply.

3.Where an interoperability constituent bearing the EC declaration of conformity fails to comply, the competent Member State shall take the appropriate measures against whomsoever has drawn up the declaration and shall inform the Commission and the other Member States thereof.

4.The Commission shall ensure that the Member States are kept informed of the progress and the results of that procedure.

Article 13U.K.

1.In order to draw up the EC declaration of conformity or suitability for use of an interoperability constituent, its manufacturer or his authorized representative established within the Community must apply the provisions laid down in the TSIs referring to it.

2.Where so required by the TSIs, the assessment of conformity or suitability for use of an interoperability constituent shall be appraised by the notified body with which the manufacturer or his authorized representative established within the Community has lodged the application.

3.Where the interoperability constituents are the subject of other Community Directives covering other aspects, the EC declaration of conformity or suitability for use shall, in such instances, state that the interoperability constituents also meet the requirements of those other Directives.

4.Where neither the manufacturer nor his authorized representative established within the Community has met the obligations of the paragraphs 1, 2 and 3, those obligations shall be incumbent on any person who places that interoperability constituent on the market. The same obligations shall apply to any person who assembles interoperability constituents or parts of interoperability constituents having diverse origins or who manufactures the interoperability constituents for his own use, for the purposes of this Directive.

5.Without prejudice to the provisions of Article 12:

(a)in each instance where a Member State finds that the EC declaration of conformity has been drawn up improperly, the manufacturer or his authorized representative established within the Community shall be required to ensure that the conformity of the interoperability constituent is re-established and that the infringement ceases under the conditions laid down by that Member State;

(b)where non-conformity persists, the Member State shall take all appropriate steps to restrict or prohibit the placing on the market of the interoperability constituent in question, or to ensure that it is withdrawn from the market in accordance with the procedures provided for in Article 12.

CHAPTER IVU.K.Subsystems

[F1Article 14 U.K.

1. Each Member State shall authorise the placing in service of those structural subsystems constituting the trans-European high-speed rail system which are located or operated in its territory.

To this end, each Member State shall take all appropriate steps to ensure that these subsystems may be placed in service only if they are designed, constructed and installed in such a way that they do not compromise compliance with the essential requirements concerning them when integrated into the trans-European high-speed rail system.

In particular, each Member State shall check the compatibility of these subsystems with the system into which they are being integrated.

2. Each Member State shall check, when the subsystems are placed in service and at regular intervals thereafter, that they are operated and maintained in accordance with the essential requirements concerning them. To that end, the assessment and verification procedures laid down in the respective structural and functional TSIs shall be used.

3. In the event of renewal or upgrading, the infrastructure manager or the railway undertaking shall send the Member State concerned a file describing the project. The Member State shall examine this file and, taking account of the implementation strategy indicated in the applicable TSI, shall decide whether the size of the works means that a new authorisation for placing in service within the meaning of this Directive is needed.

Such new authorisation for placing in service shall be required whenever the overall safety level of the subsystem concerned may be affected by the works envisaged.

4. Where Member States authorise the placing in service of rolling stock, they shall be responsible for ensuring that an alphanumeric identification code is assigned to each vehicle. This code must be marked on each vehicle and be entered in a national vehicle register that meets the following criteria:

(a) the register shall comply with the common specifications defined in paragraph 5;

(b) the register shall be kept and updated by a body independent of any railway undertaking;

(c) the register shall be accessible to the safety authorities and the investigating bodies designated in Articles 16 and 21 of Directive 2004/49/EC of the European Parliament and of the Council of 29 April 2004 on safety on the Community's railways (Railway Safety Directive) (4) ; it shall also be made accessible, in response to any legitimate request, to the regulatory bodies designated in Article 30 of Directive 2001/14/EC of the European Parliament and of the Council of 26 February 2001 on the allocation of railway infrastructure capacity and the levying of charges for the use of railway infrastructure and safety certification (5) , to the Agency, to the railway companies and to the infrastructure managers.

In case of rolling stock placed in service for the first time in a third country, Member States may accept vehicles clearly identified according to a different coding system. However, once a Member State has authorised the placing in service of such vehicles on its territory, it must be possible to retrieve the corresponding data, listed below in paragraph 5(c), (d) and (e), through the register.

5. The common specifications for the register shall be adopted in accordance with the procedure set out in Article 21(2), on the basis of the draft specifications prepared by the Agency. These draft specifications shall include: content, data format, functional and technical architecture, operating mode, and rules for data input and consultation. The register shall contain at least the following information:

(a) references to the EC declaration of verification and the issuing body;

(b) references to the register of rolling stock mentioned in Article 22a;

(c) identification of the owner of the vehicle or the lessee;

(d) any restrictions on how the vehicle may be used;

(e) safety-critical data relating to the maintenance schedule of the vehicle.]

Article 15U.K.

Without prejudice to Article 19, Member States may not, in their territory and on grounds of this Directive, prohibit, restrict or hinder the construction, placing in service and operation of structural subsystems constituting the trans-European high-speed rail system which satisfy the essential requirements.

[F3In particular, they may not require checks which have already been carried out as part of the procedure leading to the EC declaration of verification.]

Article 16U.K.

1.Member States shall consider as being interoperable and meeting the essential requirements concerning them those structural subsystems constituting the trans-European high-speed rail system which are covered by the EC declaration of verification.

2.Verification of the interoperability, in accordance with the essential requirements, of a structural subsystem constituting the trans-European high-speed rail system shall be established by reference to TSIs where these exist.

[F13. In the absence of TSIs, and including cases when a derogation has been notified under Article 7, Member States shall send the other Member States and the Commission, for each subsystem, a list of the technical rules in use for implementing the essential requirements. This shall be notified by  30 April 2005 and thereafter each time the list of technical rules is changed. On that occasion, Member States shall also designate the bodies responsible for carrying out, in the case of these technical regulations, the verification procedure referred to in Article 18.]

Article 17U.K.

If it emerges that the TSIs do not fully meet the essential requirements, the Committee referred to in Article 21 may be consulted at the request of a Member State or on the initiative of the Commission.

[F3In such a case, the TSIs shall be reviewed in accordance with Article 6(2). If certain technical aspects corresponding to the essential requirements cannot be explicitly covered in a TSI, they shall be clearly identified in an annex to the TSI. Article 16(3) shall apply to these aspects.]

Article 18U.K.

1.In order to draw up the EC declaration of verification, the awarding authority or its official representative shall cause the EC checking procedure to be appraised by the notified body chosen by it for that purpose.

2.The activities of the notified body responsible for the EC verification of a subsystem shall begin at the design stage and shall cover all of the manufacturing period up to the type-approval stage before a subsystem is placed in service.

[F3They shall also cover verification of the interfaces of the subsystem in question in relation to the system in which it is integrated, on the basis of the information available in the respective TSI and the registers defined in Article 22a.]

3.The notified body shall be responsible for compiling the technical file that has to accompany the EC declaration of verification. The technical file must contain all the necessary documents relating to the characteristics of the subsystem and, where appropriate, all the documents certifying conformity of the constituents of interoperability. It must also contain all of the elements relating to the conditions and limits of use and to the instructions concerning servicing, constant or routine monitoring, adjustment and maintenance.

Article 19U.K.

1.Where a Member State finds that a structural subsystem covered by the EC declaration of verification accompanied by the technical file does not fully comply with this Directive and in particular does not meet the essential requirements, it may request that additional checks be carried out.

2.The Member State making the request shall forthwith inform the Commission of any additional checks requested and set out the reasons which justify them. The Commission shall without delay initiate the procedure provided for in Article 21 (2).

CHAPTER VU.K.Notified bodies

Article 20U.K.

1.Member States shall notify the Commission and the other Member States of the bodies responsible for carrying out the procedure for the assessment of conformity or suitability for use referred to in Article 13 and the checking procedure referred to in Article 18, indicating each body's area of responsibility.

The Commission shall assign identification numbers to them. It shall publish in the Official Journal of the European Communities the list of bodies, their identification numbers and the tasks entrusted to them, and shall ensure that the list is kept updated.

2.Member States shall apply the criteria provided for in Annex VII for the assessment of the bodies to be notified. Bodies meeting the assessment criteria provided for in the relevant European standards shall be deemed to meet the said criteria.

3.A Member State shall withdraw approval from a body which no longer meets the criteria referred to in Annex VII. It shall forthwith inform the Commission and the other Member States thereof.

4.Should a Member State or the Commission consider that a body notified by another Member State no longer meets the relevant criteria, the matter shall be referred to the Committee provided for in Article 21, which shall deliver its opinion within three months; in the light of the Committee's opinion, the Commission shall inform the Member State concerned of all the changes needed if the notified body is to maintain the status awarded to it.

[F15. The Commission shall set up a notified bodies coordination group (hereinafter the coordination group) which shall discuss any matter relating to the application of the procedures for assessing conformity or suitability for the use referred to in Article 13 and the verification procedure referred to in Article 18, or to the application of the relevant TSIs. Member States representatives may take part in the work of the coordination group as observers.

The Commission and the observers shall inform the committee referred to in Article 21 of the work carried out in the framework of the coordination group. The Commission, when appropriate, will propose the measures needed to remedy the problems.

Where necessary, coordination of the notified bodies shall be implemented in accordance with Article 21.]

CHAPTER VIU.K.Committee

[F1Article 21 U.K.

1. The Commission shall be assisted by a committee.

2. Where reference is made to this paragraph, Articles 5 and 7 of Council Decision 1999/468/EC of 28 June 1999 laying down the procedures for the exercise of implementing powers conferred on the Commission (6) shall apply, having regard to the provisions of Article 8 thereof.

The period laid down in Article 5(6) of Decision 1999/468/EC shall be set at three months.

3. The Committee shall adopt its rules of procedure.

4. Should it prove necessary, the Committee may set up working parties to assist it in carrying out its tasks, in particular with a view to coordinating the notified bodies.]

[F3Article 21a U.K.

1. The Committee may discuss any matter relating to the interoperability of the trans-European high-speed rail system, including questions relating to interoperability between this system and the rail system of third countries.

2. The Committee may discuss any matter relating to the implementation of this Directive. If necessary, the Commission shall adopt an implementing recommendation in accordance with the procedure set out in Article 21(2).

Article 21b U.K.

1. The Commission may decide, on its own initiative or at the request of a Member State, in accordance with the procedure set out in Article 21(2), to mandate the drafting of a TSI for an additional subject, insofar as it concerns a subsystem mentioned in Annex II.

2. In accordance with the procedure set out in Article 21(2), the Committee shall, on the basis of a proposal by the Commission, adopt a work programme conforming to the objectives of this Directive and Directive 2001/16/EC of the European Parliament and of the Council of 19 March 2001 on the interoperability of the trans-European conventional rail system (7) .

Article 21c U.K.

Annexes II to VI may be amended in accordance with the procedure set out in Article 21(2).]

CHAPTER VIIU.K.Final provisions

Article 22U.K.

Any decision taken pursuant to this Directive concerning the assessment of conformity or suitability for use of interoperability constituents, the checking of subsystems constituting the trans-European high-speed rail system and any decision taken pursuant to Articles 11, 12, 17 and 19 shall set out in detail the reasons on which it is based. It shall be notified as soon as possible to the party concerned, together with an indication of the remedies available under the laws in force in the Member States concerned and of the time limits allowed for the exercise of such remedies.

[F3Article 22a U.K.

1. Member States shall ensure that a register of infrastructure and a register of rolling stock are published and updated annually. These registers shall indicate the main features of each subsystem or part subsystem involved, e.g. the basic parameters, and their correlation with the features laid down by the applicable TSIs. To that end, each TSI shall indicate precisely which information must be included in the registers of infrastructure and of rolling stock.

2. A copy of those registers shall be sent to the Member States concerned and to the Agency and shall be made available for consultation by interested parties, including at least the professional actors from the sector.]

Article 23U.K.

1.Member States shall amend and adopt their laws, regulations and administrative provisions so as to authorize the use of interoperability constituents and the putting into service and operation of subsystems which comply with this Directive no later than 30 months after entry into force of this Directive. They shall forthwith inform the Commission thereof.

2.When Member States adopt the provisions referred to in paragraph 1, they shall contain a reference to this Directive or be accompanied by such reference on the occasion of their official publication. The methods of making such reference shall be laid down by Member States.

Article 24U.K.

Every two years the Commission shall report to the European Parliament and the Council on the progress made towards achieving interoperability of the trans-European high-speed rail system.

Article 25U.K.

This Directive shall enter into force on the 21st day following that of its publication in the Official Journal of the European Communities

[X1Article 26 U.K.

This Directive is addressed to the Member States.]

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources