Search Legislation

Regulation (EU) 2019/943 of the European Parliament and of the CouncilShow full title

Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast) (Text with EEA relevance)

 Help about what version

What Version

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

Regulation (EU) 2019/943 of the European Parliament and of the Council is up to date with all changes known to be in force on or before 28 December 2024. There are changes that may be brought into force at a future date. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the affected provisions when you open the content using the Table of Contents below.

View outstanding changes

Changes and effects yet to be applied to :

  1. Introductory Text

  2. CHAPTER I SUBJECT MATTER, SCOPE AND DEFINITIONS

    1. Article 1.Subject matter and scope

    2. Article 2.Definitions

  3. CHAPTER II GENERAL RULES FOR THE ELECTRICITY MARKET

    1. Article 3.Principles regarding the operation of electricity markets

    2. Article 4.Just transition

    3. Article 5.Balance responsibility

    4. Article 6.Balancing market

    5. Article 7.Day-ahead and intraday markets

    6. Article 8.Trade on day-ahead and intraday markets

    7. Article 9.Forward markets

    8. Article 10.Technical bidding limits

    9. Article 11.Value of lost load

    10. Article 12.Dispatching of generation and demand response

    11. Article 13.Redispatching

  4. CHAPTER III NETWORK ACCESS AND CONGESTION MANAGEMENT

    1. SECTION 1 Capacity Allocation

      1. Article 14.Bidding zone review

      2. Article 15.Action plans

      3. Article 16.General principles of capacity allocation and congestion management

      4. Article 17.Allocation of cross-zonal capacity across timeframes

    2. SECTION 2 Network charges and congestion income

      1. Article 18.Charges for access to networks, use of networks and reinforcement

      2. Article 19.Congestion income

  5. CHAPTER IV RESOURCE ADEQUACY

    1. Article 20.Resource adequacy in the internal market for electricity

    2. Article 21.General principles for capacity mechanisms

    3. Article 22.Design principles for capacity mechanisms

    4. Article 23.Methodology for resource adequacy assessment

    5. Article 24.... Resource adequacy assessments

    6. Article 25.Reliability standard

    7. Article 26.Cross-border participation in capacity mechanisms

    8. Article 27.Approval procedure

  6. CHAPTER V TRANSMISSION SYSTEM OPERATION

    1. Article 28.European network of transmission system operators for electricity

    2. Article 29.The ENTSO for Electricity

    3. Article 30.Tasks of the ENTSO for Electricity

    4. Article 31.Consultations

    5. Article 32.Monitoring by ACER

    6. Article 33.Costs

    7. Article 34.Regional cooperation of transmission system operators

    8. Article 35.Establishment and mission of regional coordination centres

    9. Article 36.Geographical scope of regional coordination centres

    10. Article 37.Tasks of regional coordination centres

    11. Article 38.Cooperation within and between regional coordination centres

    12. Article 39.Working arrangements

    13. Article 40.Consultation procedure

    14. Article 41.Transparency

    15. Article 42.Adoption and review of coordinated actions and recommendations

    16. Article 43.Management board of regional coordination centres

    17. Article 44.Organisational structure

    18. Article 45.Equipment and staff

    19. Article 46.Monitoring and reporting

    20. Article 47.Liability

    21. Article 48.Ten-year network development plan

    22. Article 49.Inter-transmission system operator compensation mechanism

    23. Article 50.Provision of information

    24. Article 51.Certification of transmission system operators

  7. CHAPTER VI DISTRIBUTION SYSTEM OPERATION

    1. Article 52.European entity for distribution system operators

    2. Article 53.Establishment of the EU DSO entity

    3. Article 54.Principal rules and procedures for the EU DSO entity

    4. Article 55.Tasks of the EU DSO entity

    5. Article 56.Consultations in the network code development process

    6. Article 57.Cooperation between distribution system operators and transmission system operators

  8. CHAPTER VII NETWORK CODES AND GUIDELINES

    1. Article 58.Adoption of network codes and guidelines

    2. Article 59.Establishment of network codes

    3. Article 60.Amendments of network codes or guidelines

    4. Article 61.Guidelines

    5. Article 62.Right of Member States to provide for more detailed measures

  9. CHAPTER VIII FINAL PROVISIONS

    1. Article 63.New interconnectors

    2. Article 64.Derogations

    3. Article 65.Provision of information and confidentiality

    4. Article 66.Penalties

    5. Article 67.Committee procedure

    6. Article 68.Exercise of the delegation

    7. Article 69.Commission reviews and reports

    8. Article 70.Repeal

    9. Article 71.Entry into force

  10. Signature

    1. ANNEX I

      TASKS OF REGIONAL COORDINATION CENTRES

      1. 1. Coordinated capacity calculation

        1. 1.1 Regional coordination centres shall carry out the coordinated calculation of...

        2. 1.2 Coordinated capacity calculation shall be performed for the day-ahead and...

        3. 1.3 Coordinated capacity calculation shall be performed on the basis of...

        4. 1.4 Coordinated capacity calculation shall be performed based on a common...

        5. 1.5 Coordinated capacity calculation shall ensure an efficient congestion management in...

      2. 2. Coordinated security analysis

        1. 2.1 Regional coordination centres shall carry out a coordinated security analysis...

        2. 2.2 Security analysis shall be performed for all operational planning timeframes,...

        3. 2.3 Coordinated security analysis shall be performed on the basis of...

        4. 2.4 Regional coordination centres shall share the results of the coordinated...

        5. 2.5 When as a result of the coordinated security analysis a...

      3. 3. Creation of common grid models

        1. 3.1 Regional coordination centres shall set up efficient processes for the...

        2. 3.2 Transmission system operators shall appoint one regional coordination centre to...

        3. 3.3 Common grid models shall be performed in accordance with the...

        4. 3.4 Common grid models shall include relevant data for efficient operational...

        5. 3.5 Common grid models shall be made available to all regional...

      4. 4. Support for transmission system operators' defence and restoration plans with...

        1. 4.1 Regional coordination centres shall support the transmission system operators in...

        2. 4.2 All transmission system operators shall agree on a threshold above...

        3. 4.3 In providing support to the transmission system operators, the regional...

        4. 4.4 Transmission system operators shall assess and take into account the...

      5. 5. Support the coordination and optimisation of regional restoration

        1. 5.1 Each relevant regional coordination centre shall support the transmission system...

        2. 5.2 Transmission system operators may request assistance from regional coordination centres...

        3. 5.3 Regional coordination centres shall be equipped with the close to...

      6. 6. Post-operation and post-disturbances analysis and reporting

        1. 6.1 Regional coordination centres shall investigate and prepare a report on...

        2. 6.2 Regional coordination centres shall publish the report. ACER may issue...

      7. 7. Regional sizing of reserve capacity

        1. 7.1 Regional coordination centres shall calculate the reserve capacity requirements for...

      8. 8. Facilitation of the regional procurement of balancing capacity

        1. 8.1 Regional coordination centres shall support the transmission system operators in...

        2. 8.2 Regional coordination centres shall support the transmission system operators of...

      9. 9. Week-ahead to at least day-ahead regional system adequacy assessments and...

        1. 9.1 Regional coordination centres shall carry out week-ahead to at least...

        2. 9.2 Regional coordination centres shall base the short-term regional adequacy assessments...

        3. 9.3 When performing a regional system adequacy assessment, each regional coordination...

        4. 9.4 Each regional coordination centre shall deliver the results of the...

      10. 10. Regional outage planning coordination

        1. 10.1 Each Regional coordination centre shall carry out regional outage coordination...

        2. 10.2 Each Regional coordination centre shall maintain a single list of...

        3. 10.3 Each Regional coordination centre shall carry out the following activities...

      11. 11. Optimisation of inter-transmission system operator compensation mechanisms

        1. 11.1 The transmission system operators in the system operation region may...

      12. 12. Training and certification of staff working for regional coordination centres...

        1. 12.1 Regional coordination centres shall prepare and carry out training and...

        2. 12.2 The training programs shall cover all the relevant components of...

      13. 13. Identification of regional electricity crisis scenarios

        1. 13.1 If the ENTSO for Electricity delegates this function, regional coordination...

        2. 13.2 Regional coordination centres shall support the competent authorities of each...

      14. 14. Identification of needs for new transmission capacity, for upgrade of...

        1. 14.1 Regional coordination centres shall support transmission system operators in the...

      15. 15. Calculation of the maximum entry capacity available for the participation...

        1. 15.1 Regional coordination centres shall support transmission system operator in calculating...

        2. 15.2 The calculation shall be performed in accordance with the methodology...

        3. 15.3 Regional coordination centres shall provide a calculation for each bidding...

      16. 16. Preparation of seasonal adequacy assessments

        1. 16.1 If the ENTSO for Electricity delegates this function pursuant to...

        2. 16.2 The preparation of seasonal adequacy assessments shall be carried out...

    2. ANNEX II

      REPEALED REGULATION WITH LIST OF THE SUCCESSIVE AMENDMENTS THERETO

    3. ANNEX III

      CORRELATION TABLE

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources