Commission Delegated Regulation (EU) No 1268/2012 of 29 October 2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union (repealed)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
Version Superseded: 01/01/2017
Point in time view as at 01/01/2016.
There are currently no known outstanding effects for the Commission Delegated Regulation (EU) No 1268/2012 (repealed).
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
This Regulation lays down the rules of application for Regulation (EU, Euratom) No 966/2012 (hereinafter ‘the Financial Regulation’).
Where interest is due to the budget, the agreement concluded with the entities or persons listed in points (ii) to (viii) of Article 58(1)(c) of the Financial Regulation shall stipulate that pre-financing is paid to bank accounts or sub-accounts which allow the funds and related interest to be identified. Otherwise, the accounting methods of the recipients or intermediaries must make it possible to identify the funds paid by the Union and the interest or other benefits yielded by those funds.
Provisions of this Regulation concerning interest on pre-financing shall be without prejudice to the entry of pre-financing on the assets side of financial statements, as laid down in the accounting rules referred to in Article 143 of the Financial Regulation.
The commitment appropriations and payment appropriations authorised for the financial year shall consist of:
appropriations provided in the budget, including by amending budgets;
appropriations carried over;
appropriations made available again in accordance with Articles 178 and 182 of the Financial Regulation;
appropriations arising from pre-financing payments which have been repaid in accordance with Article 177(3) of the Financial Regulation;
appropriations provided following the receipt of revenue assigned during the financial year or during previous financial years and not used.
1.The commitment appropriations and the non-differentiated appropriations relating to building projects referred to in Article 13(2)(a) of the Financial Regulation may be carried over only if the commitments could not be made before 31 December of the financial year for reasons not attributable to the authorising officer and if the preparatory stages are sufficiently advanced to make it reasonable to surmise that the commitment will be made by no later than 31 March of the following year, or 31 December for building projects.
2.The preparatory stages referred to in Article 13(2)(a) of the Financial Regulation, which should be completed by 31 December of the financial year in order to allow a carryover to the following year, are in particular:
(a)for global commitments within the meaning of Article 85 of the Financial Regulation, the adoption of a financing decision or the closing by that date of the consultation of the departments concerned within each institution for the adoption of the decision;
(b)for individual commitments within the meaning of Article 85 of the Financial Regulation, the completion of the selection of potential contractors, beneficiaries, prize winners or delegatees.
3.Appropriations carried over in accordance with Article 13(2)(a) of the Financial Regulation which have not been committed by 31 March of the following financial year or up to 31 December of the following year for amounts relating to building projects shall be automatically cancelled.
The Commission shall inform the European Parliament and Council of the appropriations cancelled in this way within one month following the cancellation in accordance with the first subparagraph.
4.Appropriations carried over in accordance with Article 13(2)(b) of the Financial Regulation may be used until 31 December of the following financial year.
5.The accounts shall identify appropriations carried over in accordance with paragraphs 1 to 4.
1.Without prejudice to specific provisions arising from the application of sector-specific regulations, conversion by the responsible authorising officer shall be made using the daily euro exchange rate published in the C series of the Official Journal of the European Union.
Where conversion between the euro and another currency is to be made by the contractors or beneficiaries, the specific arrangements for conversion contained in procurement contracts, grant agreements or financing agreements shall apply.
2.In order to avoid that currency conversion operations have a significant impact on the level of the Union co-financing or a detrimental impact on the Union budget, the specific arrangements for conversion referred to in paragraph 1 shall provide, if appropriate, for a rate of conversion between the euro and other currencies to be calculated using the average of the daily exchange rate in a given period.
3.If no daily euro exchange rate is published in the Official Journal of the European Union for the currency in question, the responsible authorising officer shall use the accounting rate referred to in paragraph 4.
4.For the purposes of the accounts provided for in Articles 151 to 156 of the Financial Regulation and subject to Article 240 of this Regulation, conversion between the euro and another currency shall be made using the monthly accounting rate of the euro. That accounting exchange rate shall be established by the Commission’s accounting officer by means of any source of information he regards as reliable, on the basis of the exchange rate on the penultimate working day of the month preceding that for which the rate is established.
5.The results of the currency operations referred to in paragraph 4 of this Article shall be shown under a separate heading in the respective institution’s accounts.
The first subparagraph of this paragraph shall apply mutatis mutandis to bodies referred to in Article 208 of the Financial Regulation.
1.Without prejudice to specific provisions deriving from the application of sector-specific regulations, or from specific procurement contracts, grant agreements or grant decisions and financing agreements, the rate to be used for conversion between the euro and other currencies shall, in cases where the conversion is carried out by the responsible authorising officer, be that of the day on which the payment order or recovery order is drawn up by the authorising department.
2.In case of euro imprest accounts, the rate to be used for the conversion between the euro and other currencies shall be determined by the date of the payment by the bank.
3.For the regularisation of imprest accounts in national currencies, as referred to in Article 19 of the Financial Regulation, the rate to be used for the conversion between the euro and other currencies shall be that of the month of the expenditure from the imprest account concerned.
4.For the reimbursement of flat-rate expenditure, or expenditure arising from the Staff Regulations of Officials of the European Union and the Conditions of Employment of Other Servants of the European Union (hereinafter ‘Staff Regulations’) which is fixed at a ceiling, and which is paid in a currency other than the euro, the rate to be used shall be that which is in force when the entitlement arises.
1.Without prejudice to Articles 9 and 10, the structure to accommodate assigned revenue in the budget shall comprise:
(a)in the statement of revenue of each institution’s section, a budget line to receive the revenue;
(b)in the statement of expenditure, the budget remarks, including general remarks, shall show which lines may receive the appropriations corresponding to the assigned revenue which are made available.
In the case referred to in point (a) of the first subparagraph, a token entry ‘pro memoria’ shall be made and the estimated revenue shall be shown for information in the remarks.
2.The appropriations corresponding to assigned revenue shall be made available automatically, both as commitment appropriations and as payment appropriations, when the revenue has been received by the institution, save in any of the following cases:
(a)in cases provided for in Article 181(2) and 183(2) of the Financial Regulation;
(b)in the case provided for in Article 21(2)(b) of the Financial Regulation for Member States where the contribution agreement is expressed in euro.
In the case referred to in point (b) of the first subparagraph, commitment appropriations may be made available upon signature by the Member State of the contribution agreement.
1.The Member States’ contributions to the financing of certain supplementary research programmes, provided for in Article 5 of Council Regulation (EC, Euratom) No 1150/2000(1) shall be paid as follows:
(a)seven twelfths of the sum entered in the budget shall be paid by no later than 31 January of the current financial year;
(b)the remaining five twelfths shall be paid by no later than 15 July of the current financial year.
2.Where the budget has not been finally adopted before the start of a financial year, the contributions provided for in paragraph 1 shall be based on the sum entered in the budget for the previous financial year.
3.Any contribution or additional payment owed by the Member States to the budget shall be entered in the Commission’s account or accounts within 30 calendar days of the call for funds.
4.Payments made shall be entered in the account provided for in Regulation (EC, Euratom) No 1150/2000 and shall be subject to the conditions laid down by that Regulation.
1.The budget structure to accommodate the participation of the Member States of the European Free Trade Association (hereinafter ‘EFTA States’) in certain Union programmes shall be as follows:
(a)in the statement of revenue, a line with a token entry ‘pro memoria’ shall be entered to accommodate the full amount of the EFTA States’ contribution for the financial year in question.
(b)in the statement of expenditure:
the remarks for each line relating to the Union activities in which the EFTA States participate shall show ‘for information’ the estimated amount of the participation;
an annex, forming an integral part of the budget, shall set out all the lines covering the Union activities in which the EFTA States participate.
For the purposes of point (a) of the first subparagraph the estimated amount shall be shown in the budget remarks.
The annex referred to in point (b)(ii) of the first subparagraph reflects and is part of the structure to accommodate the appropriations corresponding to such participation, as provided for in paragraph 2, and to allow the expenditure to be implemented.
2.Under Article 82 of the Agreement on the European Economic Area (hereinafter ‘EEA Agreement’) the amounts of the annual participation of the EFTA States, as confirmed to the Commission by the Joint Committee of the European Economic Area in accordance with Article 1(5) of Protocol 32 annexed to the EEA Agreement, shall give rise to the provision, at the start of the financial year, of the full amounts of the corresponding commitment appropriations and payment appropriations.
3.If, in the course of the financial year, additional appropriations are provided on the budget lines with EFTA State participation without the EFTA States being able, during that year, to adjust their contributions accordingly in order to comply with the ‘proportionality factor’ provided for in Article 82 of the EEA Agreement, the Commission may, as a provisional and exceptional measure, use its cash resources to pre-finance the share of the EFTA States. Whenever such additional appropriations are provided, the Commission shall, as soon as possible, call in the corresponding contributions from the EFTA States. The Commission shall inform the European Parliament and Council each year of any such decisions taken.
The pre-financing shall be regularised as soon as possible in the budget for the following financial year.
4.In accordance with Article 21(2)(e) of the Financial Regulation, the financial contributions of the EFTA States shall constitute external assigned revenue. The accounting officer shall adopt appropriate measures to ensure that use of the revenue arising from those contributions and of the corresponding appropriations is monitored separately.
In the report provided for in Article 150(2) of the Financial Regulation, the Commission shall show separately the stage of implementation, in both revenue and expenditure, corresponding to EFTA State participation.
The budget structure to accommodate the proceeds of the sanctions referred to in Section 4 of Council Regulation (EC) No 1467/97(2) shall be as follows:
in the statement of revenue, a line carrying a token entry ‘pro memoria’ shall be entered to accommodate the interest on such amounts;
at the same time, and without prejudice to Article 77 of the Financial Regulation, entry of those amounts in the statement of revenue shall give rise to the provision, in the statement of expenditure, of commitment appropriations and payment appropriations.
The appropriations referred to in point (b) of the first subparagraph shall be implemented in accordance with Article 20 of the Financial Regulation.
For the purposes of the authorisation of the European Parliament and of the Council referred to in Article 22(2) of the Financial Regulation, the Commission shall estimate and duly explain the financial charges, including follow-up costs, entailed by the acceptance of donations made to the Union.
Any taxes borne by the Union under Article 23(2) and 23(3)(a) of the Financial Regulation shall be entered in a suspense account until they are refunded by the States concerned.
1.The percentages referred to in Article 25 of the Financial Regulation shall be calculated at the time the request for transfer is made and with reference to the appropriations provided in the budget, including amending budgets.
2.The amount to be taken into consideration shall be the sum of the transfers to be made on the line from which transfers are being made, after adjustment for earlier transfers made.
The amount corresponding to the transfers which can be carried out autonomously by the institution concerned without a decision of the European Parliament and Council shall not be taken into consideration.
1.The percentages referred to in Article 26(1) of the Financial Regulation shall be calculated at the time the request for transfer is made and with reference to the appropriations provided in the budget, including amending budgets.
2.The amount to be taken into consideration shall be the sum of the transfers to be made on the line from which or to which transfers are being made, after adjustment for earlier transfers made.
The amount corresponding to the transfers which can be carried out autonomously by the Commission without a decision of the European Parliament and the Council shall not be taken into consideration.
The expenditure referred to in point (b) of the first subparagraph of Article 26(1) of the Financial Regulation shall cover, for each policy area, the items referred to in Article 44(3) of the Financial Regulation.
Proposals for transfers and all information for the European Parliament and Council concerning transfers made under Articles 25 and 26 of the Financial Regulation shall be accompanied by appropriate and detailed supporting documents showing the implementation of appropriations and estimates of requirements up to the end of the financial year, both for the lines to which the appropriations are to be transferred and for those from which they are to be taken.
Proposals for transfers to allow the utilisation of the emergency aid reserve, referred to in Article 29 of the Financial Regulation, shall be accompanied by appropriate and detailed supporting documents showing:
for the line to which the transfer is to be made, the most recent information available for the implementation of appropriations and the estimate of requirements up to the end of the financial year;
for all lines relating to external action, the implementation of appropriations up to the end of the month preceding the request for transfer and an estimate of requirements up to the end of the financial year, including a comparison with the initial estimate;
an analysis of the possibilities of reallocating appropriations.
1.All proposals for programmes or activities occasioning budget expenditure shall be the subject of an ex ante evaluation, which shall address:
(a)the need to be met in the short or long term;
(b)the added value of Union involvement;
(c)the policy and management objectives to be achieved, which include measures necessary to safeguard the financial interests of the Union in the field of fraud prevention, detection, investigation, reparation and sanctions;
(d)the policy options available, including the risks associated with them;
(e)the results and impacts expected, in particular economic, social and environmental impacts, and the indicators and evaluation arrangement needed to measure them;
(f)the most appropriate method of implementation for the preferred option(s);
(g)the internal coherence of the proposed programme or activity and its relations with other relevant instruments;
(h)the volume of appropriations, human resources and other administrative expenditure to be allocated with due regard for the cost-effectiveness principle;
(i)the lessons learned from similar experiences in the past.
2.The proposal shall set out the arrangements for monitoring, reporting and evaluation, taking due account of the respective responsibilities of all levels of government that will be involved in the implementation of the proposed programme or activity.
3.All programmes or activities, including pilot projects and preparatory actions, where the resources mobilised exceed EUR 5 000 000 shall be the subject of an interim and/or ex post evaluation in terms of the human and financial resources allocated and the results obtained in order to verify that they were consistent with the objectives set, as follows:
(a)the results obtained in carrying out a multiannual programme shall be periodically evaluated in accordance with a timetable which enables the findings of that evaluation to be taken into account for any decision on the renewal, modification or suspension of the programme;
(b)activities financed on an annual basis shall have their results evaluated at least every six years.
Points (a) and (b) of the first subparagraph shall not apply to each of the projects or actions conducted within those activities, for which the requirement may be met by the final reports sent by the bodies which carried out the action.
4.The evaluations referred to in paragraphs 1 and 3 shall be proportionate to the resources mobilised for and the impact of the programme and activity concerned.
The financial statement shall contain the financial and economic data for the assessment by the legislative authority of the need for Union action. It shall provide appropriate information as regards coherence with other activities of the Union and any possible synergy.
In the case of multiannual operations, the financial statement shall contain the foreseeable schedule of annual requirements in terms of appropriations and posts, including for external staff, and an evaluation of their medium-term financial impact.
As soon as possible and no later than four weeks after the final adoption of the budget, the final detailed budget figures shall be published in all languages on the internet site of the institutions, on the Commission’s initiative, pending official publication in the Official Journal of the European Union.
1.The information on recipients of Union’s funds awarded under direct management shall be published on an internet site of the Union institutions, no later than 30 June of the year following the financial year in which the funds were awarded.
In addition to the publication referred to in the first subparagraph the information may also be published, according to a standard presentation, by other appropriate means.
2.The following information shall be published unless otherwise provided in this Regulation and in the sector specific rules, taking into account the criteria set out in Article 35(3) of the Financial Regulation:
(a)the name of the recipient;
(b)the locality of the recipient;
(c)the amount awarded;
(d)the nature and purpose of the measure.
For the purpose of point (b) the term ‘locality’ shall mean:
the address of the recipient when the latter is a legal person;
the Region on NUTS 2 level when the recipient is a natural person.
As far as personal data referring to natural persons are concerned, the information published shall be removed two years after the end of the financial year in which the funds were awarded. The same shall apply to personal data referring to legal persons for whom the official title identifies one or more natural persons.
3.The information referred to in paragraph 2 shall only be published for prizes, grants and contracts which have been awarded as a result of contests or grant award procedures or public procurement procedures. The information shall not be published for:
(a)scholarships paid to natural persons and other direct support paid to natural persons in most need, referred to in Article 125(4)(c) of the Financial Regulation;
(b)contracts below the amount referred to in Article 137(2) of this Regulation.
4.The publication shall be waived if such disclosure risks threatening the rights and freedoms of individuals concerned as protected by the Charter of Fundamental Rights of the European Union or harm the commercial interests of the recipients.
Where the management of Union funds is delegated to the authorities and bodies referred to in Article 58(1)(c) of the Financial Regulation, the delegation agreements shall require that information referred to in paragraphs 2 and 3 of Article 21 is published according to a standard presentation, by those entrusted authorities and bodies on their website.
The internet site of the Union institutions shall contain a reference at least of the address of the website where the information can be found if it is not published directly in the dedicated place of the internet site of the Union institutions.
In addition to the publication referred to in the first subparagraph the information may also be published, according to a standard presentation, by any other appropriate means.
Paragraphs 2 to 4 of Article 21 shall apply to the publication referred to in the first paragraph of this Article.
The financial programming referred to in Article 38 of the Financial Regulation shall be structured by category of expenditure, policy area and budget line. The complete financial programming shall cover all categories of expenditure with the exception of agriculture, cohesion policy and administration for which only summary data shall be provided.
Draft amending budgets shall be accompanied by statements of grounds and the information on the implementation of the budget for the preceding and current financial years available at the time of their establishment.
The budget nomenclature shall comply with the principles of specification, transparency and sound financial management. It shall provide clarity and transparency necessary for the budgetary process, facilitating the identification of the main objectives as reflected in the relevant legal bases, making possible choices on political priorities and enabling efficient and effective implementation.
For the purposes of establishing the budget, actual expenditure in the last financial year for which the accounts have been closed shall be determined as follows:
in commitments: commitments entered in the accounts during the financial year against appropriations for that financial year as defined in Article 3;
in payments: payments made during the financial year, that is to say, for which a payment order has been sent to the bank, against appropriations for that financial year as defined in Article 3.
The budget remarks shall include:
the references of the basic act, where one exists;
all appropriate explanations concerning the nature and purpose of the appropriations.
The staff of the Supply Agency shall appear separately in the Commission establishment plan.
In any call made in the context of grants, procurement or prizes implemented in direct management, potential beneficiaries, candidates, tenderers and participants shall, in accordance with Regulation (EC) No 45/2001 of the European Parliament and of the Council(3) be informed that, for the purposes of safeguarding the financial interests of the Union, their personal data may be transferred to internal audit services, to the European Court of Auditors, to the Financial Irregularities Panel or to the European Anti-Fraud Office (hereinafter ‘OLAF’) and between authorising officers of the Commission and the executive agencies.
The financing of measures agreed by the Council for the preparation of Union crisis management operations under Title V of the Treaty on European Union shall cover incremental costs directly arising from a specific field deployment of a mission or team involving inter alia personnel from the Union institutions, including high risk insurance, travel and accommodation costs and per diem payments.
1.The articles of the Treaty on the Functioning of the European Union (hereinafter ‘TFEU’) which directly confer specific powers on the Commission are as follows:
(a)Article 154 (social dialogue);
(b)Article 156 (studies, opinions and consultations on social matters);
(c)Articles 159 and 161 (special reports on social matters);
(d)Article 168(2) (initiatives to promote coordination on health protection matters);
(e)Article 171(2) (initiatives to promote coordination on trans-European networks);
(f)Article 173(2) (initiatives to promote coordination on matters relating to industry);
(g)Article 175, second subparagraph (report on progress made towards achieving economic, social and territorial cohesion);
(h)Article 181(2) (initiatives to promote coordination on research and technological development);
(i)Article 190 (report on research and technological development);
(j)Article 210(2) (initiatives to promote coordination of development cooperation policies);
(k)Article 214(6) (initiatives to promote coordination on humanitarian aid measures).
2.The articles of the Treaty Establishing the European Atomic Energy Community (hereinafter ‘Euratom Treaty’) which directly confer specific powers on the Commission are as follows:
(a)Article 70 (financial support, within the limits set by the budget, for prospecting programmes in the territories of the Member States);
(b)Articles 77 to 85.
3.In the presentation of the draft budget, further detail may be added to the lists set out in paragraphs 1 and 2, with an indication of the articles in question and the amounts involved.
1.[F1Acts likely to be affected by a conflict of interests within the meaning of Article 57(2) of the Financial Regulation may, inter alia, take one of the following forms without prejudice to their qualification as illegal activities under point (d) of Article 106(1) of the Financial Regulation:]
(a)granting oneself or others unjustified direct or indirect advantages;
(b)refusing to grant a beneficiary the rights or advantages to which that beneficiary is entitled;
(c)committing undue or wrongful acts or failing to carry out acts that are mandatory.
Other acts likely to be affected by a conflict of interests are those which may impair the impartial and objective performance of a person’s duties such as, inter alia, the participation in an evaluation committee for a public procurement or grant procedure when the person may, directly or indirectly, benefit financially from the outcome of these procedures.
2.A conflict of interest shall be presumed to exist if an applicant, candidate or tenderer is a member of staff covered by the Staff Regulations, unless his participation in the procedure has been authorised in advance by his superior.
3.In the event of a conflict of interests, the authorising officer by delegation shall take appropriate measures to avoid any undue influence of the person concerned on the process or procedure in question.
Textual Amendments
F1 Substituted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
The accounting system of the Commission shall identify the management mode and, under each management mode, the type of entity or person listed in Article 58(1)(c) of the Financial Regulation entrusted with tasks of budget implementation.
As regards direct management by the Commission according to Article 58(1)(a) of the Financial Regulation, the accounting system shall distinguish management by the following:
departments of the Commission;
executive agencies;
heads of Union delegations;
trust funds referred to in Article 187 of the Financial Regulation.
Where the Commission implements the budget directly in its departments, implementation tasks shall be performed by the financial actors within the meaning of Articles 64 to 75 of the Financial Regulation and in compliance with the conditions laid down in this Regulation.
1.Decisions to delegate powers to executive agencies shall authorise them, as authorising officers by delegation, to implement appropriations relating to the Union programme the management of which is entrusted to them.
2.The Commission’s instrument of delegation shall contain at least the provisions as provided for in points (a) to (d) and (h) of Article 40. It shall be formally accepted in writing by the director on behalf of the executive agency.
Where the Commission entrusts tasks to private bodies under Article 63(2) of the Financial Regulation, it shall conclude a contract in accordance with Title V of Part One and Part Two Title IV Chapter III of the Financial Regulation.
The Commission shall compile a register of bodies responsible for management, certification and audit activities under the sector-specific regulations.
In order to promote best practices in the implementation of the Structural Funds, the Cohesion Fund, the European Agricultural Fund for Rural Development, the European Agricultural Guarantee Fund and the European Fisheries Fund, the Commission may make available for information purposes to bodies responsible for management and control activities a methodological guide setting out its own control strategy and approach, including checklists, and best practice examples. This guide shall be updated whenever it proves necessary.
1.The Commission may accept that procurement rules and procedures are equivalent to its own if the following conditions are met:
(a)they comply with the principle of broad competition of tenderers to obtain the best value for money, and negotiated procedures are limited to reasonable amounts or are duly justified;
(b)they ensure transparency with adequate ex ante publication, in particular of calls for tenders, and adequate ex post publication of contractors;
(c)they ensure equal treatment, proportionality and non-discrimination;
(d)they prevent conflicts of interests throughout the entire procurement procedure.
National law of Member States or third countries transposing Directive 2004/18/EC shall be considered equivalent to the rules applied by the institutions in accordance with the Financial Regulation.
2.The Commission may accept that grant rules and procedures are equivalent to its own if the following conditions are met:
(a)they comply with the principles of proportionality, sound financial management, equal treatment and non-discrimination;
(b)they ensure transparency with adequate publication of calls for proposals, direct award procedures being limited to reasonable amounts or being duly justified, and adequate ex post publication of beneficiaries taking account of the principle of proportionality;
(c)they prevent conflicts of interests throughout the entire grant award procedure;
(d)they provide that grants may not be cumulative or awarded retrospectively, that they must, as a rule, involve co-financing and that they may not have the purpose or the effect of producing a profit for the beneficiary.
3.The Commission may accept that the accounting systems and the internal control systems used by entities and persons to be entrusted with budget implementation tasks on behalf of the Commission are providing equivalent levels of protection of the financial interests of the Union and of reasonable assurance of achieving the management objectives if they comply with the principles laid down in Article 32 of the Financial Regulation.
For the purposes of the ex ante assessment pursuant to Article 61(1) of the Financial Regulation, the authorising officer responsible may rely on an ex ante assessment made by another authorising officer provided that their conclusions are relevant to the specific risks of the tasks to be entrusted, in particular their nature and the amounts involved.
The authorising officer responsible may rely on an ex ante assessment made by other donors as far as this assessment was made with regard to conditions equivalent to those for indirect management set out in Article 60 of the Financial Regulation.
Delegation agreements shall include detailed arrangements ensuring the protection of the financial interests of the Union and the transparency of operations carried out. They shall include at least the following:
a clear definition of the tasks assigned and the limits thereof, concerning in particular the modification of the tasks entrusted, the waiving of debts, the use of funds reimbursed or unused;
conditions and detailed arrangements for performing the tasks, responsibilities and organising the controls to be carried out, including the evaluation of the programmes;
conditions for payments of the Union contribution, including the reimbursement of costs incurred in respect of implementation as well as the remuneration of the entrusted entity, together with rules on which supporting documents are required to justify the payments;
rules on reporting to the Commission on how the tasks are performed, the results expected, irregularities which occurred and the measures taken, the conditions under which payments may be suspended or interrupted as well as the conditions under which performance of the tasks terminates;
the date, by which individual contracts and agreements which implement the delegation agreement shall be concluded, which shall be commensurate with the nature of the tasks entrusted;
[F1rules which allow the entity or person to exclude economic operators which are in a situation referred to in points (d) and (f) of Article 106(1) and in point (b) of Article 107 of the Financial Regulation from participating in procurement, grant or prize award procedures or from being awarded procurement contracts, grants or prizes and rules which allow the entity or person to impose a financial penalty to these economic operators;]
detailed arrangements for Commission scrutiny as well as provisions granting the Commission, OLAF and the Court of Auditors access to the information that is required for them to perform their duties, as well as the power to conduct audits and investigations including on the spot-checks;
[F1arrangements providing for:
an undertaking of the entrusted entity to inform the Commission without delay of fraud or irregularity as referred to in points (d) and (f) of Article 106(1) of the Financial Regulation occurring in the management of Union funds and the measures taken;]
the designation of a contact point which shall have the appropriate powers to cooperate directly with OLAF in order to facilitate the latter’s operational activities;
conditions governing the use of bank accounts and of the interest yielded as provided for in Article 8(4) of the Financial Regulation;
provisions guaranteeing the visibility of Union action in relation to the other activities of the body.
[F2In the case of point (f) of the first paragraph, for the purpose of Article 106(5) of the Financial Regulation, a third country is considered in failure to act, inter alia, where its national legislation does not allow to exclude an economic operator from all EU financed award procedures within the meaning of Article 106 of the Financial Regulation. The delegation agreements specify where a third country is considered in failure to act.
For the purpose of point (h)(i) of the first paragraph, in the case of third countries and international organisations, these arrangements specify where the third country and the international organisation shall prevent, detect, correct and notify irregularities and fraud in accordance Article 60(3) of the Financial Regulation.]
Textual Amendments
F1 Substituted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
F2 Inserted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
In case of actions terminating before the end of the financial year concerned, the final report of the entrusted entity or person for such action may replace the management declaration referred to in Article 60(5)(b) of the Financial Regulation, provided it is submitted before 15 February of the year following the financial year concerned.
Where international organisations and third countries implement non-multiannual actions limited to 18 months, the compliance statement referred to in Article 60(5) of the Financial Regulation may be incorporated in the final report.
1.Without prejudice to specific provisions contained in sector specific rules, the procedures referred to in points (b) and (c) of Article 60(6) of the Financial Regulation shall include:
(a)desk reviews and, where appropriate, on-the-spot checks by the Commission;
(b)the establishment by the Commission of the amount of expenditure recognised as accepted, following, where necessary, a contradictory procedure with the authorities and bodies and after these authorities and bodies have been informed;
(c)where appropriate, calculation by the Commission of financial corrections;
(d)recovery or payment by the Commission of the balance arising from the difference between accepted expenditure and the sums already paid to the authorities or bodies.
For the purposes of point (d) of the first subparagraph, the Commission shall recover amounts due preferably by offsetting as set out in Article 87.
2.Where budget implementation tasks are entrusted to an entity implementing a multi-donor action, the procedures referred to in points (b) and (c) of Article 60(6) of the Financial Regulation shall consist in verifying that an amount corresponding to that paid by the Commission for the action concerned has been used by the entity for the action and that the expenditure has been incurred in accordance with the obligations laid down in the agreement signed with the entity.
For the purpose of this Regulation, multi-donor action shall mean any action where Union funds are pooled with at least one other donor.
1. The international organisations referred to in point (ii) of Article 58(1)(c) of the Financial Regulation shall be international public-sector organisations set up by international agreements and specialised agencies set up by such organisations.
The agreements referred to in the first subparagraph shall be submitted to the authorising officer responsible for the ex ante assessment referred to in Article 39 before the Commission entrusts tasks of budget implementation.
2. The following organisations shall be assimilated to international organisations:
(a) the International Committee of the Red Cross;
(b) the International Federation of National Red Cross and Red Crescent Societies.
3. The Commission may adopt a duly justified decision assimilating a non-profit organisation to an international organisation providing that it satisfies the following conditions:
(a) it has its own legal personality and autonomous governance bodies;
(b) it has been established to perform specific tasks of general international interest;
(c) at least six Member State are members of the non-profit organisation;
(d) it provides adequate financial guarantees;
(e) it operates on the basis of a permanent structure and in accordance with systems, rules and procedures which may be assessed in accordance with Article 61(1) of the Financial Regulation.
4. Where the Commission implements the budget under indirect management with international organisations, the verification agreements concluded with them shall apply.]
Textual Amendments
F1 Substituted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
1.The public law bodies or bodies governed by private law with a public-service mission shall be subject to the law of the Member State or the country in which they have been set up.
2.In cases of management by a network, requiring the designation of at least one body or entity by Member State or by country concerned, the body or entity shall be designated by the Member State or the country concerned in accordance with the basic act.
In all other cases, the Commission shall designate such bodies or entities in agreement with the Member States or countries concerned.
1.Each institution shall provide each financial actor with the resources required to perform his duties and a charter describing in detail his tasks, rights and obligations.
2.Heads of Union delegations acting as authorising officers by subdelegation in accordance with Article 56(2) of the Financial Regulation shall be subject to the charter provided by the Commission for the implementation of the financial management tasks subdelegated to them.
The authorising officer responsible may be assisted in his duties by staff entrusted, under his responsibility, with certain operations required for the implementation of the budget and production of the financial and management information. In order to prevent any conflict of interests, staff assisting authorising officers by delegation or subdelegation shall be subject to the obligations referred to in Article 57 of the Financial Regulation.
Heads of Union delegations acting as authorising officers by subdelegation in accordance with the second paragraph of Article 56(2) of the Financial Regulation may be assisted in their duties by staff of the Commission.
In accordance with the Financial Regulation and this Regulation, each institution shall lay down in its internal rules such measures for the management of appropriations as it considers necessary for proper implementation of its section of the budget.
Heads of Union delegations acting as authorising officers by subdelegation in accordance with the second paragraph of Article 56(2) of the Financial Regulation shall be subject to the internal rules of the Commission for the implementation of the financial management tasks subdelegated to them.
The authorising officer shall set up paper based or electronic systems for the keeping of original supporting documents relating to and subsequent to budget implementation and budget implementation measures. The systems shall provide for:
such documents to be numbered;
such documents to be dated;
registers, which may be computerised, to be kept identifying the exact location of such documents;
such documents to be kept for at least five years from the date on which the European Parliament grants discharge for the budgetary year to which the documents relate;
keeping of documents relating to pre-financing guarantees for the institution and of a log to enable such guarantees to be adequately monitored.
Documents relating to operations not definitively closed shall be kept for longer than provided for in point (d) of the first paragraph, that is to say, until the end of the year following that in which the operations are closed.
Personal data contained in supporting documents shall be deleted where possible when those data are not necessary for budgetary discharge, control and audit purposes. Article 37(2) of Regulation (EC) No 45/2001 shall apply to the conservation of traffic data.
1.Initiation of an operation shall be understood as all the operations which are normally carried out by the staff referred to in Article 46 and which are preparatory to the adoption of the acts implementing the budget by the authorising officer responsible.
2.Ex ante verification of an operation shall be understood as all the ex ante checks put in place by the authorising officer responsible in order to verify its operational and financial aspects.
3.Ex ante controls shall verify the coherence among supporting documents requested and any other information available.
The extent in terms of frequency and intensity of the ex ante controls shall be determined by the authorising officer responsible taking into account risk-based and cost-effectiveness considerations. In case of doubt, the authorising officer responsible for validating the relevant payment shall request complementary information or perform an on-the-spot control in order to obtain reasonable assurance as part of the ex ante control.
The purpose of the ex ante controls shall be to ascertain that:
(a)the expenditure and revenue are in order and comply with the provisions applicable, in particular those of the budget and the relevant regulations and of any acts adopted in implementation of the Treaties or regulations and, where appropriate, the terms of contracts;
(b)the principle of sound financial management referred to in Chapter 7 of Title II of Part One of the Financial Regulation is applied.
For the purpose of controls, a series of similar individual transactions relating to routine expenditure on salaries, pensions, reimbursement of mission expenses and medical expenses may be considered by the authorising officer responsible to constitute a single operation.
4.The ex post controls may be carried out on the basis of documents and, where appropriate, on the spot.
The ex post controls shall verify that operations financed by the budget are correctly implemented and in particular that the criteria referred to in paragraph 3 are complied with.
The outcomes of ex post controls shall be reviewed by the authorising officer by delegation at least annually to identify any potential systemic issues. The authorising officer by delegation shall take measures to address those issues.
The risk analysis referred to in Article 66(6) of the Financial Regulation shall be reviewed in the light of the results of controls and other relevant information.
In case of multiannual programmes, the authorising officer by delegation shall establish a multiannual control strategy, specifying the nature and extent of controls over the period and the manner how the results are to be measured year-on-year for the annual assurance process.
1.The staff designated by the authorising officer responsible to verify financial operations shall be chosen on the grounds of their knowledge, skills and particular qualifications as evidenced by diplomas or by appropriate professional experience, or after an appropriate training programme.
2.Each institution shall draw up a code of professional standards which determine, on matters of internal control:
(a)the level of technical and financial competence required of the staff referred to in paragraph 1;
(b)the obligation for such staff to undergo continuous training;
(c)the mission, role and tasks allocated to them;
(d)the rules of conduct, in particular the standards of ethics and integrity that they must comply with and the rights they enjoy.
3.Heads of Union delegations acting as authorising officers by subdelegation in accordance with the second paragraph of Article 56(2) of the Financial Regulation shall be subject to the Commission code of professional standards referred to in paragraph 2 of this Article for the implementation of the financial management tasks subdelegated to them.
4.Each institution shall put in place the appropriate structures to distribute to authorising departments and update periodically appropriate information concerning the control standards and the methods and techniques available for that purpose.
Failure by the authorising officer by delegation to take action, as referred to in Article 66(8) of the Financial Regulation, shall mean the absence of any reply within a reasonable time given the circumstances of the case and, in any event, within a month at most.
The authorising officer by delegation shall send the accounting officer, in accordance with the rules adopted by the latter, the financial and management information required for the performance of the accounting officer’s duties.
The accounting officer shall be informed, regularly and at least for the closure of the accounts, by the authorising officer of the relevant financial data of the fiduciary bank accounts in order to allow the use of Union funds to be reflected in the accounts of the Union.
Authorising officers by delegation shall record, for each financial year, contracts concluded by the negotiated procedures referred to in points (a) to (f) of Article 134(1) and Article 266 of this Regulation. If the proportion of negotiated procedures in relation to the number of contracts awarded by the same authorising officer by delegation increases appreciably in relation to earlier years or if that proportion is distinctly higher than the average recorded for the institution, the authorising officer responsible shall report to the institution setting out any measures taken to reverse that trend. Each institution shall send a report on negotiated procedures to the European Parliament and Council. In the case of the Commission, that report shall be annexed to the summary of the annual activity reports referred to in Article 66(9) of the Financial Regulation.]
Textual Amendments
F1 Substituted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
1.Each institution shall appoint an accounting officer from officials subject to the Staff Regulations of Officials of the European Union.
The accounting officer shall be chosen by the institution on the grounds of his particular competence as evidenced by diplomas or by equivalent professional experience.
2.Two or more institutions or bodies may appoint the same accounting officer.
In such case, they shall make the necessary arrangements in order to avoid any conflict of interest.
1.A trial balance shall be drawn up without delay in the event of termination of the duties of the accounting officer.
2.The trial balance accompanied by a handing over report shall be transmitted by the accounting officer who is terminating his duties or, if it is not possible, by an official in his department to the new accounting officer.
The new accounting officer shall sign the trial balance in acceptance within one month from the date of transmission and he may make reservations.
The handing over report shall also contain the result of the trial balance and any reservations made.
3.Each institution or body referred to in Article 208 of the Financial Regulation shall inform the European Parliament, the Council and the accounting officer of the Commission within two weeks of the appointment or termination of duties of its accounting officer.
The responsible authorising officer shall notify the accounting officer of all developments or significant modifications of a financial management system, an inventory system or a system for the valuation of assets and liabilities, if it provides data for the accounts of the institution or is used to substantiate data thereof, so that the accounting officer can verify compliance with the validation criteria.
At any time, the accounting officer may reexamine a financial management system already validated. Where a financial management system set up by the authorising officer is not or is no longer validated by the accounting officer, the responsible authorising officer shall establish an action plan in order to correct, in due time, weaknesses for which the validation has been rejected.
The responsible authorising officer shall be responsible for the completeness of information transmitted to the accounting officer.
1.The accounting officer shall ensure that his institution has at its disposal sufficient funds to cover the cash requirements arising from budgetary implementation.
2.For the purposes of paragraph 1, the accounting officer shall set up cash management systems enabling him to draw up cash-flow forecasts.
3.The accounting officer of the Commission shall divide up the funds available in accordance with Regulation (EC, Euratom) No 1150/2000.
1.For the requirements of treasury management, the accounting officer may open accounts in the name of the institution with financial institutions or national central banks or cause such accounts to be opened. In duly warranted circumstances, the accounting officer may open accounts in currencies other than the euro.
2.The accounting officer shall be responsible for closing accounts referred to in the paragraph 1 or for ensuring that such accounts are closed.
3.The accounting officer shall set the operating terms for accounts referred to in paragraph 1 with financial institutions, in accordance with the principles of sound financial management, efficiency and competitive tendering.
4.At least every five years the accounting officer shall relaunch competitive tendering between financial institutions with which accounts could be opened in accordance with paragraph 1.
Where local banking conditions allow for it, imprest related bank accounts opened with financial institutions located outside the Union shall be regularly subject to a competitive survey. Such a survey shall be undertaken, at least every five years, at the initiative of the imprest account holder, who then shall submit to the accounting officer a substantiated proposal for the selection of a bank for a period not exceeding five years.
5.The accounting officer shall ensure strict compliance with the operating terms for accounts opened with financial institutions in accordance with paragraph 1.
For imprest related bank accounts opened with financial institutions located outside the Union, the imprest account holder shall assume this responsibility taking into account the applicable legislation in the country where that holder exercises his mandate.
6.The accounting officer of the Commission shall inform the accounting officers of the other institutions and of the bodies referred to in Article 208 of the Financial Regulation, on the operating terms of accounts opened with financial institutions. The accounting officers of the other institutions and of the bodies referred to in Article 208 of the Financial Regulation shall harmonise, with those operating terms, the operating terms of the accounts they open.
The terms governing the opening, operation and use of accounts shall provide, depending on internal control requirements, that cheques, bank credit transfer orders or any other banking operations must be signed by one or more duly authorised members of staff. Manual instructions shall be signed by at least two duly authorised members of staff, or by the accounting officer in person.
For the purposes of the first subparagraph, the accounting officer of each institution shall communicate to all financial institutions with which the institution concerned has opened accounts the names and specimen signatures of the authorised members of staff.
1.The accounting officer shall ensure that the balance on the bank accounts provided for in Article 58 does not deviate significantly from the cash-flow forecasts referred to in Article 57(2) and in any event:
(a)that none of those accounts is in debit;
(b)that the balance of accounts held in other currencies is periodically converted into euro.
2.The accounting officer may not maintain balances in foreign currency accounts which might cause excessive losses to the institution as a result of exchange rate fluctuations.
Without prejudice to Article 69, the accounting officer shall conduct transfers between accounts opened by him in the name of the institution with financial institutions, and conduct currency conversion operations.
Payments shall be made by bank credit transfer, by cheque or, from imprest accounts by debit card in accordance with Article 67(4).
1.The accounting officer may make payments by bank credit transfer only if the payee’s bank account details and information confirming the payee’s identity, or any modification, have first been entered in a common file by institution.
Any such entry in the file of the payee’s legal and bank account details or modification of those details shall be based on a supporting document, the form of which shall be defined by the accounting officer.
2.With a view to payment by bank credit transfer, authorising officers may enter into a commitment towards a third party on behalf of their institution only if that third party has provided the documentation required for its entry in the file.
Authorising officers shall inform the accounting officer of any change in the legal and bank account details communicated to them by the payee and shall check that these details are valid before a payment is made.
In connection with pre-accession aid, individual commitments may be concluded with the public authorities in the countries applying for accession to the European Union without a prior entry in the third-party file. In such cases the authorising officer shall do his utmost to ensure that the entry is made as quickly as possible. The agreements shall provide that communication to the Commission of the payee’s bank account details is a condition to be fulfilled before the first payment can be made.
Supporting documents for the accounting system and for the preparation of the accounts referred to in Article 141 of the Financial Regulation shall be kept for at least five years from the date on which the European Parliament grants discharge for the budgetary year to which the documents relate.
However, documents relating to operations not definitively closed shall be kept for longer, that is to say, until the end of the year following that in which the operations are closed. Article 37(2) of Regulation (EC) No 45/2001 shall apply to the conservation of traffic data.
Each institution shall decide in which department the supporting documents are to be kept.
Each institution shall lay down the conditions in accordance with which the staff it designates and empowers to administer accounts in the local units referred to in Article 72 are authorised to communicate the names and specimen signatures to local financial institutions.
1.Where, owing to the limited amounts involved, it is materially impossible or inefficient to carry out payment operations by budgetary procedures, imprest accounts may be set up for the payment of such expenditure.
2.The imprest administrator may provisionally validate and pay expenditure, on the basis of a detailed framework set out in the instructions from the authorising officer responsible. Those instructions shall specify the rules and conditions under which the provisional validation and payments shall be carried out and, where appropriate, the terms for signing legal commitments within the meaning of Article 97(1)(e).
3.The creation of an imprest account and the appointment of an imprest administrator shall be the subject of a decision by the accounting officer, on a duly substantiated proposal from the authorising officer responsible. That decision shall set out the respective responsibilities and obligations of the imprest administrator and the authorising officer.
Amendment of the operating terms for an imprest account shall also be the subject of a decision by the accounting officer on a duly substantiated proposal from the authorising officer responsible.
4.In Union delegations, imprest accounts shall be set up for the payment of expenditure from both the Commission section of the budget and the European External Action Service (hereinafter ‘EEAS’) section of the budget, ensuring full traceability of expenditure.
1.The decision setting up an imprest account and appointing an imprest administrator and the decision amending the operating terms for an imprest account shall specify in particular:
(a)the maximum amount which may be initially provided as an imprest, and its purpose;
(b)whether a bank account or post office giro account is to be opened in the name of the institution;
(c)the nature and maximum amount of each item of expenditure which may be paid by the imprest administrator to third parties or collected from them;
(d)the frequency with which supporting documents must be produced, the procedure for producing them and the arrangements for transmitting them to the authorising officer for settlement;
(e)the procedure to be followed if the imprest has to be replenished;
(f)that imprest transactions will be settled by the authorising officer by no later than the end of the following month, so that the accounting balance and the bank balance can be reconciled;
(g)the period of validity of the authorisation given to the imprest administrator by the accounting officer;
(h)the identity of the appointed imprest administrator.
2.In proposals for decisions setting up imprest accounts the authorising officer responsible shall ensure that:
(a)priority is given to the use of budgetary procedures where there is access to the central computerised accounting system;
(b)imprest accounts are used only in substantiated cases.
The maximum amount which may be paid by the imprest administrator where it is materially impossible or inefficient to carry out payment operations by budgetary procedures shall not exceed EUR 60 000 for each item of expenditure.
3.The imprest administrator may make payments to third parties on the basis and within the limits of:
(a)prior budgetary and legal commitments signed by the authorising officer responsible;
(b)the positive residual balance of the imprest account, in cash or at the bank.
4.Payments from imprest accounts may be made by bank credit transfer, including the direct debit system referred to in Article 89 of the Financial Regulation, cheque or other means of payment, including debit cards, in accordance with the instructions laid down by the accounting officer.
5.Payments made shall be followed by formal final validation decisions and/or payment orders signed by the authorising officer responsible.
Imprest administrators shall be chosen from officials or, should the need arise and only in duly substantiated cases, from other members of staff. Imprest administrators shall be chosen on the grounds of their knowledge, skills and particular qualifications as evidenced by diplomas or by appropriate professional experience, or after an appropriate training programme.
1.The accounting officer shall make payments endowing imprest accounts and shall monitor those accounts from the point of view of opening of bank accounts and delegation of signatures and controls on the spot and in the centralised accounts. The accounting officer shall endow the imprest accounts. Imprests shall be paid to the bank account opened for the imprest.
Imprest accounts may also be endowed directly by miscellaneous local revenue such as that arising from:
(a)sales of equipment;
(b)publications;
(c)miscellaneous repayments;
(d)interest.
The imprest shall be regularised, in terms of expenditure or miscellaneous or assigned revenue, in accordance with the decision setting up the imprest account referred to in Article 67 and the provisions of the Financial Regulation. The amounts in question shall be deducted by the authorising officer when he subsequently replenishes the imprest accounts concerned.
2.In order, in particular, to avoid any exchange losses, the imprest administrator may make transfers between different bank accounts relating to the same imprest.
1.The imprest administrator shall keep an account of the funds at his disposal, in cash and at the bank, and of payments made and amounts received, in accordance with the rules and on the instructions given by the accounting officer. Statements of that account shall be accessible at all times to the authorising officer responsible and a list of transactions shall be established at least once a month and be sent in the following month together with supporting documents by the imprest administrator to the authorising officer responsible for settlement of the imprest operations.
2.The accounting officer shall carry out, or have carried out by a staff member in his own department or in the authorising department specially empowered for that purpose, checks, which must as a general rule be effected on the spot and without warning, to verify the existence of the funds allocated to the imprest administrators and the bookkeeping and to check that imprest transactions are settled within the time limit set. The accounting officer shall communicate the findings of those checks to the authorising officer responsible.
Payments made from imprest accounts may, within the limits laid down in Article 137(3), consist simply in the payment of costs against invoices, without prior acceptance of a tender.
For the payment of certain categories of expenditure, one or more imprest accounts may be set up in each local unit outside the Union in accordance with Article 70 of the Financial Regulation. A local unit shall be, for instance, a Union delegation, office or branch office in a third country.
The decision setting up such an imprest account shall lay down its operating terms in accordance with Article 70 of the Financial Regulation and on the basis of the specific needs of each local unit.
In exceptional circumstances and for the purposes of continuity of service, the duties of EEAS imprest administrator in the Union delegations may be performed by staff of the Commission. Under the same conditions, the staff of the EEAS may be designated as imprest administrators for the Commission in the Union delegations.
In Union delegations the rules and conditions laid down in first subparagraph shall apply to the appointment of persons authorised by the accounting officer to carry out banking operations.
The authorities and bodies referred to in Articles 66(8) and 72(2) of the Financial Regulation shall be understood as the bodies designated in the Staff Regulations and the decisions of the Union institutions concerning the terms and conditions for internal investigations in relation to the prevention of fraud, corruption and any other illegal activity detrimental to the Union’s interests.
Without prejudice to the powers of OLAF, the Financial Irregularities Panel referred to in Article 29 (hereinafter ‘the Panel’) shall be competent in respect of any infringement of a provision of the Financial Regulation or of a provision relating to financial management or the checking of operations resulting from an act or omission of a member of staff.
1.Cases of financial irregularities as referred to in Article 75 of this Regulation shall be referred to the Panel by the appointing authority for an opinion referred to in the second subparagraph of Article 73(6) of the Financial Regulation.
Where Heads of Union delegations act as authorising officers by subdelegation in accordance with Article 56(2) of the Financial Regulation, the responsible authorising officer may refer directly to the Panel for an opinion on cases of financial irregularities as referred to in Article 75 of this Regulation.
An authorising officer by delegation may refer a matter to the panel if he considers that a financial irregularity has occurred. The Panel shall deliver an opinion evaluating whether irregularities within the meaning of Article 75 have occurred, how serious they are and what their consequences might be. Where the Panel’s analysis suggests that the case referred to it is a matter for OLAF, it shall transmit the file to the appointing authority without delay and shall inform OLAF at once.
When the Panel is directly informed of a matter by a member of staff in accordance with Article 66(8) of the Financial Regulation, it shall transmit the file to the appointing authority and shall inform the member of staff accordingly. The appointing authority may request the Panel’s opinion on the case.
2.The institution or, in the case of a joint Panel, the participating institutions shall, depending on its or their own internal organisation, specify the operating arrangements of the Panel and its composition, which shall include an external participant with the required qualifications and expertise.
1.An authorising officer by delegation or subdelegation who receives a binding instruction which he considers to be irregular or contrary to the principle of sound financial management, in particular because the instruction cannot be carried out with the resources allocated to him, shall, in writing, so inform the authority from which he received the delegation or subdelegation. If the instruction is confirmed in writing and that confirmation is received in good time and is sufficiently clear, in that it refers explicitly to the points which the authorising officer by delegation or subdelegation has challenged, the authorising officer may not be held liable. He shall carry out the instruction, unless it is manifestly illegal or constitutes a breach of the relevant safety standards.
2.Paragraph 1 shall also apply in cases where an authorising officer learns, in the course of acting on a binding instruction, that the circumstances of the case may give rise to an irregular situation.
Any instructions confirmed in the circumstances described in Article 73(3) of the Financial Regulation shall be recorded by the authorising officer by delegation responsible and mentioned in his annual activity report.
The authorising officer shall draw up a schedule indicating when the own resources defined in the Decision on the system of the Union’s own resources will be made available to the Commission.
Own resources shall be established and recovered in accordance with the rules adopted pursuant to the Decision referred to in the first paragraph.
1.Estimates of amounts receivable shall specify the type of revenue and the budget item to which they are to be booked and, as far as possible, the particulars of the debtor and the estimated amount.
When drawing up an estimate of amounts receivable, the authorising officer responsible shall check in particular that:
(a)the revenue is booked to the correct budget item;
(b)the estimate is in order and complies with the provisions applicable and the principle of sound financial management.
2.Subject to Articles 181(2) and 183(2) of the Financial Regulation and Article 7(2) of this Regulation, an estimate of amounts receivable shall not have the effect of making commitment appropriations available. In the cases referred to in Article 21 of the Financial Regulation, appropriations may be made available only after the sums due have actually been recovered by the Union.
1.The establishment by the authorising officer responsible of an amount receivable shall constitute recognition of the right of the Union in respect of a debtor and establishment of entitlement to demand that the debtor pay the debt.
2.The recovery order shall be the operation by which the authorising officer responsible instructs the accounting officer to recover the amount established.
3.The debit note shall be to inform the debtor that:
(a)the Union has established the amount receivable;
(b)if payment of the debt is made before the deadline, no default interest will be due;
(c)failing reimbursement by the deadline referred to in point (b) the debt shall bear interest at the rate referred to in Article 83, without any prejudice to any specific regulations applicable;
(d)failing reimbursement by the deadline referred to in point (b) the institution shall effect recovery either by offsetting or by enforcement of any guarantee lodged in advance;
(e)the accounting officer may effect recovery by offsetting before the deadline referred to in point b), where it is necessary to protect the Union’s financial interests when he has justified grounds to believe that the amount due to the Commission would be lost, after the debtor has been informed of the reasons and date of the recovery by offsetting;
(f)if, after taking all the steps set out in points (a) to (e) of this subparagraph, the amount has not been recovered in full, the institution shall effect recovery by enforcement of a decision secured either in accordance with Article 79(2) of the Financial Regulation or by legal action.
The Authorising officer shall print out the debit note and send it to the debtor. The accounting officer shall be informed of that dispatch through the financial information system.
To establish an amount receivable the authorising officer responsible shall ensure that:
the receivable is certain, meaning that it is not subject to any condition;
the receivable is of fixed amount, expressed precisely in cash terms;
the receivable is due and is not subject to any payment time;
the particulars of the debtor are correct;
the amount to be recovered is booked to the correct budget item;
the supporting documents are in order; and
the principle of sound financial management is complied with, in particular with regard to the criteria referred to in point (a) of Article 91(1).
1.The establishment of an amount receivable shall be based on supporting documents certifying the Union’s entitlement.
2.Before establishing an amount receivable the authorising officer responsible shall personally check the supporting documents or, on his own responsibility, shall ascertain that this has been done.
3.The supporting documents shall be kept by the authorising officer in accordance with Article 48.
1.Without prejudice to any specific provisions deriving from the application of sector-specific regulations, any amount receivable not repaid on the deadline referred to in Article 80(3)(b) shall bear interest in accordance with paragraphs 2 and 3 of this Article.
2.The interest rate for amounts receivable not repaid on the deadline referred to in Article 80(3)(b) shall be the rate applied by the European Central Bank to its principal refinancing operations, as published in the C series of the Official Journal of the European Union, in force on the first calendar day of the month in which the deadline falls, increased by:
(a)eight percentage points where the obligating event is a public supply and service contract referred to in Title V;
(b)three and a half percentage points in all other cases.
3.Interest shall be calculated from the calendar day following the deadline referred to in Article 80(3)(b) and specified in the debit note up to the calendar day on which the debt is repaid in full.
The recovery order corresponding to the amount of the default interest shall be issued when this interest is actually received.
4.In the case of fines, where the debtor provides a financial guarantee which is accepted by the accounting officer instead of payment, the interest rate applicable from the deadline referred to in Article 80(3)(b) shall be the rate referred to in paragraph 2 of this Article as in force on the first day of the month in which the decision imposing a fine has been adopted and increased only by one and a half percentage points.
1.The recovery order shall specify:
(a)the financial year to which the revenue is to be booked;
(b)the references of the act or legal commitment which is the source of the debt and gives rise to the entitlement to recovery;
(c)the budget article and any other subdivision that may apply, including, where appropriate, the references of the corresponding budget commitment;
(d)the amount to be recovered, expressed in euro;
(e)the name and address of the debtor;
(f)the deadline referred to in Article 80(3)(b);
(g)the possible method of recovery, including in particular recovery by offsetting or enforcement of any guarantee lodged.
2.The recovery order shall be dated and signed by the authorising officer responsible, then sent to the accounting officer.
3.The accounting officer of each institution shall keep a list of amounts due to be recovered. Union entitlements shall be grouped in the list according to the date of issue of the recovery order. He shall transfer this list to the accounting officer of the Commission.
The accounting officer of the Commission shall prepare a consolidated list showing the amount due per institution and per date of issue of the recovery order. The list shall be added to the Commission’s Report on budgetary and financial management.
4.In order to reinforce the protection of the Union’s financial interests, the Commission shall establish a list of Union entitlements stating the names of the debtors and the amount of the debt, where the debtor has been ordered to reimburse by a Court decision that has the force of res judicata and where no or no significant reimbursement has been made for one year following its pronouncement. The list shall be published, with due regard to the protection of personal data in accordance with the requirements of Regulation (EC) No 45/2001.
As far as personal data referring to natural persons are concerned, the information published shall be removed once the amount of the debt has been fully reimbursed. The same shall apply to personal data referring to legal persons for whom the official title identifies one or more natural persons.
The decision to include the debtor on the list of Union entitlements shall be taken in compliance with the principle of proportionality and shall take into account, in particular the significance of the amount.
1.The exceptional circumstances referred to in article 79(2) of the Financial Regulation are met when the possibility to have a voluntary payment and to recover the debt by offsetting as provided for in Article 80(1) of the Financial Regulation have been exhausted by the institution concerned and the debt represents a significant amount.
2.In the case referred to in paragraph 1, the institutions concerned other than those mentioned under Article 299 of the TFEU may request the Commission to adopt an enforceable decision.
3.In all cases, the enforceable decision shall specify that the amounts claimed shall be entered in the section of the budget corresponding to the institution concerned, which shall act as Authorising officer. The revenue shall be entered as general revenue except if it falls within the specified cases of assigned revenues as provided for in Article 21(3) of the Financial Regulation.
4.The requesting institution shall inform the Commission of any event likely to alter the recovery and shall intervene in support of the Commission in case of appeal against the enforceable decision.
5.The Commission and the institution concerned shall agree on the practical modalities for the implementation of this Article.
1.Upon the recovery of an amount receivable, the accounting officer shall make an entry in the accounts and shall inform the authorising officer responsible.
2.A receipt shall be issued in respect of any cash payments made to the accounting officer or imprest administrator.
3.Partial reimbursement by a debtor subject to several recovery orders shall first be posted on the oldest entitlement unless otherwise specified by the debtor.
Any partial payments shall first cover the interest.
1.Where the debtor has a claim on the Union that is certain as defined in point (a) of Article 81, of a fixed amount and due, relating to a sum established by a payment order, the accounting officer shall, following the deadline referred to in Article 80(3)(b) recover established amounts receivable by offsetting.
In exceptional circumstances, where it is necessary to safeguard the financial interests of the Union, when the accounting officer has justified grounds to believe that the amount due to the Union would be lost, the accounting officer shall recover by offsetting before the deadline referred to in Article 80(3)(b).
The accounting officer shall also recover by offsetting before the deadline referred to in Article 80(3)(b) when the debtor agrees.
2.Before proceeding with any recovery in accordance with paragraph 1, the accounting officer shall consult the authorising officer responsible and inform the debtors concerned.
Where the debtor is a national authority or one of its administrative entities, the accounting officer shall also inform the Member State concerned at least 10 working days in advance of his intention to resort to recovery by offsetting. However, in agreement with the Member State or administrative entity concerned, the accounting officer may proceed with the recovery by offsetting before the deadline has passed.
3.The offsetting referred to in paragraph 1 shall have the same effect as a payment and discharge the Union for the amount of the debt and, where appropriate of the interest due.
1.Without prejudice to Article 87, if the full amount has not been recovered by the deadline referred to in Article 80(3)(b) and specified in the debit note, the accounting officer shall inform the authorising officer responsible and shall without delay launch the procedure for effecting recovery by any means offered by the law, including, where appropriate, by enforcement of any guarantee lodged in advance.
2.Without prejudice to Article 87, where the recovery method referred to in paragraph 1 of this Article cannot be used and the debtor has failed to pay in response to the letter of formal notice sent by the accounting officer, the accounting officer shall enforce a recovery decision secured either in accordance with Article 79(2) of the Financial Regulation or by legal action.
The accounting officer, in collaboration with the authorising officer responsible, may allow additional time for payment only at the written request of the debtor, with due indication of the reasons, and provided that the following two conditions are fulfilled:
the debtor undertakes to pay interest at the rate specified in Article 83 for the entire additional period allowed, starting from the deadline referred to in Article 80(3)(b);
in order to safeguard the rights of the Union, the debtor lodges a financial guarantee covering the debt outstanding in both the principal sum and the interest, which is accepted by the institution’s accounting officer.
The guarantee referred to in point (b) of the first paragraph may be replaced by a joint and several guarantee by a third party approved by the institution’s accounting officer.
In exceptional circumstances, following a request by the debtor, the accounting officer may waive the requirement of a guarantee referred to in point (b) of the first paragraph when, on the basis of his assessment, the debtor is willing and able to make the payment in the additional time period but is not able to lodge such guarantee and is in a distressed situation.
1.Where an action is brought before the Court of Justice of the European Union against a Commission decision imposing a fine or other penalties under the TFEU or Euratom Treaty and until such time as all legal remedies have been exhausted, the debtor shall either provisionally pay the amounts concerned on the bank account designated by the accounting officer or provide a financial guarantee acceptable to the accounting officer. The guarantee shall be independent of the obligation to pay the fine or penalty payment or other penalties and shall be enforceable upon first call. It shall cover the claim as to principal and the interest due as specified in Article 83(4).
2.The Commission shall secure the provisionally cashed amounts by having them invested in financial assets thus ensuring the security and liquidity of the monies whilst also aiming at yielding a positive return.
3.After the exhaustion of all legal remedies and where the fine or penalty has been confirmed any of the following measures shall be taken:
(a)the provisionally collected amounts and the interest and other amounts they have yielded shall be entered into the budget in accordance with Article 83 of the Financial Regulation at the latest during the financial year following the year in which all legal remedies have been exhausted;
(b)where a financial guarantee has been lodged, the latter shall be enforced and the corresponding amounts entered in the budget;
Where the amount of the fine or of the penalty has been increased by the Court, points (a) and (b) of the first subparagraph shall apply up to the amounts of the decision of the Commission and the accounting officer shall collect the amount corresponding to the increase, which will be entered into the budget.
4.After all legal remedies have been exhausted and where the fine or penalty has been cancelled or reduced any of the following measures shall be taken:
(a)the amounts unduly collected together with the interest yielded shall be repaid to the third party concerned. In cases where the overall return yielded for the relevant period has been negative, the nominal value of the amounts unduly collected shall be repaid;
(b)where a financial guarantee has been lodged, the latter shall be released accordingly.
1.The authorising officer responsible may waive recovery of all or part of an established amount receivable only in the following cases:
(a)where the foreseeable cost of recovery would exceed the amount to be recovered and the waiver would not harm the image of the Union;
(b)where the amount receivable cannot be recovered in view of its age or the insolvency of the debtor;
(c)where recovery is inconsistent with the principle of proportionality.
2.In the case referred to in point (c) of paragraph 1, the authorising officer responsible shall act in accordance with predetermined procedures established within each institution and shall apply the following criteria which are compulsory and applicable in all circumstances:
(a)the facts, having regard to the gravity of the irregularity giving rise to the establishment of the amount receivable (fraud, repeat offence, intent, diligence, good faith, manifest error);
(b)the impact that waiving recovery would have on the operation of the Union and its financial interests (amount involved, risk of setting a precedent, undermining of the authority of the law).
Depending on the circumstances of the case, the authorising officer responsible may also have to take the following additional criteria into account:
(a)any distortion of competition that would be caused by the waiving of recovery;
(b)the economic and social damage that would be caused were the debt to be recovered in full.
3.The waiver decision referred to in Article 80(2) of the Financial Regulation shall be substantiated and shall refer to the diligence exercised to secure recovery and the points of law and fact on which the waiver is based. The authorising officer responsible shall waive recovery in accordance with Article 84.
4.The waiving of recovery of an established amount receivable may not be delegated by the institution in any of the following cases:
(a)where the amount to be waived is EUR 1 000 000 or more;
(b)where the amount to be waived is EUR 100 000 or more, where this represents 25 % or more of the established amount receivable.
Beneath the thresholds set out in the first subparagraph, each institution shall lay down in its internal rules the conditions and procedure for delegating the power to waive recovery of an established debt.
5.Each institution shall send to the European Parliament and Council each year a report on the waivers referred to in paragraphs 1 to 4 of this Article involving EUR 100 000 or more. In the case of the Commission, that report shall be annexed to the summary of the annual activity reports referred to in Article 66(9) of the Financial Regulation.
1.In the event of a mistake, the authorising officer responsible shall cancel totally or partially the established amount receivable in accordance with Articles 82 and 84 and include adequate reasons.
2.Each institution shall lay down in its internal rules the conditions and procedure for delegating the power to cancel an established amount receivable.
1.The limitation period for entitlements of the Union in respect of third parties shall begin to run on the expiry of the deadline communicated to the debtor in the debit note as specified in Article 80(3)(b).
The limitation period for entitlements of third parties in respect of the Union shall begin to run on the date on which the payment of the third party’s entitlement is due according to the corresponding legal commitment.
2.The limitation period for entitlements of the Union in respect of third parties shall be interrupted by any act of an institution, or a Member State acting at the request of an institution, notified to the third party and aiming at recovering the debt.
The limitation period for entitlements of third parties in respect of the Union shall be interrupted by any act notified to the Union by its creditors or on behalf of its creditors aiming at recovering the debt.
3.A new limitation period of five years shall begin to run on the day following the interruptions referred to in paragraph 2.
4.Any legal action relating to an amount receivable as referred to in paragraph 1, including actions brought before a court which later declares itself not to have jurisdiction, shall interrupt the limitation period. The new limitation period of five years shall not begin until a judgment having the force of res judicata is given or there is an extrajudicial settlement between the same parties on the same action.
5.Where the accounting officer allows the debtor additional time for payment in accordance with Article 89, this shall be considered as an interruption of the limitation period. The new limitation period of five years shall begin to run on the day following the expiry of the extended time for payment.
6.Entitlements shall not be recovered after the expiry of the limitation period, as established in paragraphs 1 to 5.
1.The financing decision shall set out the essential elements of an action involving expenditure from the budget.
2.The financing decision shall in particular set out the following:
(a)for grants:
the reference to the basic act and the budgetary line;
the priorities of the year, the objectives to be fulfilled and the foreseen results with the appropriations authorised for the financial year;
the essential eligibility, selection and award criteria to be used to select the proposals;
the maximum possible rate of co-financing and if different rates are envisaged the criteria to be followed for each rate;
the timetable and the indicative amount of the calls for proposals;
(b)for procurement:
the global budgetary envelope reserved for the procurements during the year;
the indicative number and type of contracts envisaged and if possible their subject in generic terms;
the indicative time-frame for launching the procurement procedures;
(c)for trust funds referred to in Article 187 of the Financial Regulation:
the reference to the basic act and the budgetary line;
the appropriations reserved to the trust fund for the year together with the amounts planned over its duration;
the objectives of the trust fund and its duration;
the rules of governance of the trust fund;
the possibility to entrust budget implementation tasks to the entities and persons referred to in Article 187(2) of the Financial Regulation;
(d)for prizes:
the reference to the basic act and the budgetary line;
the objectives to be fulfilled and the foreseen results;
the essential conditions for participation and award criteria;
the timetable of the contest and the amount of the prize or prizes;
(e)for financial instruments:
the reference to the basic act and the budgetary line;
the objectives to be fulfilled and the foreseen results;
the amount allocated to the financial instrument;
the indicative implementation timetable.
3.Where the work programme referred to in Article 128 of the Financial Regulation contains the information set out in point (a) of paragraph 2 of this Article for the grants financed from appropriations authorised for the financial year, the decision adopting it shall be considered to be the financing decision for those grants.
As regards procurement, trust funds, prizes and financial instruments, where the implementation of the corresponding appropriations authorised for the financial year is provided for by a work programme containing the information referred to in points (b), (c), (d) and (e) of paragraph 2 of this Article, the decision adopting this work programme shall also be considered to be the financing decision for the procurement, trust funds, prizes and financial instruments involved.
If the work programme does not contain such information for one or more actions, it must be modified accordingly or a specific financing decision must be adopted for the actions concerned.
4.Without prejudice to any specific provision of a basic act, any substantial change in a financing decision already adopted shall follow the same procedure as the initial decision.
1.The global budgetary commitment shall be implemented either by the conclusion of a financing agreement, itself providing for the subsequent conclusion of one or more legal commitments, or by the conclusion of one or more legal commitments.
Financing agreements in the field of direct financial assistance to third countries, including budget support, which constitute legal commitments may give rise to payments without the conclusion of other legal commitments.
2.The provisional budgetary commitment shall be implemented either by the conclusion of one or more legal commitments giving rise to an entitlement to subsequent payments or, in cases relating to expenditure on staff management or relating to communication expenditures engaged in by the institutions for the coverage of Union events, directly by payments.
1.A global commitment shall be made on the basis of a financing decision.
The global commitment shall be made at the latest before the decision on the selection of recipients is taken and, where implementation of the appropriations concerned involves the adoption of a work programme within the meaning of Article 188, at the earliest after that programme has been adopted.
2.Where the global commitment is implemented by the conclusion of a financing agreement, the second subparagraph of paragraph 1 shall not apply.
1.The rule that there shall be a single signatory for the budget commitment and the corresponding legal commitment may be departed from only in the following cases:
(a)where the commitments are provisional;
(b)where global commitments relate to financing agreements with third countries;
(c)where the institution’s decision constitutes the legal commitment;
(d)where the global commitment is implemented by a number of legal commitments, for which different authorising officers are responsible;
(e)where, in connection with imprest accounts available for external action, legal commitments must be signed by members of staff of the local units referred to in Article 72 on the instruction of the authorising officer responsible, who remains, however, fully responsible for the underlying transaction.
(f)where an institution has delegated authorising officer powers to the director of an interinstitutional European office pursuant to Article 199(1) of the Financial Regulation.
2.If the authorising officer responsible who signed the budget commitment is not available and remains unavailable for a period incompatible with the time limits for concluding the legal commitment, that legal commitment shall be concluded by the person designated under the deputisation rules adopted by each institution, provided that that person has the status of authorising officer in accordance with Article 65(3) of the Financial Regulation.
Items regarded as routine administrative expenditure which may give rise to provisional commitments shall include the following:
expenditure on staff, whether or not covered by the Staff Regulations, on other human resources and pensions and on the remuneration of experts;
expenditure relating to members of the institution;
training expenditure;
expenditure on competitions, selection and recruitment;
mission expenses;
representation expenses;
meeting expenses;
freelance interpreters and translators;
exchanges of officials;
recurring rentals of movable and immovable property or recurring payments relating to building contracts within the meaning of Article 121 of this Regulation or loan instalments pursuant to Article 203(8) of the Financial Regulation;
miscellaneous insurance;
cleaning, maintenance and security;
welfare and medical expenditure;
the use of telecommunications services;
financial charges;
legal expenses;
damages, including interest;
work equipment;
water, gas and electricity;
publications on paper or in electronic versions;
communications activities engaged in by the institutions for the coverage of Union events.
In the case of a global budget commitment followed by one or several individual legal commitments, the authorising officer responsible shall register in the central accounts the amounts of this or these successive individual legal commitments.
The registration in the accounts shall indicate the references of the global commitment against which the individual commitments are being booked.
The authorising officer responsible shall register the amounts in the accounts before signing the corresponding individual legal commitment, except in the cases referred to in the fourth subparagraph of Article 86(4) of the Financial Regulation.
In all cases, the authorising officer responsible shall check that the aggregated amount does not exceed the amount of the global commitment covering them.
1.Validation of any expenditure shall be based on supporting documents within the meaning of Article 110 attesting the creditor’s entitlement, on the basis of a statement of services actually rendered, supplies actually delivered or work actually carried out, or on the basis of other documents justifying payment, including recurring payments of subscriptions or training courses.
2.The authorising officer responsible shall personally check the supporting documents or shall, on his own responsibility, ascertain that this has been done, before taking the decision validating the expenditure.
3.The validation decision shall be expressed by the signing of a ‘passed for payment’ voucher by the authorising officer responsible or by technically competent member of staff, duly empowered by a formal decision of the authorising officer and under his responsibility in accordance with Article 65(5) of the Financial Regulation. Such empowerment decisions shall be kept for future reference.
For pre-financing payments, the authorising officer responsible or a technically competent member of staff, duly empowered by the authorising officer responsible shall certify with the endorsement ‘certified correct’ that the conditions required in the legal commitment for the payment of the pre-financing are met.
For interim and balance payments corresponding to procurement contracts, the endorsement ‘passed for payment’ shall certify that:
the institution has received and formally registered an invoice drawn up by the contractor;
the invoice itself, or an internal document accompanying the invoice received, has been endorsed ‘certified correct’ and signed by the authorising officer responsible or by a technically competent member of staff, duly empowered by the authorising officer responsible;
all aspects of the invoice have been checked by the authorising officer responsible or on his responsibility with a view to determining in particular the amount to be paid and the validity of the payment as discharge of the debt.
The endorsement ‘certified correct’, referred to in point (b) of the first paragraph shall certify that the services provided for in the contract have been properly provided, or that the supplies provided for in the contract have been properly delivered, or that the work provided for in the contract has been properly carried out. For supplies and work, the official or other servant technically competent shall draw up a provisional acceptance certificate, then a final acceptance certificate at the end of the guarantee period laid down in the contract. Those two certificates shall count as the ‘certified correct’ endorsement.
For recurring payments including payment of subscriptions or training courses, the endorsement ‘certified correct’, shall certify that the entitlement of the creditor is in accordance with relevant documents justifying payment.
For interim and balance payments corresponding to grants, the endorsement ‘passed for payment’ shall certify that:
the institution has received and formally registered a payment request drawn up by the beneficiary;
the payment request itself, or an internal document accompanying the cost statement received, has been endorsed ‘certified correct’ and signed by an official or other servant technically competent, duly empowered by the authorising officer responsible;
all aspects of the payment request have been checked by the authorising officer responsible or on his responsibility with a view to determining in particular the amount to be paid and the validity of the payment as discharge of the debt.
By endorsement referred to in point (b) of the first paragraph, the official or other servant technically competent, duly empowered by the authorising officer responsible, certifies that the action or work programme carried out by the beneficiary is in all respects in compliance with the grant agreement or decision, including, where applicable that the costs declared by the beneficiary are eligible.
For payments corresponding to staff expenditure, the endorsement ‘passed for payment’ shall certify that the following supporting documents exist:
in respect of monthly salary:
the complete list of staff, giving all the components of remuneration;
a form (personal information sheet) based on decisions taken in each individual case, showing, whenever such change occurs, any change in any component of remuneration;
in the case of recruitments or appointments, a certified true copy of the recruitment or appointment decision which accompanies the validation of the first salary payment;
in respect of other remunerations such as staff paid on an hourly or daily basis: a statement signed by the authorised member of staff showing the days and hours worked;
in respect of overtime: a statement signed by the authorised member of staff certifying the amount of overtime worked;
in respect of mission expenses:
the travel order signed by the competent authority;
the statement of mission expenses, signed by the member of staff on mission and by the administrative superior to whom the appropriate powers have been delegated, if the mission expenses differ from the mission order;
in respect of some other administrative expenditure related to staff including subscriptions or training courses which, according to the contract, are to be paid in advance: the supporting documents referring to the decision on which the expenditure is based and giving all the components of the calculation.
The statement of mission expenses referred to in point (d)(ii) of the first subparagraph shall indicate the place of mission, the dates and times of departure and arrival at the place of mission, travel expenses, subsistence expenses, and other expenses duly authorised on production of supporting documents.
In a non-computerised system, ‘passed for payment’ shall take the form of a stamp incorporating the signature of the authorising officer responsible or of a technically competent member of staff, duly empowered by the authorising officer responsible in accordance with Article 100. In a computerised system, ‘passed for payment’ shall take the form of an electronically secured validation by the authorising officer responsible or of a technically competent member of staff, duly empowered by the authorising officer responsible.
In a non-computerised system, ‘certified correct’ shall take the form of a stamp incorporating the signature of the authorising officer responsible or of a technically competent member of staff, duly empowered by the authorising officer responsible in accordance with Article 101. In a computerised system, ‘certified correct’ may take the form of an electronically secured validation by the technically competent member of staff, duly empowered by the authorising officer responsible.
When drawing up the payment order, the authorising officer responsible shall ensure that:
the payment order has been properly issued, meaning that a corresponding validation decision has been taken previously in the form of ‘passed for payment’, that the particulars of the payee are correct and that the amount is due;
the payment order corresponds to the budgetary commitment against which it is booked;
the expenditure is charged to the correct item in the budget;
appropriations are available.
1.The payment order shall state:
(a)the financial year to which the expenditure is to be booked;
(b)the budget article and any other subdivision that may apply;
(c)the references of the legal commitment giving rise to an entitlement to payment;
(d)the references of the budgetary commitment against which it is to be booked;
(e)the amount to be paid, expressed in euro;
(f)the name, address and bank account details of the payee;
(g)the object of the expenditure;
(h)the means of payment;
(i)the entry of items in the inventory in accordance with Article 248.
2.The payment order shall be dated and signed by the authorising officer responsible, then sent to the accounting officer.
1.Pre-financing shall provide a float. It may be split into a number of payments in accordance with sound financial management.
2.An interim payment, which may be repeated, may cover expenditure incurred for the implementation of the decision or agreement or to pay for services, supplies or works completed and/or delivered at interim stages of the contract. It may clear pre-financing in whole or in part, without prejudice to the provisions of the basic act.
3.The closure of the expenditure shall take the form of the payment of the balance which may not be repeated and which clears all preceding expenditure, or a recovery order.
1.Pre-financing, including in cases where it is split into a number of payments, shall be paid either on the basis of the contract, the decision, agreement or the basic act, or on the basis of supporting documents which make it possible to check that the terms of the contract, decision or agreement in question are complied with. If a date of payment for pre-financing is determined in those instruments, payment of the due amount shall not be dependent upon further demand.
2.Interim payments and payments of balances shall be based on supporting documents which make it possible to check that the action financed has been carried out in accordance with the basic act or the decision, or in accordance with the terms of the contract or agreement.
3.The authorising officer responsible shall lay down, in compliance with the principle of sound financial management, the nature of the supporting documents referred to in this Article in accordance with the basic act, decisions, contracts and agreements. Interim and final technical and financial implementation reports, shall constitute supporting documents for the purposes of paragraph 2.
4.The supporting documents shall be kept by the authorising officer responsible in accordance with Article 48.
1.The time allowed for making payments shall be understood as including validation, authorisation and payment of expenditure.
It shall begin to run from the date on which a payment request is received.
A payment request shall be registered by the authorised department of the authorising officer responsible as soon as possible and is deemed to be received on the date it is registered.
The date of payment is deemed to be the date on which the institution’s account is debited.
2.A payment request shall include the following essential elements:
(a)creditor’s identification;
(b)amount;
(c)currency;
(d)date.
Where at least one essential element is missing, the payment request shall be rejected.
The creditor shall be informed in writing of the rejection and the reasons for it as soon as possible and in any case within 30 calendar days from the date on which the payment request was received.
3.In the case of suspension as referred to in Article 92(2) of the Financial Regulation, the remaining time allowed for payment shall begin to run again from the date on which the requested information or revised documents are received or the necessary further verification, including on-the-spot checks, is carried out.
4.On expiry of the time limits laid down in Article 92(1) of the Financial Regulation, the creditor shall be entitled to interest in accordance with the following conditions:
(a)the interest rates shall be those referred to in Article 83(2) of this Regulation;
(b)the interest shall be payable for the period elapsing from the calendar day following expiry of the time limit for payment laid down in Article 92(1) of the Financial Regulation up to the day of payment.
However, when the interest calculated in accordance with the first subparagraph is lower than or equal to EUR 200, it shall be paid to the creditor only upon a demand submitted within two months of receiving late payment.
5.Each institution shall submit to the European Parliament and Council a report on the compliance with the time limits and on the suspension of the time limits laid down in Article 92 of the Financial Regulation. The report of the Commission shall be annexed to the summary of the annual activity reports referred to in Article 66(9) of the Financial Regulation.
Where computer systems and subsystems are used to process budget implementation operations, a full and up-to-date description of each system or subsystem shall be required.
Each description shall define the content of all data fields and describe how the system treats each individual operation. It shall show in detail how the system guarantees the existence of a complete audit trail for each operation.
The data in computer systems and subsystems shall be saved periodically and kept in a safe place.
1.Each institution shall appoint its internal auditor in accordance with arrangements adapted to its specific features and requirements. The institution shall inform the European Parliament and Council of the appointment of the internal auditor.
2.Each institution shall determine, in accordance with its specific features and its requirements, the scope of the mission of the internal auditor and shall lay down in detail the objectives and procedures for the exercise of the internal audit function with due respect for international internal audit standards.
3.The institution may appoint as internal auditor, by virtue of their particular competence, an official or other servant covered by the Staff Regulations chosen from nationals of the Member States.
4.If two or more institutions appoint the same internal auditor they shall make the necessary arrangements for him to be declared liable for his actions as laid down in Article 119.
5.The institution shall inform the European Parliament and Council when the duties of the internal auditor are terminated.
The institution shall provide the internal auditor with the resources required for the proper performance of his audit function and a mission charter detailing his tasks, duties and obligations.
1.The internal auditor shall adopt his work programme and shall submit it to the institution.
2.The institution may ask the internal auditor to carry out audits not included in the work programme referred to in paragraph 1.
1.The internal auditor shall submit to the institution the annual internal audit report provided for in Article 99(3) of the Financial Regulation, indicating the number and type of internal audits carried out, the principal recommendations made and the action taken on those recommendations.
That annual report shall also mention any systemic problems detected by the specialised panel set up pursuant to Article 73(6) of the Financial Regulation.
2.Each institution shall consider whether the recommendations made in the reports of its internal auditor are suitable for an exchange of best practices with the other institutions.
3.The internal auditor shall, during the elaboration of his report, particularly focus on the overall compliance with the principle of sound financial management and shall ensure that appropriate measures have been taken in order to steadily improve and enhance its application.
The internal auditor shall enjoy complete independence in the conduct of his audits. He may not be given any instructions nor be restricted in any way as regards the performance of the functions which, by virtue of his appointment, are assigned to him under the Financial Regulation.
The institution alone, proceeding in accordance with this Article, may act to have the internal auditor, as an official or other servant subject to the Staff Regulations, declared liable for his actions.
The institution shall take a reasoned decision to open an investigation. That decision shall be communicated to the interested party. The institution may put in charge of the investigation, under its direct responsibility, one or more officials of a grade equal to or higher than that of the member of staff concerned. In the course of the investigation, the views of the interested party shall be heard.
The investigation report shall be communicated to the interested party, who shall then be heard by the institution on the subject of that report.
On the basis of the report and the hearing, the institution shall adopt either a reasoned decision terminating the proceedings or a reasoned decision in accordance with Articles 22, 86 and Annex IX of the Staff Regulations. Decisions imposing disciplinary measures or financial penalties shall be notified to the interested party and communicated, for information purposes, to the other institutions and the Court of Auditors.
The interested party may bring an action in respect of such decisions before the Court of Justice of the European Union, as provided for in the Staff Regulations.
Without prejudice to the remedies allowed by the Staff Regulations, the internal auditor may bring an action directly before the Court of Justice of the European Union in respect of any act relating to the performance of his duties as internal auditor. Such an action must be lodged within three months running from the calendar day on which the act in question is notified.
Such actions shall be investigated and heard as provided for in Article 91(5) of the Staff Regulations of Officials of the European Union.
1. Building contracts cover the purchase, long lease, usufruct, leasing, rental or hire purchase, with or without option to buy, of land, existing buildings or other immovable property.
2. Supply contracts cover the purchase, leasing, rental or hire purchase, with or without option to buy, of products. A supply contract may include, as an incidental matter, siting and installation operations.
3. Works contracts cover either the execution, or both the execution and design, of works or a work related to one of the activities referred to in Annex II to Directive 2014/24/EU of the European Parliament and of the Council (4) or the realisation, by whatever means, of a work corresponding to the requirements specified by the contracting authority exercising a decisive influence on the type or design of the work.
A ‘ work ’ shall mean the outcome of building or civil engineering works taken as a whole that is sufficient in itself to fulfil an economic or technical function.
4. Service contracts cover all intellectual and non-intellectual services other than those covered by supply contracts, works contracts and building contracts.
5. In the case of mixed contracts consisting of supplies and services, the main subject matter shall be determined by a comparison of the values of the respective supplies or services.
A contract covering one type of procurement (works, supplies or services) and concessions (works or services) shall be awarded in accordance with the provisions applicable to the public contract.
6. Any references to nomenclatures in the context of public procurement shall be made using the ‘Common Procurement Vocabulary (CPV)’ as set out in Regulation (EC) No 2195/2002 of the European Parliament and of the Council (5) .
7. The contracting authority shall not demand that a group of economic operators have a given legal form in order to submit a tender or request to participate, but the selected group may be required to adopt a given legal form after it has been awarded the contract if this change is necessary for proper performance of the contract.
8. All exchanges with contractors, including the conclusion of contracts and any amendments thereto, may be done through electronic exchange systems set up by the contracting authority.
9. The electronic exchange systems shall meet the following requirements:
(a) only authorised persons may have access to the system and to documents transmitted through it;
(b) only authorised persons may electronically sign or transmit a document through the system;
(c) authorised persons must be identified through the system by established means;
(d) the time and date of the electronic transaction must be determined precisely;
(e) the integrity of documents must be preserved;
(f) the availability of documents must be preserved;
(g) where appropriate, the confidentiality of documents must be preserved;
(h) the protection of personal data in accordance with the requirements of Regulation (EC) No 45/2001 must be ensured.
10. Data sent or received through such a system shall enjoy legal presumption of the integrity of the data and the accuracy of the date and time of sending or receiving the data indicated by the system.
A document sent or notified through such a system shall be considered as equivalent to a paper document, shall be admissible as evidence in legal proceedings, shall be deemed original and shall enjoy legal presumption of its authenticity and integrity, provided it does not contain any dynamic features capable of automatically changing it.
The electronic signatures referred to in point (b) of paragraph 9 shall have the equivalent legal effect of handwritten signatures.
1. The duration of a framework contract may not exceed four years, save in exceptional cases duly justified in particular by the subject matter of the framework contract.
Specific contracts based on framework contracts shall be awarded in accordance with the terms of the framework contract.
When awarding specific contracts, the parties may not make substantial changes to the framework contract.
2. Where a framework contract is concluded with a single economic operator, the specific contracts shall be awarded within the limits of the terms laid down in the framework contract.
In duly justified circumstances, contracting authorities may consult in writing the contractor, requesting it to supplement its tender if necessary.
3. Where a framework contract is to be concluded with several economic operators ( ‘ multiple framework contract ’ ), it may take the form of separate contracts signed in identical terms with each contractor.
Specific contracts based on framework contracts concluded with several economic operators shall be implemented in one of the following ways:
(a) following the terms of the framework contract: without reopening of competition, where it sets out all the terms governing the provision of the works, supplies or services concerned and the objective conditions for determining which of the contractors shall perform them;
(b) where not all the terms governing the provision of the works, supplies or services concerned are laid down in the framework contract: through reopening of competition among the contractors, in accordance with paragraph 4 and on the basis of any of the following:
the same and, where necessary, more precisely formulated terms,
where appropriate, on the basis of other terms referred to in the procurement documents relating to the framework contract.
(c) partly without reopening of competition in accordance with point (a) and partly with reopening of competition amongst the contractors in accordance with point (b), where this possibility has been stipulated by the contracting authority in the procurement documents relating to the framework contract.
The procurement documents referred to in point (c) of the second subparagraph shall also specify which terms may be subject to reopening of competition.
4. A multiple framework contract with reopening of competition shall be concluded with at least three economic operators, provided that there is a sufficient number of admissible tenders as referred to in Article 158(4).
When awarding a specific contract through reopening of competition among the contractors, the contracting authority shall consult them in writing and fix a time limit which is sufficiently long to allow specific tenders to be submitted. Specific tenders shall be submitted in writing. The contracting authority shall award each specific contract to the tenderer who has submitted the most economically advantageous specific tender on the basis of the award criteria set out in the procurement documents relating to the framework contract.
5. In sectors subject to a rapid price and technological evolution, framework contracts without reopening of competition shall contain a clause either on a mid-term review or on a benchmarking system. After the mid-term review, if the conditions initially laid down are no longer adapted to the price or technological evolution, the contracting authority shall not use the framework contract concerned and shall take appropriate measures to terminate it.
6. Specific contracts based on framework contracts shall be preceded by a budgetary commitment.
1. The notices for publication in the Official Journal of the European Union shall include all the information set out in the relevant standard forms referred to in Directive 2014/24/EU to ensure transparency of the procedure.
2. The contracting authority may make known its intentions of planned procurement for the financial year through the publication of a prior information notice. It shall cover a period equal to or less than 12 months from the date on which the notice is sent to the Publications Office.
The contracting authority may publish the prior information notice either in the Official Journal of the European Union or on its buyer profile. In the latter case, a notice of publication on the buyer profile shall be published in the Official Journal of the European Union .
3. The contract notice shall be used as a means of launching a procedure with an estimated value equal to or greater than the thresholds laid down in Article 118(1) of the Financial Regulation, except for the procedure set out in Article 134 of this Regulation.
4. The contracting authority shall send to the Publications Office an award notice on the results of the procedure no later than 30 days after the signature of a contract or framework contract with a value equal to or greater than the thresholds laid down in Article 118(1) of the Financial Regulation.
However, notices relating to contracts based on a dynamic purchasing system may be grouped together on a quarterly basis. In such cases, the contracting authority shall send the notice no later than 30 days after the end of each quarter.
Award notices shall not be published for specific contracts based on a framework contract.
5. The contracting authority shall publish an award notice:
(a) before signing a contract or a framework contract with a value equal to or greater than the thresholds laid down in Article 118(1) of the Financial Regulation and awarded pursuant to the procedure under Article 134(1)(b) of this Regulation;
(b) after signing a contract or a framework contract with a value equal to or greater than the thresholds laid down in Article 118(1) of the Financial Regulation including awarded pursuant to the procedures under points (a) and (c) to (f) of Article 134(1) of this Regulation.
6. The contracting authority shall publish in the Official Journal of the European Union a notice of modification of contract during its duration in the cases set out in points (a) and (b) of Article 114a(3) of the Financial Regulation where the value of the modification is equal or greater than the thresholds defined in Article 118(1) of the Financial Regulation.
7. In case of interinstitutional procedure, the contracting authority responsible for the procedure shall be in charge of the applicable publicity measures.
1. Procedures with an estimated contract value below the thresholds laid down in Article 118(1) of the Financial Regulation shall be advertised by appropriate means. Such advertising shall involve appropriate ex ante publicity on the internet or a contract notice or, for contracts awarded in accordance with the procedure set out in Article 136 of this Regulation, the publication of a notice for a call for expressions of interest in the Official Journal of the European Union . This obligation shall not apply to the procedure set out in Article 134 of this Regulation and the negotiated procedure for very low value contracts under Article 137(2) of this Regulation.
2. For contracts awarded in accordance with points (g) and (i) of Article 134 of this Regulation, the contracting authority shall send a list of contracts no later than 30 June of the following financial year, to the European Parliament and Council. In the case of the Commission, it shall be annexed to the summary of the annual activity reports referred to in Article 66(9) of the Financial Regulation.
3. Contract award information shall contain the name of the contractor, the amount awarded and the subject matter of the contract and, in the case of direct and specific contracts, it shall comply with Article 21(3).
The contracting authority shall publish a list of contracts on its internet site no later than 30 June of the following financial year for:
(a) contracts below the thresholds laid down in Article 118(1) of the Financial Regulation;
(b) contracts awarded in accordance with points (h) and (j) to (m) of Article 134 of this Regulation;
(c) modifications of contracts as set out in point (c) of Article 114a(3) of the Financial Regulation;
(d) modifications of contracts as set out in points (a) and (b) of Article 114a(3) of the Financial Regulation where the value of the modification is below the thresholds laid down in Article 118(1) of the Financial Regulation;
(e) specific contracts under a framework contract.
For the purposes of point (e) of the second subparagraph the published information may be aggregated per contractor for the same subject matter.
4. In case of interinstitutional framework contracts, each contracting authority shall be responsible for advertising its specific contracts and their modifications under the conditions set in paragraph 3.
1. The contracting authority shall draw up and transmit the notices referred to in Articles 123 and 124 by electronic means to the Publications Office.
2. The Publications Office shall publish the notices referred to in Articles 123 and 124 in the Official Journal of the European Union no later than:
(b) 12 days after their dispatch in all other cases.
3. The contracting authority must be able to provide evidence of the date of dispatch.
In addition to the advertising provided for in Articles 123 and 124 procurement procedures may be advertised in any other way, notably in electronic form. Any such advertising shall refer to the notice published in the Official Journal of the European Union if the notice has been published, and may not precede the publication of that notice, which alone is authentic.
Such advertising may not introduce any discrimination between candidates or tenderers nor contain details other than those contained in the contract notice, if the notice has been published.
1. In a restricted procedure and in the procedures referred to in points (a) and (b) of Article 136(1) and in Article 136a, the minimum number of candidates shall be five.
2. In the competitive procedure with negotiation, the competitive dialogue, the innovation partnership, the prospection of the local market under Article 134(1)(g) and the negotiated procedure for low value contracts under Article 137(1) the minimum number of candidates shall be three.
3. Paragraphs 1 and 2 of this Article shall not apply in the following cases:
(a) negotiated procedures for very low value contracts under Article 137(2);
(b) negotiated procedures without prior publication under Article 134 except for design contests under Article 134(1)(d) and prospection of the local market under Article 134(1)(g).
4. Where the number of candidates meeting the selection criteria is below the minimum number specified in paragraphs 1 and 2, the contracting authority may continue the procedure by inviting the candidates with the required capacities. The contracting authority may not include other economic operators that did not initially request to participate or that it did not initially invite.
5. During a negotiation, the contracting authority shall ensure equal treatment for all tenderers.
A negotiation may take place in successive stages in order to reduce the number of tenders to be negotiated by applying the award criteria specified in the procurement documents. The contracting authority shall indicate whether it will use that option in the procurement documents.
6. For the procedures laid down in points (d) and (g) of Article 134(1) and Articles 136a and 137, the contracting authority shall invite at least all economic operators who have expressed interest following ex ante publicity as set out in Article 124(1) or prospection of the local market or a design contest.
1. The innovation partnership shall aim at the development of an innovative product, service or innovative works and the subsequent purchase of the resulting works, supplies or services, provided that they correspond to the performance levels and maximum costs agreed between the contracting authorities and the partners.
The innovation partnership shall be structured in successive phases following the sequence of steps in the research and innovation process, which may include the completion of the works, the manufacturing of the products or the provision of the services. The innovation partnership shall set intermediate targets to be attained by the partners.
Based on those intermediate targets, the contracting authority may decide after each phase to terminate the innovation partnership or, in the case of an innovation partnership with several partners, to reduce the number of partners by terminating individual contracts, provided that the contracting authority has indicated in the procurement documents those possibilities and the conditions for their use.
2. Before launching an innovation partnership, the contracting authority shall consult the market as provided for in Article 137a in order to ascertain that the work, supply or service does not exist on the market or as near-to-market development activity.
The arrangements on negotiation set out in Article 104(4) of the Financial Regulation and in Article 128(5) of this Regulation shall be followed.
In the procurement documents, the contracting authority shall identify the need for innovative works, supplies or services that cannot be met by purchasing works, supplies or services already available on the market. It shall indicate which elements of this description define the minimum requirements. The information provided shall be sufficiently precise to enable economic operators to identify the nature and scope of the required solution and decide whether to request to participate in the procedure.
The contracting authority may decide to set up the innovation partnership with one partner or with several partners conducting separate research and development activities.
The contracts shall be awarded on the sole basis of the best price-quality ratio as set out in Article 110(4) of the Financial Regulation.
3. In the procurement documents, the contracting authority shall specify the arrangements applicable to intellectual property rights.
In the framework of the innovation partnership, the contracting authority shall not reveal to the other partners solutions proposed or other confidential information communicated by a partner without its agreement.
The contracting authority shall ensure that the structure of the partnership and, in particular, the duration and value of the different phases reflect the degree of innovation of the proposed solution and the sequence of the research and innovation activities required for the development of an innovative solution not yet available on the market. The estimated value of works, supplies or services shall not be disproportionate in relation to the investment required for their development.
1. Design contests shall be subject to the rules on advertising set out in Article 123 and may include the award of prizes.
Where design contests are restricted to a limited number of candidates, the contracting authority shall lay down clear and non-discriminatory selection criteria.
The number of candidates invited to participate must be sufficient to ensure genuine competition.
2. The jury shall be appointed by the authorising officer responsible. It shall be composed exclusively of natural persons who are independent of candidates in the contest. Where a particular professional qualification is required from candidates in a contest, at least one third of the members of the jury must have the same or an equivalent qualification.
The jury shall be autonomous in its opinions. Its opinions shall be adopted on the basis of projects submitted to it anonymously by the candidates and solely in the light of the criteria set out in the contest notice.
3. The proposals of the jury, based on the merits of each project, and its ranking and remarks, shall be recorded in a report signed by its members.
Candidates shall remain anonymous until the jury has given its opinion.
Candidates may be asked by the jury to answer the questions recorded in the report in order to clarify a project. A full report of the resulting dialogue shall be drawn up.
4. The contracting authority shall then take an award decision giving the name and address of the candidate selected and the reasons for the choice by reference to the criteria announced in the contest notice, especially if it departs from the proposals made in the jury's opinion.
1. The dynamic purchasing system is a completely electronic process for making commonly used purchases, which is open throughout its duration to any economic operator who satisfies the selection criteria. It may be divided into categories of works, supplies or services that are objectively defined on the basis of characteristics of the procurement to be undertaken under the category concerned. In this case, selection criteria must be defined for each category.
2. The contracting authority shall indicate in the procurement documents the nature and estimated quantity of the purchases envisaged and all the necessary information concerning the purchasing system, the electronic equipment used and the technical connection arrangements and specifications.
3. The contracting authority shall give any economic operator, throughout the period of validity of the dynamic purchasing system, the possibility of requesting to participate in the system. It shall complete its evaluation of such requests within 10 working days of receipt of that request. This deadline may be prolonged to 15 working days where justified. However, the contracting authority may extend the evaluation period provided that no invitation to tender is issued in the meantime.
The contracting authority shall inform the candidate at the earliest possible opportunity of whether or not it has been admitted to the dynamic purchasing system.
4. The contracting authority shall invite all candidates admitted to the system under the relevant category to submit a tender within a reasonable time. The contracting authority shall award the contract to the tenderer who has submitted the most economically advantageous tender on the basis of the award criteria set out in the contract notice. Those criteria may, if appropriate, be formulated more precisely in the invitation to tender.
5. The contracting authority shall indicate the period of validity of the dynamic purchasing system in the contract notice.
A dynamic purchasing system may not last for more than four years, except in duly justified exceptional cases.
The contracting authority may not resort to this system to prevent, restrict or distort competition.
1. The contracting authority shall specify its needs and requirements, the award criteria and an indicative timeframe in the contract notice or in a descriptive document.
It shall award the contract to the tender offering the best price-quality ratio.
2. The contracting authority shall open a dialogue with the candidates satisfying the selection criteria in order to identify and define the means best suited to satisfying its needs. It may discuss all aspects of the procurement with the selected candidates during this dialogue but it cannot alter its needs and requirements and award criteria as provided for in paragraph 1.
During the course of dialogue, the contracting authority shall ensure equality of treatment among all tenderers and shall not reveal the solutions proposed or other confidential information communicated by a tenderer without its agreement to waive that confidentiality.
The competitive dialogue may take place in successive stages in order to reduce the number of solutions to be discussed by applying the announced award criteria if provision is made for this possibility in the contract notice or the descriptive document.
3. The contracting authority shall continue the dialogue until it can identify the solution or solutions which are capable of meeting its needs.
After informing the remaining tenderers that the dialogue is concluded, the contracting authority shall ask each of them to submit their final tenders on the basis of the solution or solutions presented and specified during the dialogue. These tenders shall contain all the elements required and necessary for the performance of the project.
At the request of the contracting authority, these final tenders may be clarified, specified and optimised provided this does not involve substantial changes to the tender or to the procurement documents.
The contracting authority may negotiate with the tenderer having submitted the tender offering the best price-quality ratio to confirm commitments contained in the tender provided this does not have the effect of modifying substantial aspects of the tender and does not risk distorting competition or causing discrimination.
4. The contracting authority may specify payments to the selected candidates taking part in the dialogue.
In the case of an interinstitutional procedure, one contracting authority shall manage the procedure and the subsequent direct or framework contract acting on its own behalf and on behalf of the other contracting authorities concerned.
The contract notice shall indicate the contracting authorities referred to in Article 104a(1) of the Financial Regulation which are involved in the procurement procedure, the institution responsible for the procedure and the global volume of the contracts for all those contracting authorities.
1. When the contracting authority uses the negotiated procedure without prior publication of a contract notice, it shall follow the arrangements on negotiation set out in Article 104(4) of the Financial Regulation and in Article 128(5) of this Regulation.
The contracting authority may use the negotiated procedure regardless of the estimated value of the contract, in the following cases:
(a) where no tenders, or no suitable tender, or no request to participate or no suitable request to participate as provided for in paragraph 2 have been submitted in response to an open procedure or restricted procedure after this procedure has been completed, provided that the original procurement documents are not substantially altered;
(b) where the works, supplies or services can only be provided by a single economic operator under the conditions set out in paragraph 3 and for any of the following reasons:
the aim of the procurement is the creation or acquisition of a unique work of art or artistic performance;
competition is absent for technical reasons;
the protection of exclusive rights including intellectual property rights must be ensured;
(c) in so far as is strictly necessary where, for reasons of extreme urgency brought about by unforeseeable events, it is impossible to comply with the time limits laid down in Articles 152, 154 and 275 and where the justification of such extreme urgency is not attributable to the contracting authority;
(d) where a service contract follows a design contest and is to be awarded to the winner or to one of the winners; in the latter case, all winners must be invited to participate in the negotiations;
(e) for new services or works consisting in the repetition of similar services or works entrusted to the economic operator to which the same contracting authority awarded an original contract, provided that these services or works are in conformity with a basic project for which the original contract was awarded after publication of a contract notice, subject to the conditions set out in paragraph 4;
(f) for supply contracts:
for additional deliveries which are intended either as a partial replacement of supplies or installations or as the extension of existing supplies or installations, where a change of supplier would oblige the contracting authority to acquire supplies having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance; when the institutions award contracts on their own account, the duration of such contracts may not exceed three years;
where the products are manufactured purely for the purpose of research, experimentation, study or development; however such contracts shall not include quantity production to establish commercial viability or to recover research and development costs;
for supplies quoted and purchased on a commodity market;
for purchases of supplies on particularly advantageous terms, from either an economic operator which is definitively winding up its business activities, or the liquidators in an insolvency procedure, an arrangement with creditors, or a similar procedure under national law;
(g) for building contracts, after prospecting the local market;
(h) for contracts for any of the following:
legal representation by a lawyer within the meaning of Article 1 of Council Directive 77/249/EEC (6) in arbitration or conciliation or judicial proceedings;
legal advice given in the preparation of the proceedings referred to above or where there is tangible indication and high probability that the matter to which the advice relates will become the subject of such proceedings, provided that the advice is given by a lawyer within the meaning of Article 1 of Directive 77/249/EEC;
for arbitration and conciliation services;
document certification and authentication services which must be provided by notaries;
(i) for contracts declared to be secret or for contracts whose performance must be accompanied by special security measures, in accordance with the administrative provisions in force or when the protection of the essential interests of the Union so requires, provided the essential interests concerned cannot be guaranteed by other measures; these measures may consist of requirements to protect the confidential nature of information which the contracting authority makes available in the procurement procedure;
(j) for financial services in connection with the issue, sale, purchase or transfer of securities or other financial instruments within the meaning of Directive 2004/39/EC of the European Parliament and of the Council (7) , central bank services and operations conducted with the European Financial Stability Facility and the European Stability Mechanism;
(k) loans, whether or not in connection with the issue, sale, purchase or transfer of securities or other financial instruments;
(l) for the purchase of public communication networks and electronic communications services within the meaning of Directive 2002/21/EC of the European Parliament and of the Council (8) ;
(m) services provided by an international organisation where it cannot participate in competitive procedures according to its statute or act of establishment.
2. A tender shall be considered unsuitable where it does not relate to the subject matter of the contract and a request to participate shall be considered unsuitable where the economic operator is in an exclusion situation under Article 106(1) of the Financial Regulation or does not meet the selection criteria.
3. The exceptions set out in points (ii) and (iii) of point (b) of paragraph 1 shall only apply when no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters when defining the procurement.
4. In the cases referred to in point (e) of paragraph 1, the basic project shall indicate the extent of possible new services or works and the conditions under which they will be awarded. As soon as the basic project is put up for tender, the possible use of the negotiated procedure shall be disclosed, and the total estimated amount for the subsequent services or works shall be taken into consideration in applying the thresholds referred to in Article 118(1) of the Financial Regulation or in Articles 265(1)(a), 267(1)(a) or 269(1)(a) of this Regulation in the field of external actions. When the institutions award contracts on their own account, that procedure may only be used during the performance of the original contract and at the latest during the three years following its signature.
1. When the contracting authority uses the competitive procedure with negotiation or the competitive dialogue, it shall follow the arrangements on negotiation set out in Article 104(4) of the Financial Regulation and in Article 128(5) of this Regulation. The contracting authority may use these procedures regardless of the estimated value of the contract, in the following cases:
(a) where only irregular or unacceptable tenders as defined in paragraphs 2 and 3 have been submitted in response to an open or restricted procedure after this procedure has been completed provided that the original procurement documents are not substantially altered; the publication of a contract notice may be waived under the conditions set out in paragraph 4;
(b) with regard to works, supplies or services fulfilling one or more of the following criteria:
where the needs of the contracting authority cannot be met without the adaptation of a readily available solution;
the works, supplies or services include design or innovative solutions;
the contract cannot be awarded without prior negotiations because of specific circumstances related to the nature, complexity or the legal and financial make-up of the contract or the risks attached to the subject matter of the contract;
the technical specifications cannot be established with sufficient precision by the contracting authority with reference to a standard, as set out in Article 139(3);
(c) for concession contracts;
(d) for the service contracts referred to in Annex XIV to Directive 2014/24/EU;
(e) for research and development services other than those covered by CPV codes 73000000-2 to 73120000-9, 73300000-5, 73420000-2 and 73430000-5 unless the benefits accrue exclusively to the contracting authority for its use in the conduct of its own affairs, or unless the service provided is wholly remunerated by the contracting authority;
(f) for service contracts for the acquisition, development, production or co-production of programme material intended for audiovisual or radio media services as defined in Directive 2010/13/EU of the European Parliament and of the Council (9) or contracts for broadcasting time or programme provision.
2. A tender shall be considered irregular in any of the following cases:
(a) when it does not comply with the minimum requirements specified in the procurement documents;
(b) when it does not comply with the requirements for submission set out in Article 111(4) of the Financial Regulation;
(c) when the tenderer is rejected under points (b) or (c) of Article 107(1) of the Financial Regulation;
(d) when the contracting authority has declared the tender to be abnormally low.
3. A tender shall be considered unacceptable in any of the following cases:
(a) when the price of the tender exceeds the contracting authority's maximum budget as determined and documented prior to the launching of the procurement procedure;
(b) when the tender fails to meet the minimum quality levels for award criteria.
4. In the cases referred to in point (a) of paragraph 1, the contracting authority shall not be required to publish a contract notice if it includes in the competitive procedure with negotiation all those tenderers who satisfied exclusion and selection criteria except those who submitted a tender declared to be abnormally low.
1. For contracts with a value below the thresholds referred to in Article 118(1) of the Financial Regulation or in Article 265(1)(b) of this Regulation and without prejudice to Articles 134 and 135 of this Regulation, the contracting authority may use a call for expressions of interest to do either of the following:
(a) to pre-select candidates to be invited to submit tenders in response to future restricted invitations to tender;
(b) to collect a list of vendors to be invited to submit requests to participate or tenders.
2. The list drawn up following a call for expressions of interest shall be valid for not more than four years from the date on which the notice referred to in Article 124(1) is published.
The list referred to in the first subparagraph may include sub-lists.
Any interested economic operator may express interest at any time during the period of validity of the list, with the exception of the last three months of that period.
3. Where a contract is to be awarded, the contracting authority shall invite all candidates or vendors entered on the relevant list or sub-list to do either of the following:
(a) to submit a tender in the case referred to in point (a) of paragraph 1;
(b) to submit, in case of the list referred to in point (b) of paragraph 1, either of the following:
tenders including documents relating to exclusion and selection criteria;
documents relating to exclusion and selection criteria and, in a second step, tenders, for those fulfilling these criteria.
A middle value contract of a value below the thresholds referred to in Article 118(1) of the Financial Regulation may be awarded by negotiated procedure following the arrangements on negotiation set out in Article 104(4) of the Financial Regulation and in Article 128(5) of this Regulation. Article 124(1) and paragraphs 1 and 4 of Article 128 of this Regulation shall apply to such procedures. Only candidates invited simultaneously and in writing by the contracting authority may submit an initial tender.
1. A low value contract of a value not exceeding EUR 60 000 may be awarded by negotiated procedure following the arrangements on negotiation set out in Article 104(4) of the Financial Regulation and in Article 128(5) of this Regulation. Articles 124(1) and paragraphs 2 and 4 of Article 128 of this Regulation shall apply to such procedures. Only candidates invited simultaneously and in writing by the contracting authority may submit an initial tender.
2. A very low value contract of a value not exceeding EUR 15 000 may be awarded by negotiated procedure following the arrangements on negotiation set out in Article 104(4) of the Financial Regulation and in Article 128(5) of this Regulation. Article 128(3) of this Regulation shall apply to such procedures. Only candidates invited simultaneously and in writing by the contracting authority may submit an initial tender.
3. Payments of amounts not exceeding EUR 1 000 in respect of items of expenditure may consist simply in payment against invoices, without prior acceptance of a tender.
1. For preliminary market consultation, the contracting authority may seek or accept advice from independent experts or authorities or from economic operators. That advice may be used in the planning and conduct of the procurement procedure, provided that such advice does not have the effect of distorting competition and does not result in a violation of the principles of non-discrimination and transparency.
2. Where an economic operator has advised the contracting authority or has otherwise been involved in the preparation of the procurement procedure, the contracting authority shall take appropriate measures as set out in Article 142 to ensure that competition is not distorted by the participation of that economic operator.
1. The procurement documents shall include the following:
(a) if applicable, the contract notice or other advertising measure as provided for in Articles 123 to 126;
(b) the invitation to tender;
(c) the tender specifications or the descriptive documents in the case of a competitive dialogue; they shall include the technical specifications and the relevant criteria;
(d) the draft contract based on the model contract.
Point (d) of the first subparagraph shall not apply to cases where, due to exceptional and duly justified circumstances, the model contract cannot be used.
2. The invitation to tender shall contain the following:
(a) specify the rules governing the submission of tenders, including in particular the conditions to maintain them confidential until opening, the closing date and time for receipt and the address to which they must be sent or delivered or the internet address in case of electronic submission;
(b) state that submission of a tender implies acceptance of the terms and conditions set out in the procurement documents and that this submission binds the contractor to whom the contract is awarded during performance of the contract;
(c) specify the period during which a tender will remain valid and may not be modified in any respect;
(d) forbid any contact between the contracting authority and the tenderer during the procedure, save, exceptionally, under the conditions laid down in Article 160, and, where provision is made for an on-the-spot visit, specify the arrangements for such a visit;
(e) specify the means of proof for compliance with the time-limit for receipt of tenders;
(f) state that submission of a tender implies acceptance of receiving notification of the outcome of the procedure by electronic means.
3. The tender specifications shall contain the following:
(a) the exclusion and selection criteria;
(b) the award criteria and their relative weighting or, where weighting is not possible for objective reasons, their decreasing order of importance, which shall also apply to variants if they are authorised in the contract notice;
(c) the technical specifications referred to in Article 139;
(d) if variants are authorised, the minimum requirements which they must meet;
(e) information whether the Protocol on the Privileges and Immunities of the European Union or, where appropriate, the Vienna Convention on Diplomatic Relations or Vienna Convention on Consular Relations applies;
(f) the evidence of access to procurement, as set out in Articles 172 and 263;
(g) in the case of a dynamic purchasing system or electronic catalogues, the electronic equipment used and the technical connection arrangements and specifications needed.
4. The draft contract shall contain the following:
(a) specify the liquidated damages for failure to comply with its clauses;
(b) specify the details which must be contained in invoices and in the relevant supporting documents in accordance with Article 102;
(c) state that, when the institutions award contracts on their own account, the law which applies to the contract is Union law complemented, where necessary, by a national law or, if necessary for contracts referred to in Article 121(1), exclusively national law;
(d) specify the competent court for hearing disputes;
(e) specify that the contractor shall comply with applicable obligations in the fields of environmental, social and labour law established by Union law, national law, collective agreements or by the international environmental, social and labour law provisions listed in Annex X of Directive 2014/24/EU;
(f) specify whether the transfer of intellectual property rights will be required;
(g) state that the price quoted in the tender is firm and non-revisable or lay down the conditions or formulas for revision of prices during the lifetime of the contract.
For the purposes of point (g) of the first subparagraph, if a revision of prices is set out in the contract, the contracting authority shall take particular account of:
the subject matter of the procurement and the economic situation in which it is taking place;
the type of contract and tasks and its duration;
its financial interests.
Points (c) and (d) of the first subparagraph may be waived for contracts signed in accordance with point (m) of Article 134(1).
1. Technical specifications shall allow equal access of economic operators to the procurement procedures and not have the effect of creating unjustified obstacles to the opening up of procurement to competition.
Technical specifications shall include the characteristics required for works, supplies or services, including minimum requirements, so that they fulfil the use for which they are intended by the contracting authority.
2. The characteristics referred to in paragraph 1 may include as appropriate:
(a) the quality levels;
(b) environmental performance and climate performance;
(c) for purchases intended for use by natural persons, the accessibility criteria for people with disabilities or the design for all users, except in duly justified cases;
(d) the levels and procedures of conformity assessment;
(e) performance or use of the supply;
(f) safety or dimensions, including, for supplies, the sales name and user instructions, and, for all contracts, terminology, symbols, testing and test methods, packaging, marking and labelling, production processes and methods;
(g) for works contracts, the procedures relating to quality assurance and the rules relating to design and costing, the test, inspection and acceptance conditions for works and methods or techniques of construction and all the other technical conditions which the contracting authority is in a position to prescribe under general or specific regulations in relation to the finished works and to the materials or parts which they involve.
3. The technical specifications shall be formulated in any of the following ways:
(a) in order of preference, by reference to European standards, European technical assessments, common technical specifications, international standards, other technical reference systems established by European standardisation bodies or, failing this, their national equivalents; every reference shall be accompanied by the words ‘ or equivalent ’ ;
(b) in terms of performance or of functional requirements, including environmental characteristics, provided that the parameters are sufficiently precise to allow tenderers to determine the subject matter of the contract and to allow the contracting authority to award the contract;
(c) by a combination of the two methods set out in points (a) and (b).
4. Where the contracting authority uses the option of referring to the specifications provided for in point (a) of paragraph 3, it shall not reject a tender on the grounds that it does not comply with those specifications once the tenderer proves, by any appropriate means, that the solution proposed satisfies in equivalent manner the requirements defined in the technical specifications.
5. Where the contracting authority uses the option provided for in point (b) of paragraph 3, to formulate technical specifications in terms of performance or functional requirements, it shall not reject a tender which complies with a national standard transposing a European standard, a European technical approval, a common technical specifications, an international standard or technical reference systems established by a European standardisation body, if those specifications address the performance or functional requirements which it has laid down.
The tenderer shall prove by any appropriate means that the work, supply or service in compliance with the standard meets the performance or functional requirements set by the contracting authority.
6. Where a contracting authority intends to purchase works, supplies or services with specific environmental, social or other characteristics, it may require a specific label or specific requirements from a label, provided that all of the following conditions are satisfied:
(a) the label requirements only concern criteria which are linked to the subject matter of the contract and are appropriate to define the characteristics of the purchase;
(b) the label requirements are based on objectively verifiable and non-discriminatory criteria;
(c) the labels are established in an open and transparent procedure in which all the relevant stakeholders may participate;
(d) the labels are accessible to all interested parties;
(e) the label requirements are set by a third party over which the economic operator applying for the label cannot exercise a decisive influence.
The contracting authority may require that economic operators provide a test report or a certificate as means of proof of conformity with the procurement documents from a conformity assessment body accredited in accordance with Regulation (EC) No 765/2008 of the European Parliament and of the Council (10) or an equivalent conformity assessment body.
7. The contracting authority shall accept any other appropriate means of proof than those referred to in paragraph 6, such as a technical dossier from the manufacturer, where the economic operator had no access to the certificates or test reports, or no possibility of obtaining them or obtaining a specific label within the relevant time limits, for reasons that are not attributable to that economic operator and provided that the economic operator concerned proves that the works, supplies or services to be provided fulfil the requirements of the specific label or specific requirements indicated by the contracting authority.
8. Unless justified by the subject matter of the contract, technical specifications shall not refer to a specific make or source, or a particular process which characterises the products or services provided by a specific economic operator, or to trade marks, patents, types or a specific origin or production with the effect of favouring or eliminating certain products or economic operators.
Such reference shall be permitted on an exceptional basis where a sufficiently detailed and intelligible description of the subject matter of the contract is not possible. Such reference shall be accompanied by the words ‘ or equivalent ’ .
1. For the purpose of Article 106(10) of the Financial Regulation, the contracting authority shall accept the European Single Procurement Document (ESPD) referred to in Directive 2014/24/EU or, failing that, a declaration on honour, signed and dated, stating that the economic operator is not in one of the situations referred to in paragraphs 1 and 4 of Article 106 and in Article 107 of the Financial Regulation or that it is in one of the cases referred to in point (a) of Article 106(7) of the Financial Regulation.
An economic operator may reuse an ESPD which has already been used in a previous procedure, provided that the economic operator confirms that the information contained therein continues to be correct.
Where the contracting authority limits the number of candidates under Article 104(3) of the Financial Regulation, all the candidates shall provide the evidence referred to in paragraph 3 of this Article.
Depending on its risk assessment, the contracting authority may decide not to request the ESPD or declaration on honour for any of the following:
(a) procedures for very low value contracts under Article 137(2);
(b) procedures for contracts in the field of external actions with a value not exceeding EUR 20 000 under Articles 265(1), 267(1) or 269(1).
2. The successful tenderer shall provide, within a time limit set by the contracting authority and preceding the signature of the contract, the evidence referred to in paragraph 3, confirming the ESPD or the declaration on honour in the following cases:
(a) for contracts awarded by the institutions on their own account, with a value equal to or greater than the thresholds referred to in Article 118(1) of the Financial Regulation;
(b) for contracts in the field of external actions with a value equal to or greater than the thresholds laid down in Articles 265(1)(a), 267(1)(a) or 269(1)(a).
3. The contracting authority shall accept as satisfactory evidence that an economic operator is not in one of the situations described in points (a), (c), (d) or (f) of Article 106(1) of the Financial Regulation, a recent extract from the judicial record or, failing that, an equivalent document recently issued by a judicial or administrative authority in its country of establishment showing that those requirements are satisfied.
The contracting authority shall accept, as satisfactory evidence that an economic operator is not in the situation described in point (a) or (b) of Article 106(1) of the Financial Regulation, a recent certificate issued by the competent authority of the State concerned.
Where the certificate is not issued in the country concerned the economic operator may provide a sworn statement made before a judicial authority or notary or, failing that, a solemn statement made before an administrative authority or a qualified professional body in its country of establishment.
4. The contracting authority shall waive the obligation of an economic operator to submit the documentary evidence referred to in paragraph 3 in the case of international organisations, if it can access it on a national database free of charge or if such evidence has already been submitted to it for the purposes of another procedure and provided that the issuing date of the documents does not exceed one year and that they are still valid.
In such a case, the economic operator shall declare on its honour that the documentary evidence has already been provided in a previous procedure and confirm that no changes in its situation have occurred.
The measures referred to in point (c) of Article 107(1) of the Financial Regulation shall include the communication to the other candidates and tenderers of relevant information exchanged in the context of or resulting from the involvement of the candidate or tenderer in the preparation of the procurement procedure and the fixing of adequate time limits for the receipt of tenders.
The candidate or tenderer concerned shall only be rejected from the procedure where there are no other means to ensure compliance with the principle of equal treatment.
Prior to any such exclusion, candidates or tenderers shall be given the opportunity to prove that their involvement in preparing the procurement procedure is not capable of distorting competition.
In order to ensure the functioning of the database referred in Article 108(1) of the Financial Regulation, the institutions, offices, bodies, agencies and entities referred to in points (c), (d) and (e) of Article 108(2) of the Financial Regulation shall designate authorised persons.
Where applicable, these authorised persons shall provide the information referred to in Article 108(3) of the Financial Regulation. They shall be granted access in accordance with paragraphs 4 and 12 of Article 108 of the Financial Regulation.
Authorised persons already designated by the entities referred to in point (d) of Article 108(2) of the Financial Regulation in accordance with the sector-specific rules may be used for the purposes of Article 108(12) of the Financial Regulation.
Information requested from the entities referred to in point (d) of Article 108(2) of the Financial Regulation shall be transmitted only through the Irregularity Management System which is the automated information system established by the Commission currently in use for reporting of fraud and irregularities, in accordance with the sector-specific rules.
1. The Chair of the panel shall be appointed by the Commission. He or she shall be chosen from among former members of the Court of Auditors, the Court of Justice or former officials who have had at least the rank of Director-General in an institution of the Union other than the Commission. He or she shall be selected on the basis of his/her personal and professional qualities, extensive experience in legal and financial matters and proven competence, independence and integrity. The term of office shall be five years and shall not be renewable. The Chair shall be appointed as special adviser within the meaning of Article 5 of the Conditions of Employment of Other Servants of the European Union.
The Chair of the panel shall preside at all sessions of the panel. He/she shall be independent in the performance of his or her duties. He/she shall not have a conflict of interests between his or her duties as Chair of the panel and any other official duties.
2. Two permanent members shall be designated by the Commission. One additional member shall represent the requesting contracting authority and shall be designated in accordance with its own internal organisation.
3. The permanent secretariat of the panel shall ensure the following:
(a) prepare the analysis of the information submitted to the panel pursuant to Article 108(8)(a) of the Financial Regulation;
(b) liaise with the economic operators and the other authorising officers for the purposes of points (b), (c), and (f) of Article 108(8) of the Financial Regulation;
(c) keep the repository of the recommendations adopted by the panel in accordance with Article 108(5) of the Financial Regulation and the decisions taken by the contracting authority in accordance with Article 106(3) of the Financial Regulation;
(d) ensure the centralised publication in accordance with Article 106(16) of the Financial Regulation.
4. Each member of the panel shall consider each submitted case in accordance with the rules and procedures laid down in this Regulation, the Financial Regulation and any other applicable rules established by the Commission. Prior to his or her designation, and throughout his or her service, each member of the panel shall have the obligation to promptly disclose any acts likely to constitute a conflict of interests within the meaning of Article 57 of the Financial Regulation and Article 32 of this Regulation. Members of the panel shall recuse themselves from any case in which they have an actual conflict of interests.
5. The rules of procedure of the panel shall be adopted by the Commission.
1. The contracting authority shall indicate in the procurement documents the selection criteria, the minimum levels of capacity and the evidence required to prove this capacity. All requirements shall be related and proportionate to the subject matter of the contract.
The contracting authority shall specify in the procurement documents how groups of economic operators are to meet the selection criteria taking into account paragraph 6.
Where a contract is divided into lots, the contracting authority may set minimum levels of capacity for each lot. It may set additional minimum levels of capacity in case several lots are awarded to the same contractor.
2. With regard to capacity to pursue the professional activity, the contracting authority may require an economic operator to fulfil at least one of the following conditions:
(a) be enrolled in a relevant professional or trade register, except for international organisations;
(b) for service contracts, hold a particular authorisation proving that it is authorised to perform the contract in its country of establishment or be a member of a specific professional organisation.
3. When receiving requests to participate or tenders, the contracting authority shall accept the ESPD or, failing that, a declaration on honour stating that the candidate or tenderer fulfils the selection criteria.
The contracting authority may ask tenderers and candidates at any moment during the procedure to submit an updated declaration or all or part of the supporting documents where this is necessary to ensure the proper conduct of the procedure.
The contracting authority shall require the candidates or successful tenderer to submit up-to-date supporting documents except where it has already received them for the purpose of another procedure and provided that the documents are still up-to-date or it can access them on a national database free of charge.
4. The contracting authority may, depending on its assessment of risks, decide not to require evidence of the legal, regulatory, financial, economic, technical and professional capacity of economic operators in the following cases:
(a) procedures for middle or low value contracts awarded by the institutions on their own account, with a value not exceeding the value referred to in Article 118(1) of the Financial Regulation;
(b) procedures for contracts awarded in the field of external actions, with a value not exceeding the thresholds referred to in Articles 265(1)(a), 267(1)(a) or 269(1)(a).
Where the contracting authority decides not to require evidence of the legal, regulatory, financial, economic, technical and professional capacity of economic operators, no pre-financing shall be made.
5. An economic operator may, where appropriate and for a particular contract, rely on the capacities of other entities, regardless of the legal nature of the links which it has with them. It must in that case prove to the contracting authority that it will have at its disposal the resources necessary for the performance of the contract by producing a commitment by those entities to that effect.
With regard to technical and professional criteria, an economic operator may only rely on the capacities of other entities where the latter will perform the works or services for which these capacities are required.
Where an economic operator relies on the capacities of other entities with regard to criteria relating to economic and financial capacity, the contracting authority may require that the economic operator and those entities be jointly liable for the performance of the contract.
The contracting authority may request information from the tenderer on any part of the contract that the tenderer intends to subcontract and on the identity of any subcontractors.
For works or services provided at a facility directly under the oversight of the contracting authority, the contracting authority shall require the contractor to indicate the names, contacts and authorised representatives of subcontractors involved in the performance of the contract, including any changes of subcontractors.
6. The contracting authority shall verify whether the entities on whose capacity the economic operator intends to rely and the envisaged subcontractors, when subcontracting represents a significant part of the contract, fulfil the relevant selection criteria.
The contracting authority shall require that the economic operator replaces an entity or subcontractor which does not meet a relevant selection criterion.
7. In the case of works contracts, service contracts and siting or installation operations in the context of a supply contract, the contracting authority may require that certain critical tasks be performed directly by the tenderer itself or, where the tender is submitted by a group of economic operators, a participant in the group.
1. To ensure that economic operators possess the necessary economic and financial capacity to perform the contract, the contracting authority may require in particular that:
(a) economic operators have a certain minimum yearly turnover, including a certain minimum turnover in the area covered by the contract;
(b) economic operators provide information on their annual accounts showing ratios between assets and liability;
(c) economic operators provide an appropriate level of professional risk indemnity insurance.
For the purposes of point (a) of the first subparagraph, the minimum yearly turnover shall not exceed two times the estimated annual contract value, except in duly justified cases linked to the nature of the purchase, which the contracting authority shall explain in the procurement documents.
For the purposes of point (b) of the first subparagraph, the contracting authority shall explain the methods and criteria for such ratios in the procurement documents.
2. In the case of dynamic purchasing systems, the maximum yearly turnover shall be calculated on the basis of the expected maximum size of specific contracts to be awarded under that system.
3. The contracting authority shall define in the procurement documents the evidence to be provided by an economic operator to demonstrate its economic and financial capacity. It may request in particular one or more of the following documents:
(a) appropriate statements from banks or, where appropriate, evidence of relevant professional risk indemnity insurance;
(b) financial statements or their extracts for a period equal to or less than the last three years for which accounts have been closed;
(c) a statement of the economic operator's overall turnover and, where appropriate, turnover in the area covered by the contract for a maximum of the last three financial years available.
If, for any valid reason, the economic operator is unable to provide the references requested by the contracting authority, it may prove its economic and financial capacity by any other document which the contracting authority considers appropriate.
1. The contracting authority shall verify that candidates or tenderers fulfil the minimum selection criteria concerning technical and professional capacity in accordance with paragraphs 2 to 5.
2. The contracting authority shall define in the procurement documents the evidence to be provided by an economic operator to demonstrate its technical and professional capacity. It may request one or more of the following documents:
(a) for works, supplies requiring siting or installation operations or services, the educational and professional qualifications, skills, experience and expertise of the persons responsible for performance;
(b) a list of the following:
of the principal services provided and supplies delivered in the past three years, with the sums, dates and clients, public or private accompanied upon request by statements issued by the clients;
of the works carried out in the last five years, accompanied by certificates of satisfactory execution for the most important works;
(c) a statement of the technical equipment, tools or plant available to the economic operator for performing a service or works contract;
(d) a description of the technical facilities and means available to the economic operator to for ensuring quality, and a description of available study and research facilities;
(e) a reference to the technicians or technical bodies available to the economic operator, whether or not belonging directly to it, especially those responsible for quality control;
(f) in respect of supplies: samples, descriptions or authentic photographs or certificates drawn up by official quality control institutes or agencies of recognised competence attesting the conformity of the products clearly identified by references to technical specifications or standards;
(g) for works or services, a statement of the average annual manpower and the number of managerial staff of the economic operator for the last three years;
(h) an indication of the supply chain management and tracking systems that the economic operator will be able to apply when performing the contract;
(i) an indication of the environmental management measures that the economic operator will be able to apply when performing the contract.
For the purposes of point (i) of point (b) of the first subparagraph, where necessary in order to ensure an adequate level of competition, the contracting authority may indicate that evidence of relevant supplies or services delivered or performed more than three years before will be taken into account.
For the purposes of point (ii) of point (b) of the first subparagraph, where necessary in order to ensure an adequate level of competition, the contracting authority may indicate that evidence of relevant works delivered or performed more than five years before will be taken into account.
3. Where the supplies or services are complex or, exceptionally, are required for a special purpose, evidence of technical and professional capacity may be secured by means of a check carried out by the contracting authority or on its behalf by a competent official body of the country in which the economic operator is established, subject to that body's agreement. Such checks shall concern the supplier's technical capacity and production capacity and, if necessary, its study and research facilities and quality control measures.
4. Where the contracting authority requires the provision of certificates drawn up by independent bodies attesting the compliance of the economic operator with certain quality assurance standards, including on accessibility for disabled persons, it shall refer to quality assurance systems based on the relevant European standards series certified by accredited bodies. The contracting authority shall also accept other evidence of equivalent quality assurance measures from an economic operator that has demonstrably no access to such certificates or has no possibility of obtaining such certificates within the relevant time limits, for reasons that are not attributable to that economic operator and provided that the economic operator proves that the proposed quality assurance measures comply with the required quality assurance standards.
5. Where the contracting authority requires the provision of certificates drawn up by independent bodies attesting that the economic operator complies with certain environmental management systems or standards, it shall refer to the European Union Eco-Management and Audit Scheme or to other environmental management systems as recognised in accordance with Article 45 of Regulation (EC) No 1221/2009 of the European Parliament and of the Council (11) or other environmental management standards based on the relevant European or international standards by accredited bodies. Where an economic operator had demonstrably no access to such certificates, or no possibility of obtaining them within the relevant time limits for reasons that are not attributable to that economic operator, the contracting authority shall also accept other evidence of environmental management measures, provided that the economic operator proves that these measures are equivalent to those required under the applicable environmental management system or standard.
6. A contracting authority may conclude that an economic operator does not possess the required professional capacity to perform the contract to an appropriate quality standard where the contracting authority has established that the economic operator has conflicting interests which may negatively affect its performance.
1. Quality criteria may include elements such as technical merit, aesthetic and functional characteristics, accessibility, design for all users, social, environmental and innovative characteristics, production, provision and trading process and any other specific process at any stage of their life cycle, organisation of the staff assigned to performing the contract, after-sales service, technical assistance or delivery conditions such as delivery date, delivery process and delivery period or period of completion.
2. The contracting authority shall specify, in the procurement documents the relative weighting which it gives to each of the criteria chosen to determine the most economically advantageous tender except when using the lowest price method. Those weightings may be expressed as a range with an appropriate maximum spread.
The weighting applied to price or cost in relation to the other criteria must not result in the neutralisation of price or cost.
If weighting is not possible for objective reasons, the contracting authority shall indicate the criteria in decreasing order of importance.
3. The contracting authority may lay down minimum levels of quality. Tenders below those levels of quality shall be rejected.
4. Life-cycle costing shall cover parts or all of the following costs, to the extent relevant, over the life cycle of works, supplies or services:
(a) costs, borne by the contracting authority or other users, such as:
costs relating to acquisition;
costs of use, such as consumption of energy and other resources;
maintenance costs;
end of life costs, such as collection and recycling costs;
(b) costs attributed to environmental externalities linked to the works, supplies or services during their life cycle, provided their monetary value can be determined and verified.
5. Where the contracting authority assesses the costs using a life-cycle costing approach, it shall indicate in the procurement documents the data to be provided by the tenderers and the method which it will use to determine the life-cycle costs on the basis of those data.
The method used for the assessment of costs attributed to environmental externalities shall fulfil the following conditions:
(a) it is based on objectively verifiable and non-discriminatory criteria;
(b) it is accessible to all interested parties;
(c) economic operators can provide the required data with reasonable effort.
Where applicable, the contracting authority shall use the mandatory common methods for the calculation of life- cycle costs provided for in Annex XIII of Directive 2014/24/EU.
1. The contracting authority may use electronic auctions, in which new prices, revised downwards or new values concerning certain elements of tenders are presented.
The contracting authority shall structure the electronic auction as a repetitive electronic process, which occurs after an initial full evaluation of the tenders, enabling them to be ranked using automatic evaluation methods.
2. In open, restricted or competitive procedures with negotiation, the contracting authority may decide that the award of a public contract is preceded by an electronic auction when the procurement documents can be established with precision.
An electronic auction may be held on the reopening of competition among the parties to a framework contract as referred to in Article 122(3)(b) and on the opening for competition of contracts to be awarded under the dynamic purchasing system referred to in Article 131.
The electronic auction shall be based on one of the award methods set out in Article 110(4) of the Financial Regulation.
3. The contracting authority which decides to hold an electronic auction shall state that fact in the contract notice.
The procurement documents shall include the following details:
(a) the values of the features which will be the subject of electronic auction, provided that those features are quantifiable and can be expressed in figures or percentages;
(b) any limits on the values which may be submitted, as they result from the specifications relating to the subject matter of the contract;
(c) the information which will be made available to tenderers in the course of the electronic auction and, where appropriate, when it will be made available to them;
(d) the relevant information concerning the electronic auction process including whether it includes phases and how it will be closed, as set out in paragraph 7;
(e) the conditions under which the tenderers will be able to tender and, in particular, the minimum differences which will, where appropriate, be required when submitting the tender;
(f) the relevant information concerning the electronic equipment used and the arrangements and technical specifications for connection.
4. All tenderers who have submitted admissible tenders shall be invited simultaneously by electronic means to participate in the electronic auction using the connections in accordance with the instructions. The invitation shall specify the date and time of the start of the electronic auction.
The electronic auction may take place in a number of successive phases. The electronic auction may not start sooner than two working days after the date on which invitations are sent out.
5. The invitation shall be accompanied by the outcome of a full evaluation of the relevant tender.
The invitation shall also state the mathematical formula to be used in the electronic auction to determine automatic re-rankings on the basis of the new prices and/or new values submitted. That formula shall incorporate the weighting of all the criteria fixed to determine the most economically advantageous tender, as indicated in the procurement documents. For that purpose, any ranges shall, however, be reduced beforehand to a specified value.
Where variants are authorised, a separate formula shall be provided for each variant.
6. Throughout each phase of an electronic auction the contracting authority shall instantaneously communicate to all tenderers at least sufficient information to enable them to ascertain their relative rankings at any moment. It may also, where this has been previously indicated, communicate other information concerning other prices or values submitted as well as announce the number of participants in any specific phase of the auction. It may not however disclose the identities of the tenderers during any phase of an electronic auction.
7. The contracting authority shall close an electronic auction in one or more of the following ways:
(a) at the previously indicated date and time;
(b) when it receives no more new prices or new values which meet the requirements concerning minimum differences, provided that it has previously stated the time which it will allow to elapse after receiving the last submission before it closes the electronic auction;
(c) when the previously indicated number of phases in the auction has been completed.
8. After closing an electronic auction, the contracting authority shall award the contract on the basis of the results of the electronic auction.
1. If, for a given contract, the price or cost proposed in a tender appears to be abnormally low, the contracting authority shall request in writing details of the constituent elements of the price or cost which it considers relevant and shall give the tenderer the opportunity to present its observations.
The contracting authority may, in particular, take into consideration observations relating to:
(a) the economics of the manufacturing process, of the provision of services or of the construction method;
(b) the technical solutions chosen or the exceptionally favourable conditions available to the tenderer;
(c) the originality of the tender;
(d) compliance of the tenderer with applicable obligations in the fields of environmental, social and labour law;
(e) compliance of subcontractors with applicable obligations in the fields of environmental, social and labour law;
(f) the possibility of the tenderer obtaining state aid in compliance with applicable rules.
2. The contracting authority may only reject the tender where the evidence supplied does not satisfactorily account for the low level of price or costs proposed.
The contracting authority shall reject the tender, where it has established that the tender is abnormally low because it does not comply with applicable obligations in the fields of environmental, social and labour law.
3. Where the contracting authority establishes that a tender is abnormally low because the tenderer has obtained state aid, it may reject the tender on that sole ground only if the tenderer is unable to prove, within a sufficient time limit fixed by the contracting authority, that the aid in question was compatible with the internal market within the meaning of Article 107 TFEU.
1. The contracting authority shall lay down time limits for the receipt of tenders and requests to participate.
When fixing time limits, the contracting authority shall take account of the complexity of the contract and the time required for drawing up tenders. The time limits shall be longer than the minimum time limits set out in this Article where tenders can only be drawn after a visit to the site or after an on-the-spot consultation of the documents supporting the procurement documents.
The time limits shall be prolonged by five days in any of the following cases:
(a) the contracting authority does not offer direct access free of charge by electronic means to the procurement documents;
(b) the contract notice is published in accordance with point (b) of Article 125(2).]
2.In open procedures for contracts with a value equal to or above the thresholds set in Article 170(1), the time limit for receipt of tenders shall be no less than [F142 days] from the date on which the contract notice is dispatched.
3.In restricted procedures, in cases of use of the competitive dialogue referred to in Article 132 and in negotiated procedures with publication of a contract notice for contracts above the thresholds set in Article 170(1), the time limit for receipt of requests to participate shall be no less than 37 days from the date on which the contract notice is dispatched.
In restricted procedures for contracts with a value equal to or above the thresholds set in Article 170(1), the time limit for receipt of tenders shall be no less than 40 days from the date on which the invitation to tender is dispatched.
However, in the procedures after a call for expressions of interest referred to in Article 136(1), the time limit shall be:
(a)no less than 21 days from the date on which the invitation to tender is dispatched for receipt of tenders in the case of the procedure referred to in Article 136(1)(a) and Article 136(3)(b)(i);
(b)no less than 10 days for receipt of requests to participate and no less than 21 days for receipt of tenders in the case of the two-step procedure referred to in Article 136(3)(b)(ii).
[F14. In restricted procedures and in competitive procedures with negotiation, the time limit for receipt of tenders shall be no less than 30 days from the date on which the invitation to tender is dispatched.
5. In a dynamic purchasing system, the time limit for receipt of tenders shall be no less than 10 days from the date on which the invitation to tender is dispatched.
6. In the procedures after a call for expressions of interest referred to in Article 136(1), the time limit shall be:
(a) no less than 10 days from the date on which the invitation to tender is dispatched for receipt of tenders in the case of the procedure referred to in Article 136(1)(a) and Article 136(3)(b)(i);
(b) no less than 10 days for receipt of requests to participate and no less than 10 days for receipt of tenders in the case of the two-step procedure referred to in Article 136(3)(b)(ii).
7. The contracting authority may reduce the time limits for receipt of tenders by five days for the open or restricted procedures if it accepts that tenders may be submitted by electronic means.
1. The contracting authority shall offer direct access free of charge by electronic means to the procurement documents from the date of publication of the contract notice or, for the procedures without contract notice or under Article 136, from the date of dispatch of the invitation to tender.
In justified cases, the contracting authority may transmit the procurement documents by other means it specifies if direct access by electronic means is not possible for technical reasons or if the procurement documents contain information of a confidential nature. In these cases, the third subparagraph of Article 152(1) shall apply except in urgent cases as provided for in Article 154(1).
The contracting authority may impose on economic operators requirements aimed at protecting the confidential nature of information contained in the procurement documents. It shall announce these requirements as well as how access to the procurement documents concerned can be obtained.
2. The contracting authority shall provide additional information linked to the procurement documents simultaneously and in writing to all interested economic operators as soon as possible.
The contracting authority shall not be bound to reply to requests for additional information made less than six working days before the deadline for receipt of tenders.
3. The contracting authority shall extend the time limit for receipt of tenders where:
(a) it did not provide additional information at the latest six days before the deadline for the receipt of tenders although the economic operator requested it in good time;
(b) it makes significant changes to the procurement documents.
1. Where duly substantiated urgency renders impracticable the minimum time limits laid down in Articles 152(2) and 152(3) for open or restricted procedures, the contracting authority may set:
(a) a time limit for the receipt of requests to participate or tenders in open procedures which shall not be less than 15 days from the date on which the contract notice was dispatched;
(b) a time limit for the receipt of tenders for restricted procedures which shall not be less than 10 days from the date of dispatch of the invitation to tender.
2. In urgent cases, the time limit set out in the first subparagraph of Article 153(2) and in Article 153(3)(a) shall be four days.
1. The arrangements for the submission of tenders and requests to participate shall be determined by the contracting authority, which may choose an exclusive method of submission.
The means of communication chosen shall be such as to ensure that the following conditions are satisfied:
(a) each submission contains all the information required for its evaluation;
(b) the integrity of data is preserved;
(c) the confidentiality of tenders and requests to participate is preserved and the contracting authority examines the content of tenders and requests to participate only after the time limit set for submitting them has expired;
(d) the protection of personal data in accordance with the requirements of Regulation (EC) No 45/2001 is ensured.
2. Except for contracts below the thresholds laid down in Article 118(1) of the Financial Regulation, devices for the electronic receipt of tenders and requests to participate shall guarantee, through technical means and appropriate procedures, that:
(a) the economic operator can be authenticated with certainty;
(b) the exact time and date of the receipt of tenders and requests to participate can be determined precisely;
(c) it may be reasonably ensured that, before the time limits laid down, no-one can have access to data transmitted under these requirements;
(d) only authorised persons may set or change the dates for opening data received;
(e) during the different stages of the procurement procedure only authorised persons may have access to all data submitted and may give access to these data as needed for the procedure;
(f) it may be reasonably ensured that any attempt to infringe any of the conditions set out in points (a) to (e) can be detected.
3. Where the contracting authority authorises submission of tenders and requests to participate by electronic means, the electronic documents submitted by means of such systems shall be deemed to be the originals.
4. Where submission is by letter, candidates or tenderers may choose to submit requests to participate or tenders:
(a) either by post or by courier service, in which case the evidence shall be constituted by the postmark or the date of the deposit slip;
(b) by hand-delivery to the premises of the contracting authority by the tenderer or candidate in person or by an agent, in which case the evidence shall be constituted by the acknowledgement of receipt.
5. By submitting a request to participate or a tender, candidates or tenderers accept to receive notification of the outcome of the procedure by electronic means.
1. Where the use of electronic means of communication is required, the contracting authority may require tenders to be presented in the format of an electronic catalogue or to include an electronic catalogue.
2. Where the presentation of tenders in the form of electronic catalogues is accepted or required, the contracting authority shall:
(a) state so in the contract notice;
(b) indicate in the procurement documents all the necessary information concerning the format, the electronic equipment used and the technical connection arrangements and specifications for the catalogue.
3. Where a multiple framework contract has been concluded following the submission of tenders in the form of electronic catalogues, the contracting authority may provide that the reopening of competition for specific contracts takes place on the basis of updated catalogues by using one of the following methods:
(a) the contracting authority invites contractors to resubmit their electronic catalogues, adapted to the requirements of the specific contract in question;
(b) the contracting authority notifies contractors that it intends to collect from the electronic catalogues which have already been submitted the information needed to constitute tenders adapted to the requirements of the specific contract in question, provided that the use of that method has been announced in the procurement documents for the framework contract.
4. When using the method under point (b) of paragraph 3, the contracting authority shall notify contractors of the date and time at which they intend to collect the information needed to constitute tenders adapted to the requirements of the specific contract in question and shall give contractors the possibility to refuse such collection of information.
The contracting authority shall allow for an adequate period between the notification and the actual collection of information.
Before awarding the specific contract, the contracting authority shall present the collected information to the contractor concerned so as to give it the opportunity to contest or confirm that the tender thus constituted does not contain any material errors.
1. The contracting authority may require a tender guarantee, submitted in accordance with Article 163, representing 1 % to 2 % of the total value of the contract.
2. The contracting authority shall call in the tender guarantee if the tender is withdrawn before contract signature.
The contracting authority shall release the tender guarantee:
(a) for tenderers rejected as referred to in point (b) of Article 159(2) and tenders rejected as referred to in point (c) of Article 159(2), after information on the outcome of the procedure;
(b) for tenders ranked as referred to in point (e) of Article 159(2), when the contract is signed.
1. In open procedures, authorised representatives from tenderers may attend the opening session.
2. Where the value of a contract is equal to or greater than the thresholds laid down in Article 118(1) of the Financial Regulation, the authorising officer responsible shall appoint a committee to open the tenders. The authorising officer may waive this obligation on the basis of a risk analysis when reopening competition within a framework contract and for the cases set out in Article 134(1) of this Regulation except points (d) and (g) of that Article.
The opening committee shall be made up of at least two persons representing at least two organisational entities of the institution concerned with no hierarchical link between them. To avoid any conflict of interests, those persons shall be subject to the obligations laid down in Article 57 of the Financial Regulation.
In the representations or local units referred to in Article 72 of this Regulation or isolated in a Member State, if there are no separate entities, the requirement of organisational entities with no hierarchical link between them shall not apply.
3. In the case of a procurement procedure launched on an interinstitutional basis, the opening committee shall be appointed by the responsible authorising officer from the institution responsible for the procurement procedure.
4. The contracting authority shall verify and ensure the integrity of the original tender including the financial offer and of the evidence of date and time of its receipt as provided for in points 2 and 4 of Article 155 by any appropriate method.
5. In open procedures, where the contract is awarded under the lowest price or lowest cost methods in accordance with Article 110(4) of the Financial Regulation, the prices quoted in tenders satisfying the requirements shall be read out loud.
6. The written record of the opening of the tenders received shall be signed by the person or persons in charge of opening or by members of the opening committee. It shall identify those tenders which comply with the requirements of Article 155 and those which do not, and shall give the grounds on which tenders were rejected as set out in Article 111(4) of the Financial Regulation. That record may be signed in an electronic system providing sufficient identification of the signatory.
1. The authorising officer responsible shall appoint an evaluation committee to give an advisory opinion on contracts with a value equal to or greater than the thresholds referred to in Article 118(1) of the Financial Regulation. The authorising officer may waive this obligation on the basis of a risk analysis when reopening competition within a framework contract and for the cases set out in points (c), (e), (f) (i), (f) (iii) and (h) of Article 134(1).
However, the authorising officer responsible may decide that the evaluation committee is to evaluate and rank the tenders on the basis of the award criteria only and that the exclusion and selection criteria are to be evaluated by other appropriate means guaranteeing the absence of conflicts of interests.
2. The evaluation committee shall be made up of at least three persons representing at least two organisational entities of the institutions or bodies referred to in Article 208 of the Financial Regulation with no hierarchical link between them, at least one of which does not come under the authorising officer responsible.
In the representations and local units referred to in Article 72 or isolated in a Member State, if there are no separate entities, the requirement of organisational entities with no hierarchical link between them shall not apply.
Outside experts may assist the committee by decision of the authorising officer responsible.
The authorising officer responsible shall ensure that the persons involved in the evaluation including outside experts satisfy the obligations laid down in Article 57 of the Financial Regulation.
3. In the case of a procurement procedure launched on an interinstitutional basis, the evaluation committee shall be appointed by the responsible authorising officer from the institution responsible for the procurement procedure. The composition of the evaluation committee shall reflect, in so far as possible, the interinstitutional character of the procurement procedure.
4. Requests to participate and tenders which are suitable under paragraph (2) of Article 134, not irregular or unacceptable under paragraphs (2) and (3) of Article 135 shall be considered admissible.
1. The outcome of the evaluation shall be an evaluation report containing the proposal to award the contract. The evaluation report shall be dated and signed by the person or persons who carried out the evaluation or by the members of the evaluation committee. That report may be signed in an electronic system providing sufficient identification of the signatory.
If the evaluation committee was not given responsibility to verify the tenders against the exclusion and selection criteria, the evaluation report shall also be signed by the persons who were given that responsibility by the authorising officer responsible.
2. The evaluation report shall contain the following:
(a) the name and address of the contracting authority, and the subject matter and value of the contract, or the subject matter and maximum value of the framework contract;
(b) the names of the candidates or tenderers rejected and the reasons for their rejection by reference to a situation set out in Article 107 of the Financial Regulation or to selection criteria;
(c) the references to the tenders rejected and the reasons for their rejection by reference to any of the following:
non-compliance with minimum requirements as set out in point (a) of Article 110(1) of the Financial Regulation;
not meeting the minimum quality levels laid down in Article 149(3) of this Regulation;
tenders found to be abnormally low as referred to in Article 151 of this Regulation;
(d) the names of the candidates or tenderers selected and the reasons for their selection;
(e) the names of the tenderers to be ranked with the scores obtained and their justifications;
(f) the names of the proposed candidates or successful tenderer and the reasons for that choice;
(g) if known, the proportion of the contract or the framework contract which the proposed contractor intends to subcontract to third parties.
3. The contracting authority shall then take its decision providing any of the following:
(a) an approval of the evaluation report containing all the information listed in paragraph 2 complemented by the following:
the name of the successful tenderer and the reasons for that choice by reference to the pre-announced selection and award criteria, including where appropriate the reasons for not following the recommendation provided in the evaluation report;
in the case of negotiated procedure without prior publication, competitive procedure with negotiation or competitive dialogue, the circumstances referred to in Articles 134, 135 and 266 which justify their use;
(b) where appropriate, the reasons why the contracting authority has decided not to award a contract.
4. The authorising officer may merge the content of the evaluation report and award decision into a single document and sign it in any of the following cases:
(a) for procedures below the thresholds set out in Article 118(1) of the Financial Regulation where only one tender was received;
(b) when reopening competition within a framework contract where no evaluation committee was nominated;
(c) for cases under points (c), (e), (f)(i), (f)(iii) and (h) of Article 134(1) where no evaluation committee was nominated.
5. In the case of a procurement procedure launched on an interinstitutional basis, the decision referred to in paragraph 3 shall be taken by the contracting authority responsible for the procurement procedure.
1. Contact between the contracting authority and candidates or tenderers during the procurement procedure may take place, exceptionally, under the conditions set out in paragraphs 2 and 3.
2. Before the closing date for receipt of requests to participate or tenders, the contracting authority may communicate the additional information in accordance with Article 153(2):
(a) at the instance of candidates or tenderers, solely for the purpose of clarifying procurement documents;
(b) at its own instance, if it discovers an error, a lack of precision, an omission or any other type of clerical defect in the text of the procurement documents.
3. In every case where contact has been made, and in the duly justified cases where contact has not been made as referred to in Article 96 of the Financial Regulation, a record shall be kept in the procurement file.
1. The contracting authority shall inform all candidates or tenderers, simultaneously and individually, by electronic means of decisions reached concerning the outcome of the procedure as soon as possible after any of the following stages:
(a) the opening phase for the cases referred to in Article 111(4) of the Financial Regulation;
(b) a decision has been taken on the basis of exclusion and selection criteria in procurement procedures organised in two separate stages;
(c) the award decision.
In each case, the contracting authority shall indicate the reasons why the request to participate or tender has not been accepted and the available legal remedies.
When informing the successful tenderer, the contracting authority shall specify that the decision notified does not constitute a commitment on its part.
2. The contracting authority shall communicate the information provided for in Article 113(3) of the Financial Regulation as soon as possible and in any case within 15 days of receipt of a request in writing. When the contracting authority awards contracts for its own account, it shall use electronic means. The tenderer may also send the request by electronic means.
3. When the contracting authority communicates through electronic means, information shall be deemed to have been received by candidates or tenderers if the contracting authority can prove to have sent it to the electronic address referred to in the tender or in the request to participate.
In such case, information shall be deemed to have been received by the candidate or tenderer on the date of dispatch by the contracting authority.]
1. If the contracting authority decides to request a guarantee, it shall announce this in the procurement documents.
2. Where contractors are required to submit a guarantee, it must be for an amount and a period that are sufficient for it to be called.
3. The guarantee shall be supplied by a bank or an authorised financial institution accepted by the contracting authority. It may be replaced by a joint and several guarantee by a third party, after acceptance by the contracting authority.
The guarantee shall be denominated in euro.
It shall have the effect of making the bank or financial institution or the third party stand as irrevocable collateral security, or first-call guarantor of the contractor's obligations.
1. Once the contracting authority has established the need for a pre-financing, it shall assess the risks associated with pre-financing payments, before launching the procurement procedure, taking into account in particular the following criteria:
(a) the estimated value of the contract;
(b) its subject matter;
(c) its duration and pace;
(d) the structure of the market.
2. No guarantee shall be required for low value contracts referred to in Article 137(1).
The guarantee shall be released as and when the pre-financing is deducted from interim payments or payments of the balance to the contractor in accordance with the terms of the contract.
1. On a case-by-case basis and subject to a preliminary risk analysis, the contracting authority may request a performance guarantee to ensure that the contractor complies with its substantial contractual obligations.
2. The performance guarantee shall amount to a maximum of 10 % of the total value of the contract.
3. It shall be fully released after final acceptance of the works, supplies or complex services, within a period subject to Article 92(1) of the Financial Regulation to be specified in the contract. It may be released partially or fully upon provisional acceptance of the works, supplies or complex services.
1. On a case-by-case basis and subject to a preliminary risk analysis, the contracting authority may request a retention money guarantee to ensure that the contractor remedies defects during the contract liability period.
The retention money guarantee shall not be used in a contract where a performance guarantee has been requested and not released.
2. A retention money guarantee amounting to a maximum of 10 % of the total value of the contract may be constituted by deductions from interim payments as and when they are made or by deduction from the final payment.
The contracting authority shall determine the amount which shall be proportionate to the risks identified in relation to the performance of the contract, taking into account its subject matter and the usual commercial terms applicable to the sector.
3. Subject to approval by the contracting authority, the contractor may request to replace the retention money guarantee by a guarantee referred to in Article 163.
4. The contracting authority shall release the retention money guarantee after the expiry of the contractual liability period, within a period subject to Article 92(1) of the Financial Regulation to be specified in the contract.
If, after suspending performance of the contract in accordance with Article 116(3) of the Financial Regulation, presumed substantial errors or irregularities or fraud are not confirmed, performance of the contract shall resume as soon as possible.]
1. A central purchasing body may act as any of the following:
(a) as wholesaler by buying, stocking and reselling supplies and services to other contracting authorities;
(b) as intermediary by awarding framework contracts or operating dynamic purchasing systems that may be used by other contracting authorities as announced in the initial notice.
2. The central purchasing body shall carry out all procurement procedures using electronic means of communication.
Each authorising officer by delegation or subdelegation within each institution shall assess whether the thresholds laid down in Article 118(1) of the Financial Regulation have been reached.
1. Whenever appropriate, technically feasible, and cost efficient, contracts shall be awarded in the form of separate lots within the same procedure.
2. Where the subject matter of a contract is subdivided into several lots, each one being the subject of an individual contract, the total value of all the lots shall be taken into account for the overall evaluation of the applicable threshold.
Where the total value of all the lots is equal to or greater than the thresholds laid down in Article 118(1) of the Financial Regulation, Articles 103(1), 104 and 104a of the Financial Regulation shall apply to each of the lots.
3. Where a contract is to be awarded in the form of separate lots, tenders shall be evaluated separately for each lot. If several lots are awarded to the same tenderer, a single contract covering those lots may be signed.
1. The contracting authority shall estimate the value of a contract based on the total amount payable including any form of options and any renewal.
This estimate shall be made at the latest when the contracting authority launches the procurement procedure.
2. For framework contracts and dynamic purchasing systems the value to be taken into account shall be the maximum value of all the contracts envisaged during the total duration of the framework contract or dynamic purchasing system.
For innovation partnerships, the value to be taken into account shall be the maximum estimated value of the research and development activities to take place during all stages of the envisaged partnership as well as of the works, supplies or services to be purchased at the end of the envisaged partnership.
Where the contracting authority provides for payments to candidates or tenderers it shall take them into account when calculating the estimated value of the contract.
3. For service contracts, account shall be taken of the following:
(a) in the case of insurance services, the premium payable and other forms of remuneration;
(b) in the case of banking or financial services, the fees, commissions, interest and other types of remuneration;
(c) in the case of design contracts, the fees, commissions payable and other forms of remuneration.
4. In the case of service contracts which do not specify a total price or of supply contracts for leasing, hire, rental or hire purchase of products, the basis for calculating the estimated contract value shall be:
(a) in the case of fixed-term contracts:
where their duration is 48 months or less in the case of services or 12 months or less in the case of supplies, the total contract value for their duration;
where their duration is more than 12 months in the case of supplies, the total value including the estimated residual value;
(b) in the case of contracts without a fixed term or, in the case of services, for a duration exceeding 48 months, the monthly value multiplied by 48.
5. In the case of service or supply contracts which are awarded regularly or are to be renewed within a given period, the basis for calculating the estimated contract value shall be any of the following:
(a) the total actual value of successive contracts of the same type awarded during the preceding 12 months or financial year, adjusted, where possible, to take account of the changes in quantity or value which would occur in the course of the 12 months following the initial contract;
(b) the total estimated value of successive contracts of the same type to be awarded during the financial year.
6. In the case of works contracts, account shall be taken not only of the value of the works but also of the estimated total value of the supplies and services needed to carry out the works and made available to the contractor by the contracting authority.
7. In the case of concession contracts, the value shall be the estimated total turnover of the concessionaire generated over the duration of the contract.
The value shall be calculated using an objective method specified in the procurement documents, taking into account in particular:
(a) the revenue from the payment of fees and fines by the users of the works or services other than those collected on behalf of the contracting authority;
(b) the value of grants or any other financial advantages from third parties for the performance of the concession;
(c) the revenue from sales of any assets which are part of the concession;
(d) the value of all the supplies and services that are made available to the concessionaire by the contracting authority provided that they are necessary for executing the works or services;
(e) the payments to candidates or tenderers.
1. The standstill period shall run from either of the following dates:
(a) the day after the simultaneous dispatch of the notifications to successful and unsuccessful tenderers by electronic means;
(b) where the contract or framework contract is awarded pursuant to Article 134(1)(b), the day after the contract award notice referred to in Article 123(5) has been published in the Official Journal of the European Union .
If necessary, the contracting authority may suspend the signature of the contract for additional examination if this is justified by the requests or comments made by unsuccessful or aggrieved candidates or tenderers or by any other relevant information received during the period set in Article 118(3) of the Financial Regulation. In the case of suspension all the candidates or tenderers shall be informed within three working days following the suspension decision.
Where the contract or framework contract cannot be signed with the successful envisaged tenderer, the contracting authority may award it to the following best tenderer.
2. The period set in paragraph 1 shall not apply in the following cases:
(a) any procedure where only one tender has been submitted;
(b) specific contracts based on a framework contract;
(c) dynamic purchasing systems;
(d) negotiated procedure without prior publications referred to in Article 134 except the procedure under Article 134(1)(b).
The procurement documents shall require candidates or tenderers to indicate in which State they are established and to present the supporting evidence normally acceptable under the law of that State.]
The subscriptions referred to in Article 121(2)(d) of the Financial Regulation shall be sums paid to bodies of which the Union is member, in accordance with the budgetary decisions and the conditions of payment established by the body concerned.
1.Grants shall be covered by a decision or by a written agreement.
2.To determine the instrument to be used, the following elements shall be taken into account:
(a)location of the beneficiary, within or outside the Union;
(b)complexity and standardisation of the content of the actions or work programmes funded.
Expenditure on the members of the institutions as referred to in Article 121(2)(a) of the Financial Regulation shall include contributions to associations of current and former members of the European Parliament. These contributions shall be implemented in accordance with the internal administrative rules of the European Parliament.
An action which may receive a grant within the meaning of Article 121 of the Financial Regulation must be clearly defined.
No action may be split in different actions for the purpose of evading the financing rules laid down in this Regulation.
A body pursuing an aim of general Union interest is:
a body involved in education, training, information, innovation or research and study in European policies, any activities contributing to the promotion of citizenship or human rights, or an European standards body;
an entity representing non-profit bodies active in the Member States, in the candidate countries or in the potential candidate countries and promoting principles and policies consistent with the objectives of the Treaties.
1.Specific grants for actions and operating grants may form part of a framework partnership.
2.A framework partnership may be established as a long-term cooperation mechanism between the Commission and the beneficiaries of grants. It may take the form of a framework partnership agreement or a framework partnership decision.
The framework partnership agreement or decision shall specify the common objectives, the nature of actions planned on a one-off basis or as part of an approved annual work programme, the procedure for awarding specific grants, in compliance with the principles and procedural rules in this Title, and the general rights and obligations of each party under the specific agreements or decisions.
The duration of the partnership may not exceed four years, save in exceptional cases, justified in particular by the subject of the framework partnership.
Authorising officers may not make undue use of framework partnership agreements or decisions or use them in such a way that the purpose or effect is contrary to the principles of transparency or equal treatment of applicants.
3.Framework partnerships shall be treated as grants with regard to programming, ex ante publication and award.
4.Specific grants based on framework partnership agreements or decisions shall be awarded in accordance with the procedures laid down in those agreements or decisions, and in compliance with this Title.
They shall be subject to the ex post publication procedures laid down in Article 191.
1.All exchanges with beneficiaries, including the conclusion of grant agreements, the notification of grant decisions and any amendments thereto, may be done through electronic exchange systems set up by the Commission.
2.These systems shall meet the following requirements:
(a)only authorised persons may have access to the system and to documents transmitted through it;
(b)only authorised persons may electronically sign or transmit a document through the system;
(c)authorised persons must be identified through the system by established means;
(d)the time and date of the electronic transaction must be determined precisely;
(e)the integrity of documents must be preserved;
(f)the availability of documents must be preserved;
(g)where appropriate, the confidentiality of documents must be preserved;
(h)the protection of personal data in accordance with the requirements of Regulation (EC) No 45/2001 must be ensured.
3.Data sent or received through such a system shall enjoy legal presumption of the integrity of the data and the accuracy of the date and time of sending or receiving the data indicated by the system.
A document sent or notified through such a system shall be considered as equivalent to a paper document, shall be admissible as evidence in legal proceedings, shall be deemed original and shall enjoy legal presumption of its authenticity and integrity, provided it does not contain any dynamic features capable of automatically changing it.
The electronic signatures referred to in point (b) of paragraph 2 shall have the equivalent legal effect of handwritten signatures.
1.The grant agreement shall at least lay down the following:
(a)the subject;
(b)the beneficiary;
(c)the duration, namely:
the date of its entry into force;
the starting date and the duration of the action or financial year being funded;
(d)the maximum amount of Union funding expressed in euro and the form of the grant supplemented, as appropriate, by:
the total estimated eligible costs of the action or work programme and the financing rate of the eligible costs;
the unit cost, lump sum or flat rate referred to in points (b), (c) and (d) of Article 123 of the Financial Regulation where determined;
a combination of the elements set out in points (i) and (ii) of this point;
(e)a description of the action or, for an operating grant, of the work programme approved for that financial year by the authorising officer together with a description of the results expected from the implementation of the action or of the work programme;
(f)the general terms and conditions applicable to all agreements of this type, such as the acceptance by the beneficiary of checks and audits by the Commission, OLAF and the Court of Auditors;
(g)the estimated overall budget of the action or work programme;
(h)where implementation of the action involves procurement, the principles referred to in Article 209 or the procurement rules which the beneficiary must comply with;
(i)the responsibilities of the beneficiary, in particular:
in terms of sound financial management and submission of activity and financial reports; whenever appropriate, intermediate targets shall be established, upon which those reports become due;
in the case of an agreement between the Commission and a number of beneficiaries, the specific obligations of the coordinator, if any, and of the other beneficiaries towards the coordinator as well as the financial responsibility of the beneficiaries for amounts due to the Commission;
(j)the arrangements and time limits for approving those reports and for payment by the Commission;
(k)as appropriate, details of the eligible costs of the action or approved work programme, or of the unit costs, lump sums or flat rates referred to in Article 123 of the Financial Regulation;
(l)provisions governing the visibility of the Union financial support, except in duly justified cases, where public display is not possible or appropriate.
The general terms and conditions referred to in point (f) of the first subparagraph shall at least:
state that Union law is the law which applies to the grant agreement, complemented, where necessary, by national law as specified in the grant agreement. Derogation may be made in the agreements concluded with international organisations;
specify the competent court or arbitration tribunal to hear disputes.
2.The grant agreement may lay down the arrangements and time limits for suspension or termination in accordance with Article 135 of the Financial Regulation.
3.In the cases referred to in Article 178, the framework partnership decision or framework partnership agreement shall specify the information referred to in points (a), (b), (c)(i), (f), and (h) to (j) and (l) of the first subparagraph of paragraph 1 of this Article.
The specific grant decision or agreement shall contain the information referred to in points (a) to (e), (g) and (k) of the first subparagraph of paragraph 1 and, where necessary, point (i) of the first subparagraph of paragraph 1.
4.Grant agreements may be amended only in writing. Such amendments, including those aiming at adding or removing a beneficiary, shall not have the purpose or the effect of making such changes to agreements as would call into question the grant award decision or be contrary to the equal treatment of applicants.
5.Paragraphs 1, 2, 3 and 4 shall apply mutatis mutandis to grant decisions.
Part of the information referred to in paragraph 1 may be provided in the call for proposals or any related document, instead of the grant decision.
1.Grants in the form referred to in point (a) of Article 123(1) of the Financial Regulation shall be calculated on the basis of the eligible costs actually incurred by the beneficiary, subject to a preliminary budget estimate as submitted with the proposal and included in the grant decision or agreement.
2.Unit costs as referred to in point (b) of Article 123(1) of the Financial Regulation shall cover all or certain specific categories of eligible costs which are clearly identified in advance by reference to an amount per unit.
3.Lump sums as referred to in point (c) of Article 123(1) of the Financial Regulation shall cover in global terms all or certain specific categories of eligible costs which are clearly identified in advance.
4.Flat-rate financing as referred to in point (d) of Article 123(1) of the Financial Regulation shall cover specific categories of eligible costs which are clearly identified in advance by applying a percentage.
1.The authorisation to use lump sums, unit costs or flat-rate financing referred to in Article 124(1) of the Financial Regulation shall apply for the duration of the programme. This authorisation may be reviewed if substantial changes are needed. Data and amounts shall be assessed periodically and, where appropriate, lump sums, unit costs or flat-rate financing shall be adjusted.
In the case of an agreement between the Commission and a number of beneficiaries, the ceiling referred to in the second subparagraph of Article 124(1) of the Financial Regulation shall apply to each beneficiary.
2.The grant decision or agreement shall contain all necessary provisions in order to verify that the conditions for the payment of the grant on the basis of lump sums, unit costs or flat-rate financing have been respected.
3.Payment of the grant on the basis of lump sums, unit costs or flat-rate financing shall be without prejudice to the right of access to the beneficiaries’ statutory records for the purposes intended by the first subparagraph of paragraph 1 and Article 137(2) of the Financial Regulation.
[F14. Where an ex post control reveals that the generating event has not occurred and an undue payment has been made to the beneficiary on a grant based on lump sums, unit costs or flat- rate financing, the Commission shall be entitled to recover up to the amount of the grant.]
Textual Amendments
F1 Substituted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
1.Under the co-financing principle, the resources which are necessary to carry out the action or the work programme shall not be provided entirely by the Union contribution.
Co-financing may take the form of the beneficiary’s own resources, income generated by the action or work programme or financial or in-kind contributions from third parties.
2.In-kind contributions shall mean non-financial resources made available free of charge by third parties to the beneficiary.
Financial contributions from third parties that may be used by the beneficiary to cover other costs than those eligible under the Union grant or that are not due to the third party where they are not used at the end of the action or work programme, shall not be considered as financial contributions specifically assigned by the donors to the financing of the eligible costs within the meaning of Article 125(5) of the Financial Regulation.
Low value grants shall be considered to be those grants which are lower than or equal to EUR 60 000.
‘Technical assistance’ shall mean support and capacity-building activities necessary for the implementation of a programme or an action, in particular preparatory, management, monitoring, evaluation, audit and control activities.
VAT shall be considered as not recoverable under the applicable national VAT legislation, if according to national law it is attributable to any of the following activities:
exempt activities without right of deduction;
activities which fall outside the scope of VAT;
activities, as referred to in points (a) or (b), in respect of which VAT is not deductible but refunded by means of specific refund schemes or compensation funds not foreseen by Directive 2006/112/EC, even if that scheme or fund is established by national VAT legislation.
VAT relating to the activities listed in Article 13(2) of Directive 2006/112/EC shall be regarded as paid by a beneficiary other than a non-taxable person as defined in the first subparagraph of Article 13(1) of that Directive, regardless of whether those activities are regarded by the Member State concerned as activities engaged in by bodies governed by public law acting as public authorities.
1.An annual or multiannual work programme for grants shall be prepared by each authorising officer responsible. The work programme shall be adopted by the institution and published on the grants internet site of the institution concerned as soon as possible, and no later than 31 March of the year of implementation.
The work programme shall specify the period it covers, the basic act, if any, the objectives pursued, the expected results, the indicative timetable of calls for proposals with the indicative amount and the maximum rate of co-financing.
The work programme shall in addition contain the information set out in Article 94 for the decision adopting it to be considered as the financing decision for the grants of the year concerned.
2.Any substantial change in the work programme shall also be adopted and published as provided for in paragraph 1.
1.Calls for proposals shall specify:
(a)the objectives pursued;
(b)the eligibility, exclusion, selection and award criteria as referred to in Articles 131 and 132 of the Financial Regulation and the relevant supporting documents;
(c)the arrangements for Union financing;
(d)the arrangements and final date for the submission of proposals and the planned date by which all applicants are to be informed of the outcome of the evaluation of their application and the indicative date for the signature of grant agreements or notification of grant decisions.
2.Calls for proposals shall be published on the internet site of the Union institutions and in addition to publication on the internet site by any other appropriate means, including the Official Journal of the European Union, where it is necessary to provide additional publicity among potential beneficiaries. They may be published as from the adoption of the financing decision referred to in Article 84 of the Financial Regulation, including during the year preceding budget implementation. Any modification of the content of the calls for proposals shall be subject to publication under the same conditions as those for the calls for proposals.
1.Grants may be awarded without a call for proposals only in the following cases:
(a)for the purposes of humanitarian aid and civil protection operations or for crisis management aid within the meaning of paragraph 2;
(b)in other exceptional and duly substantiated emergencies;
(c)to bodies with a de jure or de facto monopoly, duly substantiated in the award decision;
(d)to bodies identified by a basic act, within the meaning of Article 54 of the Financial Regulation, as beneficiaries of a grant or to bodies designated by the Member States, under their responsibility, where those Member States are identified by a basic act as beneficiaries of a grant;
(e)in the case of research and technological development, to bodies identified in the work programme referred to in Article 128 of the Financial Regulation, where the basic act expressly provides for that possibility, and on condition that the project does not fall under the scope of a call for proposals;
(f)for actions with specific characteristics that require a particular type of body on account of its technical competence, its high degree of specialisation or its administrative power, on condition that the actions concerned do not fall within the scope of a call for proposals.
The cases referred to in point (f) of the first subparagraph shall be duly substantiated in the award decision.
2.Crisis situations in third countries shall be understood as situations of immediate or imminent danger threatening to escalate into armed conflict or to destabilise the country. Crisis situations shall also be understood as situations caused by natural disasters, manmade crisis such as wars and other conflicts or extraordinary circumstances having comparable effects related inter alia to climate change, environmental degradation, privation of access to energy and natural resources or extreme poverty.
1.Information relating to grants awarded in the course of a financial year shall be published in accordance with Article 21.
2.Following the publication referred to in paragraph 1, when requested by the European Parliament and the Council, the Commission shall forward them a report on:
(a)the number of applicants in the past year;
(b)the number and percentage of successful applications per call for proposals;
(c)the mean duration of the procedure from date of closure of the call for proposals to the award of a grant;
(d)the number and amount of grants where the ex post publication obligation was waived in the past year in accordance with Article 21(4).
The Commission shall provide information and advice to applicants by the following means:
laying down joint standards for application forms for similar grants and monitoring the size and readability of the application forms;
supplying information to potential applicants in particular through seminars and the provision of handbooks;
maintaining permanent data for beneficiaries in the legal entity file referred to in Article 63.
An action may be financed jointly from separate budget lines by different authorising officers responsible.
Within the scope of Article 130(1) of the Financial Regulation, the expenditure incurred by a beneficiary before the date of submission of the application shall be eligible for Union financing under the following conditions:
the reasons for such derogation have been properly substantiated in the financing decision;
the financing decision and the grant agreement or decision set explicitly the eligibility date earlier than the date for submission of applications.
1.The arrangements for the submission of grant applications shall be determined by the authorising officer responsible, who may choose the method of submission. Grant applications may be submitted by letter or by electronic means.
The means of communication chosen shall be non-discriminatory in nature and shall not have the effect of restricting the access of applicants to the award procedure.
The means of communication chosen shall be such as to ensure that the following conditions are satisfied:
(a)each submission contains all the information required for its evaluation;
(b)the integrity of data must be preserved;
(c)the confidentiality of proposals must be preserved;
(d)the protection of personal data in accordance with the requirements of Regulation (EC) No 45/2001 is ensured.
For the purposes of point (c) of the third subparagraph, the authorising officer responsible shall examine the content of applications only after the time limit set for submitting them has expired.
The authorising officer responsible may require that electronic submission be accompanied by an advanced electronic signature within the meaning of Directive 1999/93/EC of the European Parliament and of the Council(12).
2.Where the authorising officer responsible authorises submission of applications by electronic means, the tools used and their technical characteristics shall be non-discriminatory in nature, generally available and interoperable with the information and communication technology products in general use. The information relating to the specifications required for presentation of applications, including encryption shall be made available to the applicants.
Moreover, the devices for the electronic receipt of applications shall guarantee security and confidentiality. They shall also guarantee that the exact time and date of receipt of applications can be determined precisely.
3.Where submission is by letter, applicants may choose to submit applications in one of the following ways:
(a)by post or by courier service, in which case the call for proposals shall specify that the evidence shall be constituted by the date of dispatch, the postmark or the date of the deposit slip;
(b)by hand-delivery to the premises of the institution by the applicant in person or by an agent, in which case the call for proposals shall specify the department to which applications are to be delivered against a signed and dated receipt.
1.Applications shall be made on the form established in accordance with the joint standards laid down pursuant to Article 192(a) and made available by the authorising officers responsible, and in accordance with the criteria laid down in the basic act and the call for proposals.
The supporting documents referred to in the second subparagraph of Article 131(3) of the Financial Regulation may consist in particular in the profit and loss account and the balance sheet for the last financial year for which the accounts were closed.
2.The estimated budget for the action or work programme attached to the application shall have revenue and expenditure in balance, subject to provisions for contingencies or possible variations in exchange rates which may be authorised in duly justified cases, and shall indicate the estimated eligible costs of the action or work programme.
3.Where the application concerns grants for an action for which the amount exceeds EUR 750 000 or operating grants which exceed EUR 100 000, an audit report produced by an approved external auditor shall be submitted. That report shall certify the accounts for the last financial year available.
The first subparagraph of this paragraph shall apply only to the first application made by a beneficiary to an authorising officer responsible in any one financial year.
In the case of agreements between the Commission and a number of beneficiaries, the thresholds set in the first subparagraph shall apply to each beneficiary.
In case of partnerships referred to in Article 178, the audit report referred to in the first subparagraph of this paragraph, covering the last two financial years available must be produced before signature of the framework partnership agreement or notification of the framework partnership decision.
The authorising officer responsible may, depending on a risk assessment, waive the obligation of audit report referred to in the first subparagraph for education and training establishments and, in case of agreements with a number of beneficiaries, beneficiaries who have accepted joint and several liabilities or who do not bear any financial responsibility.
The first subparagraph of this paragraph shall not apply to public bodies and the international organisations referred to in Article 43.
4.The applicant shall indicate the sources and amounts of Union funding received or applied for the same action or part of the action or for its functioning during the same financial year as well as any other funding received or applied for the same action.
The authorising officer responsible may, depending on a risk assessment, request that successful applicants provide the evidence referred to in Article 141(3) and subject to Article 141(4).
Where requested by the authorising officer responsible, successful applicants shall supply the evidence referred to in Article 141(3), subject to Article 141(4), unless there is a material impossibility recognised by the authorising officer responsible.]
Textual Amendments
F1 Substituted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
When an application for a grant is submitted by an applicant which does not have legal personality, in accordance with Article 131(2) of the Financial Regulation, the representatives of that applicant shall prove that they have the capacity to undertake legal obligations on behalf of the applicant and that the applicant has financial and operational capacity equivalent to that of legal persons.
Where several entities satisfy the criteria for applying for a grant and together form one entity, that entity may be treated by the authorising officer responsible as the sole applicant, provided that the application identifies the entities involved in the proposed action or work programme as part of the applicant.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
F3 Deleted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
1.The eligibility criteria shall be published in the call for proposals.
2.The eligibility criteria shall determine the conditions for participating in a call for proposals. Those criteria shall be established with due regard for the objectives of the action and shall comply with the principles of transparency and non-discrimination.
1.The selection criteria shall be published in the call for proposals and shall be such as to make it possible to assess the applicant’s financial and operational capacity to complete the proposed action or work programme.
2.The applicant must have stable and sufficient sources of funding to maintain his activity throughout the period during which the action is being carried out or the year for which the grant is awarded and to participate in its funding. The applicant must have the professional competencies and qualifications required to complete the proposed action or work programme unless specifically provided otherwise in the basic act.
3.Financial and operational capacity shall be verified in particular on the basis of an analysis of any of the supporting documents referred to in Article 196 and requested by the authorising officer responsible in the call for proposals.
If no supporting documents were requested in the call for proposals and if the authorising officer responsible has doubts about the financial or operational capacity of applicants, he shall request them to provide any appropriate documents.
In the case of the partnerships referred to in Article 178, that verification shall be performed before signature of the framework partnership agreement or notification of the framework partnership decision.
1.The award criteria shall be published in the call for proposals.
2.The award criteria shall be such as to enable grants to be awarded either to the actions which maximise the overall effectiveness of the Union programme which they implement or to the bodies whose work programme is designed to attain the same result. Those criteria shall be defined in such a way as to ensure also that the Union funds are properly managed.
The award criteria shall be applied in such a way as to enable the selection of planned actions or work programmes which the Commission can be confident will comply with its objectives and priorities and guarantee the visibility of the Union financing.
3.The award criteria shall be defined in such a way that it will be possible subsequently to carry out an evaluation.
1.The authorising officer responsible shall appoint a committee to evaluate the proposals, unless the Commission decides otherwise in the framework of a specific sectorial programme.
The committee shall be made up of at least three persons representing at least two organisational entities of the institutions or bodies referred to in Articles 62 and 208 of the Financial Regulation with no hierarchical link between them. To avoid any conflict of interests, those persons shall be subject to the obligations laid down in Article 57 of the Financial Regulation.
In the representations and local units referred to in Article 72 of this Regulation and the delegated bodies referred to in Articles 62 and 208 of the Financial Regulation, if there are no separate entities, the requirement of organisational entities with no hierarchical link between them shall not apply.
Outside experts may assist the committee by decision of the authorising officer responsible. The authorising officer responsible shall ensure that these experts satisfy the obligations laid down in Article 57 of the Financial Regulation.
2.The authorising officer responsible shall, where appropriate, divide the process into several procedural stages. The rules governing the process shall be announced in the call for proposals.
Where a call for proposals specifies a two-stage submission procedure, only those applicants whose proposals satisfy the evaluation criteria for the first stage shall be requested to submit a complete proposal in the second stage.
Where a call for proposals specifies a two-stage evaluation procedure, only those proposals that pass the first stage, based on the evaluation against a limited set of criteria, shall go forward for further evaluation.
The applicants whose proposals are rejected at any stage shall be informed in accordance with Article 133(3) of the Financial Regulation.
Each subsequent stage of the procedure must be clearly distinct from the previous one.
The same documents and information shall not be required to be provided more than once during the same procedure.
3.The evaluation committee or, where appropriate, the authorising officer responsible may ask an applicant to provide additional information or to clarify the supporting documents submitted in connection with the application, provided that such information or clarification does not substantially change the proposal. In accordance with Article 96 of the Financial Regulation, in the case of obvious clerical errors, the evaluation committee or the authorising officer may refrain from doing so only in duly justified cases. The authorising officer shall keep appropriate records of contacts with applicants during the procedure.
4.Upon completion of its work, the members of the evaluation committee shall sign a record of all the proposals examined, containing an assessment of their quality and identifying those which may receive funding. Those records may be signed in an electronic system providing sufficient authentication of the signatory.
Where necessary that record shall rank the proposals examined, provide recommendations on the maximum amount to award and possible non-substantial adjustments to the grant application.
The record shall be kept for future reference.
5.The authorising officer responsible may invite an applicant to adjust its proposal in the light of the recommendations of the evaluation committee. The authorising officer responsible shall keep appropriate records of contacts with applicants during the procedure.
The authorising officer responsible shall, after evaluation, take his decision giving at least:
(a)the subject and the overall amount of the decision;
(b)the name of the successful applicants, the title of the actions, the amounts accepted and the reasons for that choice, including where it is inconsistent with the opinion of the evaluation committee;
(c)the names of any applicants rejected and the reasons for that rejection.
6.Paragraphs 1, 2 and 4 of this Article are not compulsory for the award of grants pursuant to Article 190 of this Regulation and to Article 125(7) of the Financial Regulation.
Rejected applicants shall be informed as soon as possible of the outcome of the evaluation of their application and in any case within 15 calendar days after information has been sent to the successful applicants.
1.In order to limit the financial risks connected with the payment of pre-financing, the authorising officer responsible may, on the basis of a risk assessment require the beneficiary to lodge a guarantee in advance, for up to the same amount as the pre-financing, except for low value grants, or split the payment into several instalments.
2.Whenever a guarantee is required, it is subject to the assessment and acceptance of the authorising officer responsible.
The guarantee shall be valid for a period sufficiently long to allow it to be activated.
3.The guarantee shall be provided by an approved bank or financial institution established in one of the Member States. When the beneficiary is established in a third country, the authorising officer responsible may agree that a bank or financial institution established in that third country may provide the guarantee if he considers that the bank or financial institution offers equivalent security and characteristics as those offered by a bank or financial institution established in a Member State.
At the request of the beneficiary, the guarantee referred to in the first subparagraph may be replaced by a joint and several guarantee by a third party or by the irrevocable and unconditional joint guarantee of the beneficiaries of an action who are parties to the same grant agreement or decision, after acceptance by the authorising officer responsible.
The guarantee shall be denominated in euro.
It shall have the effect of making the bank or financial institution, third party or the other beneficiaries stand as irrevocable collateral security, or first-call guarantor of the grant beneficiary’s obligations.
4.The guarantee shall be released as the pre-financing is gradually cleared against interim payments or payment of the balance to the beneficiary in accordance with the conditions laid down in the grant agreement or decision.
1.For each grant, pre-financing may be split into several instalments in accordance with sound financial management.
The payment in full of the new pre-financing payment shall be subject to the consumption of at least 70 % of the total amount of any earlier pre-financing.
Where the consumption of the previous pre-financing is less than 70 %, the amount of the new pre-financing payment shall be reduced by the unused amounts of the previous pre-financing.
The statement of the beneficiary’s outlay shall be produced in support of any request for a new payment.
2.The beneficiary shall, without prejudice to Article 110, certify on his honour that information contained in payment requests is full, reliable and true. He shall also certify that the costs incurred can be considered eligible in accordance with the grant agreement or decision and that payment requests are substantiated by adequate supporting documents that can be checked.
3.A certificate on the financial statements of the action or the work programme and underlying accounts, produced by an approved external auditor or in case of public bodies, by a competent and independent public officer, may be demanded by the authorising officer responsible in support of any payment, on the basis of a risk assessment. The certificate shall be attached to the payment request. The certificate shall certify, in accordance with a methodology approved by the authorising officer responsible and on the basis of agreed-upon procedures compliant with international standards, that the costs declared by the beneficiary in the financial statements on which the payment request is based are real, accurately recorded and eligible in accordance with the grant agreement or decision.
In specific and duly justified cases, the authorising officer responsible may request the certificate in the form of an opinion or other format in accordance with international standards.
The certificate on the financial statements and underlying accounts shall be compulsory for interim payments and for payments of balances in the following cases:
(a)grants for an action for which the amount awarded in the form referred to in Article 123(1)(a) of the Financial Regulation is EUR 750 000 or more, when the cumulative amounts of payment requests under that form is at least EUR 325 000;
(b)operating grants for which the amount awarded in the form referred to in Article 123(1)(a) of the Financial Regulation is EUR 100 000 or more.
Depending on a risk assessment, the authorising officer responsible may also waive the obligation to provide such certificate on the financial statements and underlying accounts in the case of:
(a)public bodies and the international organisations referred to in Article 43;
(b)the beneficiaries of grants in connection with humanitarian aid, civil protection emergency operations and the management of crisis situations, save in respect of payments of balances;
(c)for payments of balances, beneficiaries of grants in connection with humanitarian aid who have signed a framework partnership agreement or have been notified a framework partnership decision, as referred to in Article 178, and who have in place a system of control offering equivalent guarantees for such payments;
(d)beneficiaries of multiple grants who have provided independent certification offering equivalent guarantees on the control systems and methodology used to prepare their claims.
The authorising officer responsible may also waive the obligation to provide a certificate on the financial statements and underlying accounts where an audit has been or will be directly done by the Commission’s own staff or by a body authorised to do so on its behalf, which provides equivalent assurances about the costs declared.
In the case of an agreement between the Commission and a number of beneficiaries, the thresholds referred to in points (a) and (b) of the third subparagraph shall apply to each beneficiary.
4.An operational verification report, produced by an independent third party approved by the authorising officer responsible, may be requested by the authorising officer responsible in support of any payment, on the basis of a risk assessment. Where requested by the authorising officer responsible, the verification report shall be attached to the payment request and the corresponding costs are eligible under the same conditions as the costs relating to audit certificates as laid down in Article 126 of the Financial Regulation. The verification report shall state that the operational verification was done in accordance with a methodology approved by the authorising officer responsible and whether the action or work programme was actually implemented in accordance with the conditions set out in the grant agreement or grant decision.
1.The implementation of the grant agreement or decision, the participation of a beneficiary in its implementation or payments may be suspended in order to verify whether presumed substantial errors or irregularities or fraud or breach of obligations have actually occurred. If they are not confirmed, implementation shall resume as soon as possible.
2.Where the agreed action or work programme is not carried out or is not carried out properly, in full or on time, the authorising officer responsible shall, provided that the beneficiary has been given the opportunity to make observations, either reduce or recover the grant in proportion, depending on the stage of the procedure.
1.Without prejudice to the application of the Directive 2004/18/EC, where implementation of the action or work programme requires the award of a procurement contract, the beneficiary shall award the contract to the tender offering best value for money or, as appropriate, to the tender offering the lowest price, while avoiding any conflict of interests.
2.Where implementation of the actions or work programme requires the award of a procurement contract with a value of more than EUR 60 000, the authorising officer responsible may require the beneficiary to abide by special rules in addition to those referred to in paragraph 1.
Those special rules shall be based on rules contained in the Financial Regulation and determined with due regard for the value of the contracts concerned, the relative size of the Union contribution in relation to the total cost of the action and the risk. Such special rules shall be included in the grant decision or agreement.
Provided the objectives or results to be obtained are sufficiently detailed in the conditions referred to in Article 137(1) of the Financial Regulation, the margin of discretion may only be considered to be exhausted if the grant decision or agreement also specifies the following:
the maximum amount of financial support that can be paid to a third party which shall not exceed EUR 60 000, save where the financial support is the primary aim of the action, and the criteria for determining the exact amount;
the different types of activity that may receive such financial support, on the basis of a fixed list;
the definition of the persons or categories of persons which may receive such financial support and the criteria to give it.
1.An annual or multiannual work programme for prizes shall be prepared by each authorising officer responsible. The work programme shall be adopted by the institution and published on the internet site of the institution concerned as soon as possible, and no later than 31 March of the year of implementation.
The work programme shall specify the period it covers, the basic act, if any, the objectives pursued, the expected results, the indicative timetable of contests with the indicative amount of the prizes.
The work programme shall in addition contain the information set out in Article 94 for the decision adopting it to be considered as the financing decision for the prizes of the year concerned.
2.Any substantial change in the work programme shall also be adopted and published as provided for in paragraph 1.
[F11. Rules of contests shall lay down the following:
(a) the conditions for participation, which shall at least:
specify the eligibility criteria;
specify the arrangements and final date for the registration of participants, if required, and for the submission of entries, under the conditions set out in paragraph 2;
provide for exclusion of participants which are in one of the situations referred to in Article 106(1) and Article 107 of the Financial Regulation;
provide for the sole liability of participants in case of claim relating to the activities carried out in the framework of the contest;
provide for acceptance by the winners of checks and audits by the Commission, OLAF and the Court of Auditors and of the publicity obligations as specified in the rules of the contest;
state that Union law is the law which applies to the contest, complemented, where necessary, by national law as specified in the rules of contest;
specify the competent court or arbitration tribunal to hear disputes;
state that financial penalties and exclusion decisions may be imposed on participants under Article 106 of the Financial Regulation;
(b) the award criteria, which shall be such as to make possible to assess the quality of the entries with regard to the objectives pursued and the expected results and to determine objectively whether entries qualify as the winners;
(c) the amount of the prize or prizes;
(d) the arrangements for the payment of prizes to the winners after their award.
For the purposes of point (i) of point (a) of the first subparagraph, beneficiaries of Union grants shall be eligible, unless stated otherwise in the rules of contest.
For the purposes of point (vi) of point (a) of the first subparagraph, derogation may be made in the case of participation of international organisations.]
2.The authorising officer responsible shall choose means of communication which are non-discriminatory in nature for the submission of entries and which have no effect of restricting the access of participants to the contest.
The means of communication chosen shall be such as to ensure that the following conditions are satisfied:
(a)each entry contains all the information required for its evaluation;
(b)the integrity of data is preserved;
(c)the confidentiality of entries is preserved;
(d)the protection of personal data in accordance with the requirements of Regulation (EC) No 45/2001 is ensured.
3.Rules of contests may set the conditions for cancelling the contest, in particular where its objectives cannot be fulfilled or where a legal or natural person who does not comply with the conditions for participation would qualify as the winner.
4.Rules of contests shall be published on the internet site of the Union institutions. In addition to the publication on the internet site, rules of contests may also be published by any other appropriate means, including the Official Journal of the European Union, where it is necessary to provide additional publicity among potential participants. They may be published as from the adoption of the financing decision referred to in Article 84 of the Financial Regulation, including during the year preceding budget implementation. Any modification of the content of the rules of contests shall be also subject to publication under the same conditions.
Textual Amendments
F1 Substituted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
1.Information relating to prizes awarded in the course of a financial year shall be published in accordance with Article 21.
2.Following the publication referred to in paragraph 1, when requested by the European Parliament and the Council the Commission shall forward them a report on:
(a)the number of participants in the past year;
(b)the number of participants and the percentage of successful entries per contest;
(c)a list of the experts having taken part in panels in the past year, together with a reference to the procedure for their selection.
1.For the purpose of evaluating the entries, the authorising officer responsible shall appoint a panel of at least three experts, who may be outside experts or persons representing at least two organisational entities of the institutions or bodies referred to in Articles 62 and 208 of the Financial Regulation with no hierarchical link between them, except in the representations or local bodies referred to in Article 72 of this Regulation and the delegated bodies referred to in article 62 and 208 of the Financial Regulation, if there are no separate entities.
The experts referred to in the first subparagraph shall be subject to the requirements on conflict of interests laid down in Article 57 of the Financial Regulation.
Outside experts shall declare that they are not in a situation of conflict of interests at the time of appointment and that they undertake to inform the authorising officer if any conflict of interests should arise in the course of the evaluation procedure.
2.Upon completion of their work, the members of the panel shall sign a record of all the entries examined, containing an assessment of their quality and identifying those to which the prizes may be awarded. That record may be signed in an electronic system providing sufficient authentication of the signatory.
The record referred to in the first subparagraph shall be kept for future reference.
3.The authorising officer responsible shall then decide whether or not to award the prizes. That decision shall also specify the following:
(a)the subject and total amount of prizes awarded, if any;
(b)the names of the winning participants, if any, the amount of the prizes awarded to each wining participant and the reasons for that choice;
(c)the names of any participant rejected and the reasons for that rejection.
1.Participants shall be informed as soon as possible of the outcome of the evaluation of their entry and in any case within 15 calendar days after the award decision has been taken by the authorising officer.
2.The decision to award the prize shall be notified to the winning participant and shall serve as the legal commitment within the meaning of Article 86 of the Financial Regulation.
1.For the implementation of financial instruments under indirect management, the Commission shall obtain evidence that the entrusted entity fulfils the requirements of Article 60(2) of the Financial Regulation. Once that evidence is obtained, it shall be valid for any future implementation of financial instruments by the relevant entity, unless substantial changes to the entrusted entities’ systems, rules and procedures covered by those requirements have been made.
2.For the selection of entities entrusted with the implementation of financial instruments pursuant to Article 61(2) of the Financial Regulation, the Commission shall publish a call to potential entrusted entities. That call shall include the selection and award criteria.
The call referred to in the first subparagraph shall also indicate whether the entrusted entity is required to allocate its own financial resources to the specific financial instrument or share the risk. Where such indication is made and where it is necessary to mitigate a possible conflict of interest, the call shall also indicate that the entrusted entity is required to propose measures on alignment of interest, as set out in Article 140(2) of the Financial Regulation. The measures on alignment of interest shall be included in the agreement of the specific financial instrument.
The Commission shall open a dialogue with the entities that satisfy the selection criteria in a transparent and objective manner and without giving rise to a conflict of interest. After the dialogue the Commission shall sign delegation agreements with the entity or entities that have submitted the best value for money proposals including, where applicable, the allocation of their own financial resources or risk-sharing.
3.The Commission may enter into direct negotiations with potential entrusted entities before signing delegation agreements where the entrusted entity is identified in the relevant basic act or listed in Article 58(1)(c)(iii) of the Financial Regulation, or in duly justified and properly documented exceptional cases, in particular where:
(a)no suitable proposals were submitted following a call to potential entrusted entities;
(b)financial instruments with specific characteristics require a particular type of entrusted entity on account of its technical competence, its high degree of specialisation or its administrative power;
(c)for reasons of extreme urgency brought about by unforeseeable events not attributable to the Union, it is impossible to comply with the procedure referred to in paragraph 2.
In addition to the requirements listed in Article 40, delegation agreement with entities entrusted with the implementation of financial instruments shall include appropriate arrangements for ensuring compliance with the principles and conditions set out in Article 140 of the Financial Regulation. In particular, the delegation agreements shall contain:
the description of the financial instrument, including its investment strategy or policy, the type of support provided, the criteria for eligibility for financial intermediaries and final recipients as well as additional operational requirements transposing the policy objectives of the instrument;
the requirements for a target range of values for the leverage effect;
a definition of non-eligible activities and exclusion criteria;
provisions ensuring alignment of interest and addressing possible conflicts of interest;
provisions for the selection of financial intermediaries pursuant to the second subparagraph of Article 139(4) of the Financial Regulation and for the establishment of dedicated investment vehicles, if applicable;
provisions on the liability of the entrusted entity and of other entities involved in the implementation of the financial instrument;
provisions on the settlement of disputes;
provisions on the governance of the financial instrument;
provisions regarding the use and reuse of the Union contribution in compliance with Article 140(6) of the Financial Regulation;
provisions for the management of contributions from the Union and of fiduciary accounts, including counterparty risks, acceptable treasury operations, responsibilities of parties concerned, remedial actions in the event of excessive balances on fiduciary accounts, record keeping and reporting;
provisions on the remuneration of the entrusted entity, including management fee rates and on the calculation and payment of management costs and fees to the entrusted entity in accordance with Article 218;
where appropriate, provisions on a framework of conditions for the contributions from the funds referred to in Article 175 of the Financial Regulation, in particular the European Regional Development Fund, the European Social Fund, the Cohesion Fund, the European Agricultural Fund for Rural development and the Future Fisheries Fund (hereinafter ‘CSF Funds’);
provisions on the duration, possibility of extension, and termination of the financial instrument, including the conditions for early termination and, where appropriate, exit strategies;
provisions on the monitoring of the implementation of support to financial intermediaries and final recipients including reporting by the financial intermediaries;
where applicable, type and nature of any hedging operations referred to in Article 219.
1.The Commission shall remunerate the entrusted entities for the implementation of a financial instrument through performance based fees, reimbursement of exceptional expenses and, where the entrusted entity manages the treasury of the financial instrument, treasury management fees.
2.Performance based fees shall comprise administrative fees to remunerate the entrusted entity for the work carried out in the implementation of a financial instrument. Where appropriate, they may also comprise policy related incentives to promote the achievement of the policy objectives or incentivise the financial performance of the financial instrument.
1.Entities entrusted with the implementation of financial instruments may open fiduciary accounts within the meaning of Article 68(7) of the Financial Regulation, in their name and exclusively on behalf of the Commission. Those entrusted entities shall send the corresponding account statements to the Commission’s responsible service.
2.The fiduciary accounts shall maintain appropriate liquidity and the assets held on such fiduciary accounts shall be managed in accordance with the principles of sound financial management and follow appropriate prudential rules in accordance with Article 140(7) of the Financial Regulation.
3.For the implementation of financial instruments, entrusted entities shall not carry out hedging operations for speculative purposes. The type and nature of any hedging operations shall be agreed ex ante by the Commission and included in the delegation agreements referred to in Article 217.
1.In exceptional cases, financial instruments may be implemented directly pursuant to Article 139(4) of the Financial Regulation through any of the following:
(a)a dedicated investment vehicle in which the Commission participates together with other public or private investors with a view to increasing the leverage effect of the Union contribution;
(b)loans, guarantees, equity participations and other risk-sharing instruments other than investments in dedicated investment vehicles, provided directly to final recipients or through financial intermediaries.
2.For the implementation of financial instruments, the Commission shall not carry out hedging operations for speculative purposes. The type and nature of any hedging operations shall be agreed ex ante by the Commission and included in the agreements with entities implementing the financial instrument.
1.Where the Commission implements financial instruments directly or indirectly through dedicated investment vehicles, such vehicles shall be established according to the laws of a Member State. They may also be established according to the laws of a country other than a Member State in the area of external action. The managers of such vehicles shall be obliged by law or contract to act with the diligence of a professional manager and in good faith.
2.The managers of the dedicated investment vehicles referred to in paragraph 1 and financial intermediaries or final recipients of the financial instruments shall be selected with due account of the nature of the financial instrument to be implemented, the experience and the operational and financial capacity of the entities concerned, and/or the economic viability of projects of final recipients. The choice shall be transparent, justified on objective grounds and shall not give rise to a conflict of interest.
F33.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
F3 Deleted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
1.Financial instruments shall address market imperfections or failures or sub-optimal investment situations and provide support only to final recipients that are deemed potentially economically viable at the time of the Union support through a financial instrument.
2.Financial instruments shall provide support to final recipients in a proportionate manner. In particular, preferential treatment of investors providing co-investment or risk-sharing should be justified, proportionate to the risks taken by the investors in a financial instrument and limited to the minimum necessary to ensure their investment or risk-sharing.
1.Financial instruments shall aim at achieving a leverage effect of the Union contribution by mobilising a global investment exceeding the size of the Union contribution.
The leverage effect of Union funds shall be equal to amount of finance to eligible final recipients divided by the amount of the Union contribution.
2.The target range of values for the leverage effect shall be based on an ex ante evaluation for the corresponding financial instrument.
1.Financial instruments shall be based on ex ante evaluations identifying market imperfections or failures, or sub-optimal investment situations and assessing investment needs in view of the policy objectives.
2.The ex ante evaluation shall demonstrate that identified market needs cannot be addressed appropriately and in a timely manner through either market led activities or types of Union intervention other than funding by a financial instrument, such as regulation, liberalisation, reform or other policy action. It shall assess the likelihood and possible costs of market distortions and crowding-out of private funding through the financial instruments and shall identify means to minimise negative effects of such distortions.
3.In accordance with the principle of subsidiarity, the ex ante evaluation shall demonstrate that an Union-level financial instrument addresses identified market needs more appropriately than similar financial instruments at national or regional level, including those financed by CSF Funds. Factors such as difficult access to funding at national level, in particular for cross-border projects, economies of scale or strong demonstration effects linked to the diffusion of best practices to Member States shall be taken into account when assessing the added value of the Union contribution.
4.The ex ante evaluation shall determine the most efficient mode for delivering the financial instrument.
5.The ex ante evaluation shall also demonstrate that the planned financial instrument is consistent with:
(a)new and existing financial instruments, avoiding undesirable overlaps and achieving synergies and economies of scale;
(b)financial instruments and other forms of public intervention addressing the same market environment, avoiding inconsistencies and exploring potential synergies.
6.The ex ante evaluation shall assess proportionality of the envisaged intervention with regard to the size of the identified funding gap, the expected leverage effect of the planned financial instrument and also examine additional qualitative effects, such as the diffusion of best practices, the effective promotion of Union policy objectives throughout the implementation chain or the access to specific expertise available from actors involved in the implementation chain.
7.The ex ante evaluation shall establish a set of appropriate performance indicators for the proposed financial instruments and specify the expected output, results and impact.
8.A separate ex ante evaluation of financial instruments shall only be carried out where such evaluation complying in full with the criteria in paragraphs 1 to 7 is not included in the ex ante evaluation or an impact assessment of the programme or activity covered by a basic act.
1.In order to ensure the harmonised monitoring of financial instruments referred to in Article 140(12) of the Financial Regulation, a monitoring system shall be put in place by the authorising officer responsible to contribute to the provision of reasonable assurance that Union funds are used in accordance with Article 32(2) of the Financial Regulation.
2.The monitoring system shall be used to assess the progress of the implementation towards the achievement of the policy objectives reflected in the relevant output and result indicators established pursuant to the ex ante evaluation, and to analyse the compliance of the implementation with the defined requirements pursuant to Article 140(2) of the Financial Regulation and provide the basis for the Commission’s reporting required under Articles 38(5) and 140(8) of the Financial Regulation.
3.In case of indirect management, the monitoring by the Commission shall build on the reporting and accounts provided by entrusted entities and on the audits available and controls carried out by the entrusted entity, taking due account of the management declaration of the entrusted entity and the opinion of the independent audit body referred to in Article 60(5) of the Financial Regulation. The Commission shall review the information provided by the entrusted entities and may carry out controls, including on a sample basis, at the appropriate implementation levels up to final recipients.
The monitoring by the entrusted entity shall build on the reporting and accounts provided by financial intermediaries and on the audits available and controls carried out by the financial intermediary, taking due account of the management declaration of the financial intermediary and the opinion of independent auditors.
Where, no financial intermediary exists, the entrusted entity shall directly monitor the use of the financial instrument based on the reporting and accounts provided by the final recipients.
The entrusted entity shall review, where appropriate on a sample basis, the information provided by the financial intermediaries or final recipients and shall carry out controls as set out in the agreement referred to in Article 217.
4.In case of direct management, the monitoring by the Commission shall build on the reporting and accounts provided by financial intermediaries and final recipients, subject to appropriate controls. The provisions under paragraph 3 shall apply to direct management mutatis mutandis.
5.The agreements implementing the financial instrument shall contain the provisions necessary for the application of paragraphs 1 to 4.
1.Separate records shall be kept for contributions from CSF Funds to financial instruments established under Title VIII of the Financial Regulation and supported by CSF Funds pursuant to the sector specific rules.
2.Contributions from the CSF Funds shall be placed in separate accounts and used in accordance with the objectives of the respective CSF Funds to actions and final recipients consistent with the programme or programmes from which contributions are made.
3.As regards contributions from CSF Funds to financial instruments established under Title VIII of the Financial Regulation, the sector specific rules shall apply.
The report on budgetary and financial management during the year shall give an accurate description of:
the achievement of the objectives for the year, in accordance with the principle of sound financial management;
the financial situation and the events which have had a significant influence on activities during the year.
The report on budgetary and financial management shall be separate from the reports on implementation of the budget.
Where, in a specific case, the accounting officers consider that an exception should be made to the content of one of the accounting principles outlined in the Union accounting rules, that exception shall be duly substantiated and reported in the notes to the financial statements referred to in Article 232.
1.Each entry shall be based on dated and numbered supporting documents, produced on paper or on a medium which guarantees the reliability and safeguarding of its content for the periods laid down in Article 48.
2.Operations of the same type, carried out in the same place and on the same day may be summarised in a single supporting document.
The statement of financial performance shall show the income and charges for the year, classified according to their nature.
The cash flow statement shall report cash flows during the period showing the movement between opening and closing treasury amounts.
The treasury shall be made up of the following:
cash in hand;
bank accounts and deposits payable on demand;
other disposable assets which can quickly be converted to cash and whose value is stable.
The notes referred to in article 145 of the Financial Regulation shall form an integral part of the financial statements. The notes shall contain at least the following information:
accounting principles, rules and methods;
explanatory notes, supplying additional information not contained in the body of the financial statements which is necessary for a true and fair view.
1.The budgetary outturn accounts shall contain:
(a)information on revenue comprising:
changes in the revenue estimates in the budget;
the revenue outturn;
entitlements established;
(b)information showing changes in the total commitment and payment appropriations available;
(c)information showing the use made of the total commitment and payment appropriations available;
(d)information showing commitments outstanding, those carried over from the previous year and those made during the year.
2.As regards information on revenue, a statement shall also be attached showing, for each Member State, the breakdown of amounts of own resources still to be recovered at the end of the financial year and covered by a recovery order.
Provisional accounts and the final accounts referred to in Articles 147 and 148 of the Financial Regulation may be sent by electronic means.
1.The accounting officer of each institution and body referred to in Article 141 of the Financial Regulation shall draw up and keep updated documents describing the organisation of the accounts and accounting procedures of his institution and body.
2.Budget revenue and expenditure shall be recorded in the computerised system referred to in Article 236, according to the economic nature of the operation, as current revenue or expenditure or as capital.
1.The accounts shall be kept with the help of an integrated computerised system.
2.Where accounts are kept using computerised systems and subsystems, such systems and subsystems shall be described in full.
That description shall define the content of all data fields and specify how the system treats individual operations. It shall state how the system guarantees the existence of a complete audit trail for each operation and for any change made to the computerised systems and subsystems so that it is possible at any time to identify the nature of the change and the person who made it.
The description of computerised accounting systems and subsystems shall indicate any links between those systems and the central accounting system, particularly as regards the transfer of data and the reconciliation of balances.
3.Access to the computerised systems and subsystems shall be confined to persons included on a list of authorised users which is kept and updated by each institution.
Each institution and each body referred to in Article 141 of the Financial Regulation shall keep a journal, a general ledger and at least sub-ledgers for debtors, creditors and fixed assets, unless it is not justified by cost-benefit considerations.
The accounting ledgers shall consist of electronic documents which are identified by the accounting officer and offer full guarantees for use as evidence.
Entries in the journal shall be transferred to the general ledger, itemised according to the chart of accounts referred to in Article 212.
The journal and the general ledger may be split into as many special journals and special ledgers are necessary to meet requirements.
Entries recorded in special journals and special ledgers shall be centralised at least every month in the journal and in the general ledger.
Each institution and body referred to in Article 141 of the Financial Regulation shall establish a trial balance covering all the accounts of the general accounts, including the accounts cleared during the year, with, in each case:
account number;
description;
total debits;
total credits;
balance.
1.The data in the general ledger shall be kept and organised in such a way as to justify the content of each of the accounts included in the trial balance.
2.As regards the inventory of fixed assets, the provisions of Articles 246 to 253 shall apply.
1.Entries shall be made using the double entry method, whereby any movement or variation recorded in the accounts shall be represented by an entry establishing an equivalence between the amount debited and the amount credited in the various accounts affected by that entry.
2.The euro counterpart of a transaction denominated in a currency other than the euro shall be calculated and entered in the accounts.
Transactions in foreign currencies in accounts which can be revalued shall be revalued at least each time the accounts are closed.
That revaluation shall be based on the rates laid down in accordance with Article 6.
The rate to be used for conversion between the euro and another currency to draw up the balance sheet at 31 December of year N shall be that of the last working day of year N.
3.The Union accounting rules adopted under Article 152 of the Financial Regulation shall specify the conversion and re-evaluation rules to be provided for the purposes of accrual accounting.
All accounting records shall specify the origin, content and booking reference of each data item and the references of the relevant supporting documents.
Accounting operations shall be recorded in the journal by one of the following methods, which are not mutually exclusive:
day by day, operation by operation;
in the form of a monthly summary of the total amounts involved in operations, provided that all documents allowing verification of individual operations day by day are kept.
1.Entries in the journal and in sub-ledgers shall be made final by means of a validation procedure prohibiting any change to or deletion of the entry.
2.A closure procedure designed to freeze the chronology of records and guarantee their inviolability shall be implemented at the latest before the final financial statements are presented.
1.The balance of accounts in the trial balance shall be reconciled periodically and at least at the annual closure, with the data from the management systems used by authorising officers for the management of assets and liabilities and for the daily input into the accounting system.
2.Periodically, and at least whenever the accounts are closed, the accounting officer shall check that the bank balances correspond to the actual situation, in particular as regards:
(a)cash at bank, by reconciliation of the statements of account from financial institutions;
(b)cash in cash offices, by reconciliation with the data in the cash book.
The fixed assets accounts shall be reviewed in accordance with Article 250.
3.The interinstitutional liaison accounts shall be reconciled monthly.
4.The suspense accounts shall be opened and reviewed annually by the accounting officer. Those accounts shall be under the responsibility of the authorising officer and he shall clear them as soon as possible.
1.The budget accounts shall show, for each subdivision of the budget:
(a)in the case of expenditure:
the appropriations authorised in the initial budget, the appropriations entered in amending budgets, the appropriations carried over, the appropriations available following collection of assigned revenue, transfers of appropriations and the total appropriations thus available;
the commitments and payments in respect of the financial year;
(b)in the case of revenue:
the estimates entered in the initial budget, the estimates entered in amending budgets, assigned revenue and the total amount of estimates thus determined;
the entitlements established and the amounts recovered in respect of the financial year in question;
(c)the commitments still to be paid and revenue still to be recovered carried forward from previous financial years.
The commitment appropriations and payment appropriations referred to in point (a) of the first subparagraph shall be entered and shown separately.
The global provisional commitments relating to the European Agricultural Guarantee Fund (hereinafter ‘EAGF’) and the corresponding payments shall also be recorded in the budget accounts.
Those commitments shall be presented in respect of total EAGF appropriations.
2.The budget accounts shall show separately:
(a)the use of appropriations carried over and the appropriations for the year;
(b)the clearance of outstanding commitments.
On the revenue side, amounts still to be recovered from previous financial years shall be shown separately.
3.The budget accounts may be organised in such a way as to develop a cost accounting system.
4.The budget accounts shall be kept using computer systems, in books or on file cards.
The system of property inventories shall be established by the authorising officer with technical assistance from the accounting officer. That inventory system must supply all the information required for keeping the accounts and safeguarding assets.
Each of the institutions and bodies referred to in Article 141 of the Financial Regulation shall adopt provisions on safeguarding the assets included in their respective balance sheets and decide which administrative departments are responsible for the inventory system.
All items acquired with a period of use greater than one year, which are not consumables, and whose purchase price or production cost is higher than that indicated in the Union accounting rules adopted under Article 152 of the Financial Regulation shall be entered in the inventory and recorded in the fixed assets accounts.
The inventory shall contain an appropriate description of each item and specify its location, or for movable items, the service or person responsible, the date of acquisition and its unit cost.
Inventory checks carried out by the institutions and bodies referred to in Article 141 of the Financial Regulation shall be performed in such a way as to ensure that each item physically exists and matches the relevant entry in the inventory. Such checks shall be carried out under an annual verification programme, save for fixed tangible assets and intangible assets, which shall be checked at least on a three-year basis.
Members, officials or other servants and any other staff of the institutions and bodies referred to in Article 141 of the Financial Regulation may not acquire items that are resold by these institutions and bodies, save where those items are resold by public tender procedure.
1.Sales of tangible assets shall be advertised locally in appropriate manner, if the unit purchase value is EUR 8 100 or more. The period between publication of the last announcement and conclusion of the sales contract shall be no less than 14 calendar days.
The sales referred to in the first subparagraph shall be the subject of a notice of sale published in the Official Journal of the European Union, if the unit purchase value is EUR 391 100 or more. Appropriate advertising may also be placed in the Member States’ press. The period between the date of publication of the notice in the Official Journal of the European Union and conclusion of the sales contract shall be no less than one month.
2.The institutions and bodies referred to in Article 141 of the Financial Regulation may forgo advertising where the cost of advertising exceeds the expected return from the operation.
3.The institutions and bodies referred to in Article 141 of the Financial Regulation shall always endeavour to obtain the best price for sales of tangible assets.
4.Paragraphs 1, 2 and 3 shall not apply to sales between Union institutions and their bodies referred to in Article 208 of the Financial Regulation.
A statement or record shall be drawn up by the authorising officer whenever any property in the inventory, including buildings, is sold, given away free of charge, scrapped, hired out or missing on account of loss, theft or any other reason.
The statement or record shall indicate in particular whether the item must be replaced at the expense of an official or other servant of the Union or any other person.
Where immovable property or major installations are made available free of charge, a contract must be drawn up and the case notified in an annual report sent to the European Parliament and the Council when the draft budget is presented.
Members, officials or other servants and any other staff of the institutions and bodies referred to in Article 141 of the Financial Regulation may not be recipients of the property in the inventory given away free of charge or scrapped.
1.In the case of the Union delegations, the permanent inventories of movable property belonging to the Union shall be kept locally. They shall be sent regularly to the central departments in accordance with the rules adopted by each institution.
Movable property in transit to the Union delegations shall be entered on a provisional list before being recorded in the permanent inventories.
2.The advertising for sales of movable property of Union delegations shall be done in accordance with local usage.
1.Direct action shall be carried out by the establishments of the Joint Research Centre (hereinafter ‘JRC’) and shall in principle be entirely financed from the budget. It shall consist of:
(a)research programmes;
(b)exploratory research activities;
(c)scientific and technical support activities of an institutional nature.
2.The JRC may participate in indirect actions under the conditions laid down in Article 183 of the Financial Regulation.
3.The estimate of amount receivable, as referred to in Article 181(2) of the Financial Regulation shall be sent to the accounting officer for registration.
1.The activities of a competitive nature conducted by the JRC shall consist of:
(a)activities carried out following grant or procurement procedures;
(b)activities on behalf of third parties;
(c)activities undertaken under an administrative agreement with other institutions or other Commission departments for the provision of technical-scientific services.
2.Where the activities conducted by the JRC for third parties involve procurement, the procurement procedure shall comply with the principles of transparency and equal treatment.
3.The estimates of amounts receivable referred to in Article 183(2) of the Financial Regulation shall be sent to the accounting officer for registration.
Appropriations for the actions referred to in Chapter 1 of Title IV of Part Two of the Financial Regulation may, in particular, finance procurement contracts, grants, including interest rate subsidies, special loans, loan guarantees and financial assistance, budgetary support and other specific forms of budgetary aid.
1.Where provided for in the relevant basic acts, the Commission may use sectoral or general budget support within a third country if the following conditions are met:
(a)the partner country’s management of public finances is sufficiently transparent, reliable and effective;
(b)the partner country has put in place sufficiently credible and relevant sectoral or national policies; and
(c)where the partner country has put in place stability oriented macroeconomic policies.
2.Agreements concluded with the partner country shall contain an obligation for that country to provide the Commission with reliable and timely information which allows the Commission to evaluate the fulfilment of the conditions set out in paragraph 1.
The contributions of other donors shall be taken into account when cashed in the specific bank account of the trust fund and for the amount in euro resulting from the conversion at their reception on the specific bank account.
The Union contribution shall be transferred in due time to cover the legal commitments of the trust fund taking due account of available funds provided by the other donors.
Interests accumulated on the trust fund’s specific bank account shall be invested in the trust fund except where otherwise provided for in the constitutive act of the trust fund.
All transactions made on the bank account referred to in the third paragraph during the year shall be properly accounted for in the accounts of the trust fund.
Financial reporting on the operations carried out by each trust fund shall be established twice every year by the authorising officer.
The trust funds shall be subject to an independent external audit every year.
The board of the trust fund shall approve the annual report of the trust fund drawn up by the authorising officer together with annual accounts drawn up by the accounting officer. Those reports shall be attached to the annual report of the authorising officer by delegation and presented to the European Parliament and Council within the discharge procedure of the Commission.
The rules for composition of the board and its internal rules shall be laid down in the constitutive act of the trust fund adopted by the Commission and adhered to by the donors. Those rules shall ensure a fair representation of the donors and include the requirement to have the positive vote of the Commission for the final decision on the use of the funds.
The only buildings contracts which may be financed from operational appropriations for external action shall be those relating to the renting of buildings already constructed at the time the lease is signed. These contracts shall be published as laid down in Article 124.
1. Service contracts shall comprise the following:
(a) a study contract that is concluded between a contractor and the contracting authority which includes studies for the identification and preparation of projects, feasibility studies, economic and market studies, technical studies and audits;
(b) a technical assistance contract, where the contractor is called on to play an advisory role, to manage or supervise a project or to provide the consultants specified in the contract.
2. Where a third country has qualified management staff in its departments or entities with public-sector participation, the contracts may be performed directly by these departments or entities by direct labour.
Articles 123 to 126, with the exception of the definitions, Article 128, point (a) of Article 134(1), points (a) and (c) to (f) of Article 135(1), Article 135(4), Articles 137 and 137a, paragraphs 3 to 7 of Article 139, Articles 148(4), 151(3), Article 152, paragraphs 2 and 3 of Article 153, Articles 154, 155, 157, 158 with the exception of Article 158(4), and Article 160 of this Regulation shall not apply to procurement contracts concluded by the contracting authorities referred to in Article 190(2) of the Financial Regulation or on their behalf.
Implementation of the procurement provisions under this Chapter shall be decided by the Commission, including the appropriate controls to be applied by the responsible authorising officer where the Commission is not the contracting authority.
The procurement documents shall require candidates or tenderers to indicate in which State they are effectively established and to present the supporting evidence normally acceptable under the law of that State.
1. If applicable, the prior information notice for international calls for tender shall be sent to the Publications Office by electronic means as early as possible.
2. For the purposes of this Chapter, the contract notice shall be published:
(a) at least in the Official Journal of the European Union for international calls for tender;
(b) at least in the official gazette of the recipient State or in any equivalent publication for local invitations to tender.
Where the contract notice is also published locally, it must be identical to the one published in the Official Journal of the European Union and it must be published simultaneously. The Commission shall be responsible for publication in the Official Journal of the European Union . If the notice is published locally, this may be done by the entities referred to in Article 190(2)(b) of the Financial Regulation.
3. The contract award notice shall be sent when the contract is signed except where, if still necessary, the contract was declared secret or where the performance of the contract must be accompanied by special security measures, or when the protection of the essential interests of the Union, or the third country so requires, and where the publication of the award notice is deemed not to be appropriate.
4. A notice for modification of contract shall be published in the Official Journal of the European Union in the cases set out in points (a) and (b) of Article 114a(3) of the Financial Regulation, where the value of the modification is equal to or greater than the thresholds laid down in Articles 265(1)(a), 267(1)(a) or 269(1)(a) of this Regulation.
1. The thresholds and procedures referred to in Article 190 of the Financial Regulation shall be as follows for service contracts and service concession contracts:
(a) for contracts with a value of EUR 300 000 or more:
an international restricted invitation to tender within the meaning of Article 104(1)(b) of the Financial Regulation and Article 264(2)(a) of this Regulation;
an international open invitation to tender within the meaning of Article 104(1)(a) of the Financial Regulation and Article 264(2)(a) of this Regulation.
(b) for contracts with a value of less than EUR 300 000 : competitive negotiated procedure within the meaning of paragraph 3 of this Article.
(c) Contracts with a value of less than or equal to EUR 20 000 may be awarded on the basis of a single tender.
(d) Payments for amounts less than or equal to EUR 2 500 in respect of item of expenditure may consist simply in payment against invoices without prior acceptance of a tender.
2. In the international restricted procedure referred to in point (a) of paragraph 1, the contract notice shall state the number of candidates who will be invited to submit tenders. For service contracts at least four candidates shall be invited. The number of candidates allowed to submit tenders must be sufficient to ensure genuine competition.
The list of selected candidates shall be published on the Commission's internet site.
If the number of candidates satisfying the selection criteria or the minimum capacity levels is less than the minimum number, the contracting authority may invite to submit a tender only those candidates who satisfy the criteria to submit a tender.
3. Under the competitive negotiated procedure referred to in point (b) of paragraph 1, the contracting authority shall draw up a list of at least three tenderers of its choice, without publication of a notice.
Tenderers for the competitive negotiated procedure may be chosen from a list of vendors as referred to in Article 136(1)(b) advertised by a call for expressions of interest.
If following consultation of the tenderers, the contracting authority receives only one tender that is administrative and technically valid, the contract may be awarded provided that the award criteria are met.
4. For legal services not covered under point (h) of Article 134(1), the contracting authorities may use the competitive negotiated procedure, regardless of the estimated value of the contract.
1. Contracting authorities may use the negotiated procedure with a single tender in the following cases:
(a) where the services are entrusted to public-sector bodies or to non-profit institutions or associations and relate to activities of an institutional nature or designed to provide assistance to peoples in the social field;
(b) where the tender procedure has been unsuccessful, that is to say, where no qualitatively and/or financially worthwhile tender has been received, in which case, after cancelling the tender procedure, the contracting authority may negotiate with one or more tenderers of its choice, from among those that took part in the invitation to tender, provided that the procurement documents are not substantially altered;
(c) where a new contract has to be concluded after early termination of an existing contract.
2. For the purposes of point (c) of Article 134(1), operations carried out in crisis situations as referred to in Article 190(2) shall be deemed to satisfy the test of extreme urgency. The authorising officer by delegation, where appropriate in concertation with the other authorising officers by delegation concerned, shall establish that a situation of extreme urgency exists and shall review his decision regularly with regard to the principle of sound financial management.
3. Activities of an institutional nature referred to in point (a) of the paragraph 1 include services directly linked to the statutory mission of the public sector bodies.
1. The thresholds and procedures referred to in Article 190 of the Financial Regulation shall be as follows for supply contracts:
(a) for contracts with a value of EUR 300 000 or more: an international open invitation to tender within the meaning of Article 104(1)(a) of the Financial Regulation and Article 264(2)(a) of this Regulation;
(b) for contracts with a value of less than EUR 300 000 :
for contracts of a value of EUR 100 000 or more but less than EUR 300 000 : local open invitation to tender within the meaning of Article 104(1)(a) of the Financial Regulation and Article 264(2)(b) of this Regulation;
for contracts with a value of less than EUR 100 000 : competitive negotiated procedure within the meaning of paragraph 2.
(c) payments for amounts less than or equal to EUR 2 500 in respect of item of expenditure may consist simply in payment against invoices without prior acceptance of a tender.
(d) Contracts with a value of less than or equal to EUR 20 000 may be awarded on the basis of a single tender.
2. Under the competitive negotiated procedure referred to in point (ii) of point (b) of paragraph 1, the contracting authority shall draw up a list of at least three suppliers of its choice, without publication of a notice.
If following the consultation of the suppliers, the contracting authority receives only one tender that is administrative and technically valid, the contract may be awarded provided that the award criteria are met.
1. The thresholds and procedures referred to in Article 190 of the Financial Regulation shall be as follows for works contracts and works concession contracts:
(a) for contracts with a value of EUR 5 000 000 or more any of the following:
an international open invitation to tender within the meaning of Article 104(1)(a) of the Financial Regulation and Article 264(2)(a) of this Regulation;
in view of the characteristics of certain works, an international restricted invitation to tender within the meaning of Article 104(1)(b) of the Financial Regulation and Article 264(2)(a) of this Regulation;
(b) for contracts with a value of EUR 300 000 or more but less than EUR 5 000 000 : a local open invitation to tender within the meaning of Article 104(1)(a) of the Financial Regulation and Article 264(2)(b) of this Regulation;
(c) for contracts with a value of less than EUR 300 000 : a competitive negotiated procedure within the meaning of paragraph 2 of this Article;
(d) Contracts with a value of less than or equal to EUR 20 000 may be awarded on the basis of a single tender.
(e) Payments for amounts less than or equal to EUR 2 500 in respect of item of expenditure may consist simply in payment against invoices without prior acceptance of a tender.
2. Under the competitive negotiated procedure referred to in point (c) of paragraph 1 of this Article, the contracting authority shall draw up a list of at least three contractors of its choice, without publication of a notice.
If following the consultation of the contractors, the contracting authority receives only one tender that is administrative and technically valid, the contract may be awarded provided that the award criteria are met.
By derogation to Article 138(3), for all procedures involving a request to participate, the tender specifications may be split according to the two stages of the procedure and the first step may contain only the information referred to in points (a) and (f) of Article 138(3).
1. By derogation from Article 163, guarantees shall be denominated in euro or in the currency of the contract they cover.
2. The contracting authority may request a tender guarantee in accordance with Article 156. By derogation from Article 156(2), the contracting authority shall release the tender guarantee when the contract is signed.
3. By derogation from Article 165(1), a performance guarantee shall be required where the following thresholds are exceeded:
(a) EUR 345 000 for works contracts,
(b) EUR 150 000 for supply contracts.
4. The contracting authority may require a retention money guarantee in accordance with Article 165a.
1. Tenders must reach the contracting authority at the address and by no later than the date and time shown in the invitation to tender. The time limit for receipt of tenders and requests to participate, laid down by the contracting authorities, shall be long enough to allow interested parties a reasonable and appropriate period to prepare and submit their tenders.
For service contracts, the minimum time between the date of dispatch of the letter of invitation to tender and the final date for receipt of tenders shall be 50 days. However, in certain exceptional cases other time limits may be authorised.
2. Tenderers may put questions in writing before the closing date for receipt of tenders. The contracting authority shall provide the answers to the questions before the closing date for receipt of tenders.
3. In international restricted procedures, the time limit for receipt of requests to participate shall be no less than 30 days from the date on which the contract notice is published. The period between the date on which the letter of invitation is sent and the final date for the receipt of tenders shall be no less than 50 days. However, in certain exceptional cases other time limits may be authorised.
4. In international open procedures, the time limits for receipt of tenders, running from the date on which the contract notice is sent, shall be at least:
(a) 90 days for works contracts;
(b) 60 days for supply contracts.
However, in certain exceptional cases other time limits may be authorised.
5. In local open procedures, the time limits for receipt of tenders, running from the date when the contract notice is published, shall be at least:
(a) 60 days for works contracts;
(b) 30 days for supply contracts.
However, in certain exceptional cases other time limits may be authorised.
6. For the competitive negotiated procedures referred to in Articles 265(1)(b), 267(1)(b)(ii) and 269(1)(c), candidates shall be allowed at least 30 days from the date of dispatch of the letter of invitation to tender in which to submit their tenders.
1. All requests to participate and tenders declared as satisfying the requirements shall be evaluated and ranked by an evaluation committee on the basis of the exclusion, selection and award criteria announced in advance. This committee shall have an odd number of members, at least three, with all the necessary technical and administrative expertise to assess the tenders. The members of the evaluation committee shall sign a declaration of impartiality and absence of conflict of interest.
2. If the Commission is not the contracting authority, it may request to receive a copy of procurement documents, tenders, the evaluation of the tenders and the signed contracts. It may also participate as an observer to the opening and evaluation of tenders.
3. Tenders which do not contain all the essential items demanded in the procurement documents or which do not correspond to the specific requirements laid down shall be eliminated.
However, the evaluation committee or the contracting authority may ask candidates or tenderers to supply additional material or to clarify the supporting documents submitted in connection with the exclusion, selection and award criteria, within the time limit they specify and having respect to the principle of equal treatment.
4. In the case of abnormally low tenders as referred to in Article 151, the committee shall ask for the necessary clarifications concerning the composition of the tender.
5. The obligation to establish an evaluation committee may be waived for procedures with a value less than or equal to EUR 20 000 and on the basis of a risk analysis when reopening competition within a framework contract and in the case of negotiated procedures referred to in points (c), (e), (f)(i), (f)(iii) and (h) of Article 134(1).]
In case of derogation from the co-financing requirement, grounds shall be provided in the award decision.
The offices referred to in Article 195 of the Financial Regulation are as follows:
the Publications Office;
the European Anti-Fraud Office;
The European Personnel Selection Office and the European Administrative School administratively attached to it;
the Office for the Administration and Payment of Individual Entitlements;
the Office for Infrastructure and Logistics in Brussels and the Office for Infrastructure and Logistics in Luxembourg.
One or more institutions may set up additional offices provided that this can be justified by a cost-benefit study and guarantees the visibility of the Union action.
Each institution shall be responsible for budgetary commitments. The institutions may delegate to the Director of the interinstitutional European office concerned all subsequent acts, in particular legal commitments, validation of expenditure, authorisation of payments and implementation of revenue, and shall set the limits and conditions for such delegation of powers.
With regard to the Publications Office, each institution shall decide on its publication policy. The net proceeds from the sale of publications shall be reused as assigned revenue by the institution which is the author of those publications, in accordance with Article 21 of the Financial Regulation.
The Commission accounting officer, acting on a proposal from the management committee of the Office in question, may delegate to a member of the staff of the Office some of his tasks relating to the collection of revenue and the payment of expenditure made directly by the Office in question.
To meet the cash requirements of an interinstitutional Office, bank accounts or post office giro accounts may be opened in its name by the Commission, acting on a proposal from the management committee. The final cash position for each year shall be reconciled and adjusted between the Office in question and the Commission at the end of the financial year.
The administrative appropriations covered by this Title shall be those set out in Article 41 of the Financial Regulation.
Budgetary commitments corresponding to administrative appropriations of a type common to several titles and which are managed globally may be recorded globally in the budgetary accounting following the summary classification by type as set out in Article 25.
The corresponding expenditure shall be booked to the budget lines of each title according to the same distribution as for appropriations.
Rent guarantees provided by the institutions shall take the form of a bank guarantee or a deposit on a blocked bank account in the name of the institution and of the lessor, denominated in euro, save in duly substantiated cases.
However, where, for transactions in third countries, it is not possible to use any of those forms of rent guarantees, the authorising officer responsible may accept other forms provided that those forms ensure equivalent protection of the Union’s financial interests.
Advances may be paid, in accordance with the conditions laid down in the Staff Regulations, to staff and to the members of the institutions.
1.The expenditure referred to in Article 203(3)(a) of the Financial Regulation shall include the costs of the fitting out of buildings. It shall not include the charges.
2.The early information procedure set out in Article 203(4) of the Financial Regulation and the prior approval procedure set out in Article 203(5) of the Financial Regulation shall not apply to acquisition of land free of charge or for a symbolic amount.
3.The early information and prior approval procedure set out in points 3 to 7 of Article 203 of the Financial Regulation shall not apply to residential buildings. The European Parliament and the Council may request from the institution in charge any information related to residential buildings.
4.In exceptional or urgent political circumstances the early information referred to in Article 203(4) of the Financial Regulation concerning building projects relating to Union delegations or offices in third countries may be submitted jointly with the building project pursuant to Article 203(5) of the Financial Regulation. In such cases, the early information and prior approval procedures shall be conducted at the earliest possible opportunity.
5.The prior approval procedure set out in paragraphs 5 and 6 of Article 203 of the Financial Regulation shall not apply to preparatory contracts or studies necessary to evaluate the detailed cost and financing of the building project.
6.The thresholds of EUR 750 000 or EUR 3 000 000 referred to in points (ii), (iii) and (iv) of Article 203(7) of the Financial Regulation shall include the costs of fitting out of the building. For rents and usufruct contracts, those thresholds shall take into account the costs of the fitting out of the building but not the other charges.
7.One year after the date of entry into application of the Financial Regulation, the Commission shall report on the application of the procedures set out in paragraphs 3 to 8 of Article 203 of the Financial Regulation.
1.For values below the thresholds laid down in Article 170(1), remunerated external experts may be selected on the basis of the procedure laid down in paragraph 2.
2.A call for expressions of interest shall be published in the Official Journal of the European Union or where it is necessary to provide publicity among potential candidates, on the internet site of the institution concerned.
The call for expressions of interest shall include a description of the tasks, their duration and the fixed conditions of remuneration. Those conditions may be based on unit prices.
A list of experts shall be drawn up following the call for expressions of interest. It shall be valid for no more than five years from its publication or for the duration of a multiannual programme related to the tasks.
[F13. Any interested natural person may submit an application at any time during the period of validity of the call for expression of interest, with the exception of the last three months of that period.]
4.All exchanges with selected experts, including the conclusion of contracts and any amendments thereto, may be done through electronic exchange systems set up by the institution.
These systems shall meet the following requirements:
(a)only authorised persons may have access to the system and to documents transmitted through it;
(b)only authorised persons may electronically sign or transmit a document through the system;
(c)authorised persons must be identified through the system by established means;
(d)the time and date of the electronic transaction must be determined precisely;
(e)the integrity of documents must be preserved;
(f)the availability of documents must be preserved;
(g)where appropriate, the confidentiality of documents must be preserved;
(h)the protection of personal data in accordance with the requirements of Regulation (EC) No 45/2001 must be ensured.
Data sent or received through such a system shall enjoy legal presumption of the integrity of the data and the accuracy of the date and time of sending or receiving the data indicated by the system.
A document sent or notified through such a system shall be considered as equivalent to a paper document, shall be admissible as evidence in legal proceedings, shall be deemed to be the original of the document and shall enjoy legal presumption of its authenticity and integrity, provided it does not contain any dynamic features capable of automatically changing it.
The electronic signatures referred to in point (b) of the second subparagraph shall have the equivalent legal effect of handwritten signatures.
5.The list of experts and the subject of the tasks shall be published annually. The remuneration shall be published where it exceeds EUR 15 000 for the task performed.
6.Paragraph 5 shall not apply if such publication risks threatening the rights and freedoms of individuals concerned as protected by the Charter of Fundamental Rights of the European Union or harm the commercial interests of experts.
Textual Amendments
F1 Substituted by Commission Delegated Regulation (EU) 2015/2462 of 30 October 2015 amending Delegated Regulation (EU) No 1268/2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union.
Articles 35 to 43 of Regulation (EC, Euratom) No 2342/2002 shall continue to apply to commitments made up to 31 December 2013. Articles 33 to 44 of this Regulation shall apply only to commitments made as of 1 January 2014.
Title VI of part one of Regulation (EC, Euratom) No 2342/2002 may continue to apply to grant agreements signed and grant decisions notified by 31 December 2013 in the framework of global commitments under the budget 2012 or earlier years, should the authorising officer responsible so decide, with due regard for the principles of equal treatment and transparency.
Regulation (EC, Euratom) No 2342/2002 is repealed.
References to the repealed Regulation shall be construed as references to this Regulation and shall be read in accordance with the correlation table in the Annex.
This Regulation shall enter into force on the day following that of its publication in the Official Journal of the European Union.
It shall apply as of 1 January 2013.
However, Articles 216 to 226 shall apply as of 1 January 2014.
This Regulation shall be binding in its entirety and directly applicable in all Member States.
The Whole Regulation you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Regulation you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
This Regulation without Annexes only you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
This Regulation without Annexes only you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Regulation you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Regulation without Annexes you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: