Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(1)The Roads (Scotland) Act 1984 (c. 54) is amended as follows.
(2)After section 143, insert—
(1)Subsection (3) below applies to a statutory instrument which—
(a)contains an order under section 5 of this Act directing that a road proposed to be constructed shall be a trunk road and the construction of the road would constitute a national development;
(b)contains or confirms a scheme under section 7 of this Act which authorises the carrying out of work which would constitute a national development; or
(c)is the subject of a direction by the Scottish Ministers under this paragraph.
(2)In subsection (1) above, the references to a “national development” are to any development (within the meaning of the Town and Country Planning (Scotland) Act 1997) for the time being designated under section 3A(4)(b) of that Act as a national development.
(3)The statutory instrument—
(a)is to be laid before the Scottish Parliament; and
(b)cannot come into force unless the Scottish Parliament, by resolution, approves the instrument.
(4)Unless the Scottish Ministers otherwise direct, an instrument containing or confirming an order or scheme which revokes, amends or re-enacts an instrument laid before the Scottish Parliament under paragraph (a) of subsection (3) above is not subject to the procedure in that subsection.”.
(3)In section 144(1) (regulations for procedure in schemes and orders), for the words “section 143” substitute “ sections 143 and 143A ”.
(4)In Schedule 1 (procedure for making or confirming certain orders and schemes)—
(a)after sub-paragraph (1B) of paragraph 7, insert—
“(1BA)Where—
(a)the Scottish Ministers publish under sub-paragraph (1B) above a decision to proceed with a project; and
(b)the statutory instrument giving effect to that decision is to be laid before the Scottish Parliament under section 143A(3)(a) of this Act,
they shall publish together with the decision a statement to the effect that the instrument cannot come into force until the Scottish Parliament, by resolution, approves it.”, and
(b)after sub-paragraph (1B) of paragraph 13, insert—
“(1BA)Where—
(a)the Scottish Ministers publish under sub-paragraph (1B) above a decision to proceed with a project; and
(b)the statutory instrument giving effect to that decision is to be laid before the Scottish Parliament under section 143A(3)(a) of this Act,
they shall publish together with the decision a statement to the effect that the instrument cannot come into force until the Scottish Parliament, by resolution, approves it.”.
(5)In Schedule 2 (validity and date of operation of orders and schemes)—
(a)in paragraph 1—
(i)the existing words from “stating” to “confirmed” become sub-paragraph (a),
(ii)the word “and” where it occurs for the second time is repealed,
(iii)the existing words from “naming” to “hours” become sub-paragraph (b), and
(iv)after that sub-paragraph, add—
“(c)if subsection (3) of section 143A of this Act does not apply to the statutory instrument containing or confirming the scheme or order, giving information regarding—
(i)the date on which the scheme or order will become operative; and
(ii)the right to challenge the validity of the scheme or order and the procedure for doing so; and
(d)if that subsection does apply to the relevant statutory instrument, stating that the instrument cannot come into force until the Scottish Parliament, by resolution, approves it.”,
(b)after that paragraph, insert—
As soon as may be after the Scottish Parliament has decided whether or not to approve a statutory instrument under section 143A(3)(b) of this Act, the Scottish Ministers shall publish in the Edinburgh Gazette, and in such other manner as they think best adapted for informing persons affected, a notice—
(a)stating that the Parliament has, or as the case may be has not, passed a resolution approving the instrument; and
(b)where a resolution has been passed, providing information regarding—
(i)the date on which the relevant scheme or order will become operative;
(ii)the place where a copy of it may be inspected free of charge at all reasonable hours; and
(iii)the right to challenge the validity of the scheme or order and the procedure for doing so.”, and
(c)in paragraph 2—
(i)the existing words from “the date” to “published” become sub-paragraph (a), and
(ii)after that sub-paragraph, insert “or
(b)in a case where a notice under paragraph 1A above is required, the date on which that notice is first published,”.
Commencement Information
I1S. 24 in force at 28.12.2007 by S.S.I. 2007/516, art. 2
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: