- Latest available (Revised)
- Original (As adopted by EU)
Regulation (EC) No 715/2009 of the European Parliament and of the Council of 13 July 2009 on conditions for access to the natural gas transmission networks and repealing Regulation (EC) No 1775/2005 (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Regulation (EC) No 715/2009 of the European Parliament and of the Council.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Article 4.European network of transmission system operators for gas
Article 6.Establishment of provision corresponding to network codes
Article 12.Regional cooperation of transmission system operators
Article 14.Third-party access services concerning transmission system operators
Article 15.Third-party access services concerning storage and LNG facilities
Article 16.Principles of capacity-allocation mechanisms and congestion-management procedures concerning transmission system operators
Article 17.Principles of capacity-allocation mechanisms and congestion-management procedures concerning storage and LNG facilities
Article 18.Transparency requirements concerning transmission system operators
Article 19.Transparency requirements concerning storage facilities and LNG facilities
Article 26.Right of Member States to provide for more detailed measures
Article 28A.Regulations made by the Secretary of State: consultation and procedure
Article 28B.Regulations made by the Northern Ireland department: consultation and procedure
1. Third-party access services concerning transmission system operators
1. Transmission system operators shall offer firm and interruptible services down...
2. Harmonised transport contracts and common network codes shall be designed...
3. Transmission system operators shall develop network codes and harmonised contracts...
5. Transmission system operators shall harmonise formalised request procedures and response...
6. Transmission system operators shall not separately charge network users for...
7. Information requests that require extraordinary or excessive expenses such as...
8. Transmission system operators shall cooperate with other transmission system operators...
9. Transmission system operators shall publish at least annually, by a...
10. Transmission system operators shall maintain and make available to the...
2. Those mechanisms and procedures shall take into account the integrity...
3. Those mechanisms and procedures shall neither hamper the entry of...
4. Those mechanisms and procedures shall provide appropriate economic signals for...
5. Network users shall be advised about the type of circumstance...
6. Should difficulties in meeting contractual delivery obligations arise due to...
2.2. Congestion management procedures in the event of contractual congestion
2.2.2. Capacity increase through oversubscription and buy-back scheme
1. Transmission system operators shall propose and, after approval by the...
2. The oversubscription and buy-back scheme shall provide transmission system operators...
3. The oversubscription and buy-back scheme shall be based on an...
4. For the purpose of determining transmission system operators’ revenues, technical...
5. In determining the additional capacity, the transmission system operator shall...
6. Where necessary to maintain system integrity, transmission system operators shall...
7. Transmission system operators shall, before applying a buy-back procedure, verify...
8. When proposing the oversubscription and buy-back scheme the transmission system...
2.2.3. Firm day-ahead use-it-or-lose-it mechanism
1. The national regulatory authority shall require transmission system operators to...
2. If the national regulatory authority considers that a situation as...
4. The original holder of the contracted capacity may renominate the...
5. Paragraph 3 shall not apply to network users ... holding...
6. On interconnection points where a firm day-ahead use-it-or-lose-it mechanism in...
7. The national regulatory authority may decide to implement a firm...
2.2.5. Long-term use-it-or-lose-it mechanism
1. The national regulatory authority shall require transmission system operators to...
2. The application of a firm day-ahead use-it-or-lose-it mechanism shall not...
3. Withdrawal shall result in the network user losing its contracted...
4. Transmission system operators shall regularly provide the national regulatory authority...
3. Definition of the technical information necessary for network users to...
3.1. Definition of the technical information necessary for network users to...
3.2. Definition of all relevant points for transparency requirements
3.3. Information to be published at all relevant points and the...
(1) At all relevant points, transmission system operators shall publish the...
(2) At all relevant points, the information under paragraph 3.3(1)(a), (b)...
(3) At all relevant points, transmission system operators shall publish historical...
(4) Transmission system operators shall publish measured values of the gross...
(5) For all relevant points, transmission system operators shall publish available...
3.4. Information to be published regarding the transmission system and the...
(1) Transmission system operators shall ensure the publication on a daily...
(2) Transmission system operators shall publish harmonised conditions under which capacity...
(3) Regarding the balancing service of its system, each transmission system...
(4) Where flexibility services, other than tolerances, are offered for third...
(5) Transmission system operators shall publish, per balancing zone, the amount...
(7) Transmission system operators shall keep at the disposal of the...
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: