Regulation (EU) 2017/1938 of the European Parliament and of the CouncilShow full title

Regulation (EU) 2017/1938 of the European Parliament and of the Council of 25 October 2017 concerning measures to safeguard the security of gas supply and repealing Regulation (EU) No 994/2010 (Text with EEA relevance)

 Help about what version

What Version

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

There are currently no known outstanding effects by UK legislation for Regulation (EU) 2017/1938 of the European Parliament and of the Council. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

  1. Introductory Text

  2. Article 1.Subject matter

  3. Article 2.Definitions

  4. Article 3.Responsibility for the security of gas supply

  5. Article 4.Gas Coordination Group

  6. Article 5.Infrastructure standard

  7. Article 6.Gas supply standard

  8. Article 7.Risk assessment

  9. Article 8.Establishment of preventive action plans and emergency plans

  10. Article 9.Content of preventive action plans

  11. Article 10.Content of emergency plans

  12. Article 11.Declaration of a crisis

  13. Article 12.Regional and Union emergency responses

  14. Article 13.Solidarity

  15. Article 14.Information exchange

  16. Article 15.Professional secrecy

  17. Article 16.Cooperation with the Energy Community Contracting Parties

  18. Article 17.Monitoring by the Commission

  19. Article 18.Notifications

  20. Article 19.Exercise of the delegation

  21. Article 19A.Regulations: procedure

  22. Article 20.Derogation

  23. Article 21.Repeal

  24. Article 22.Entry into force

  25. Signature

    1. ANNEX I

      Regional cooperation

    2. ANNEX II

      Calculation of the N – 1 formula

      1. 1. Definition of the N – 1 formula

      2. 2. Calculation method of the N – 1 formula

      3. 3. Definitions of the parameters of the N – 1 formula...

        1. Demand-side definition

        2. Supply-side definitions

      4. 4. Calculation of the N – 1 formula using demand-side measures...

        1. Demand-side definition

      5. 5.

    3. ANNEX III

      Permanent bi-directional capacity

      1. 1 For the execution of the provisions set out in this...

      2. 2. To enable or enhance bi-directional capacity on an interconnection or...

      3. 3. Upon receipt of the proposal or the exemption request the...

      4. 4 The regulatory authority must within six months of receipt of...

      5. 5. The Secretary of State shall on the basis of the...

      6. 6. ...

      7. 7. ...

      8. 8. ...

      9. 9. ...

      10. 10. ...

      11. 11. ...

      12. 12. The Secretary of State ..., the national regulatory authorities and...

      13. 13. Exemptions from the obligation to enable bi-directional capacity granted under...

    4. ANNEX IV

      Template for the common risk assessment

      1. The following template shall be completed in a language agreed...

      2. General information

      3. 1. Description of the system

      4. 2. Infrastructure standard (Article 5)

      5. 3. Identification of risks

      6. 4. Risk analysis and assessment

      7. 5. Conclusions

    5. ANNEX V

      Template for the national risk assessment

      1. General information

      2. 1. Description of the system

        1. 1.1. Provide a brief consolidated description of the regional gas system...

        2. ... Provide a brief description of the gas system of the...

      3. 2. Infrastructure standard (Article 5)

      4. 3. Identification of risks

        1. Analysis

      5. 4. Risk analysis and assessment

      6. 5. Conclusions

    6. ANNEX VI

      Template for preventive action plan

      1. General information

      2. 1. Description of the system

        1. 1.1. Provide a brief consolidated description of the regional gas system...

        2. ... Provide a brief description of the gas system for the...

      3. 2. Summary of the risk assessment

      4. 3. Infrastructure standard (Article 5)

        1. 3.1. N – 1 formula

        2. 3.2. ...

      5. 4. Compliance with the supply standard (Article 6)

      6. 5. Preventive measures

      7. 6. Other measures and obligations (e.g. safety operation of the system)...

      8. 7. Infrastructure projects

      9. 8. Public service obligations related to the security of supply

      10. 9. Stakeholder consultations

      11. 10. Additional matters

        1. 11.1 Calculation of the N – 1 at the level of...

        2. 11.2 Mechanisms developed for cooperation

        3. 11.3 Preventive measures

    7. ANNEX VII

      Template for emergency plan

      1. General information

      2. 1. Definition of crisis levels

      3. 2. Measures to be adopted per crisis level

        1. 2.1. Early Warning

        2. 2.2. Alert Level

        3. 2.3. Emergency Level

      4. 3. Specific measures for the electricity and district heating

      5. 4. Crisis manager or team

      6. 5. Roles and responsibilities of different actors

      7. 6. Measures regarding undue consumption by customers who are not protected...

      8. 7. Emergency tests

      9. 8. Regional Dimension

    8. ANNEX VIII

      List of non-market-based security of gas supply measures

      1. In developing the preventive action plan and the emergency plan...

      2. supply-side measures: use of strategic gas storage, enforced use of...

    9. ANNEX IX

      Correlation table

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources