Search Legislation

The Public Contracts (Scotland) Regulations 2015

Changes over time for: Section 72

 Help about opening options

Changes to legislation:

The Public Contracts (Scotland) Regulations 2015, Section 72 is up to date with all changes known to be in force on or before 21 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Regulation 72:

  • Regulations applied by 2023 c. 54 s. 119(2)(a)
  • reg. 72(3) word substituted by S.S.I. 2019/112 reg. 3(49)(a)(i) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 72(3) words substituted by S.S.I. 2019/112 reg. 3(49)(a)(ii) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 72(4)(a)-(c) and words inserted by S.S.I. 2019/112 reg. 3(49)(b) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

  • reg. 11(1)(e)(i)(aa) words substituted by S.S.I. 2019/112 reg. 3(11)(a)(i) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 11(1)(e)(i)(bb) words substituted by S.S.I. 2019/112 reg. 3(11)(a)(ii) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 78(1)(i)(ii) and words inserted by S.S.I. 2019/112 reg. 3(52)(a) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
Modification of contracts during their termS
This section has no associated Policy Notes

72.—(1) A contract and framework agreement may be modified without a new procurement procedure—

(a)where the modifications, irrespective of their monetary value, have been provided for in the initial procurement documents in clear, precise and unequivocal review clauses, which may include price revision clauses or options, provided that such clauses—

(i)state the scope and nature of possible modifications or options as well as the conditions under which they may be used; and

(ii)do not provide for modifications or options that would alter the overall nature of the contract or framework agreement;

(b)to provide for additional works, supplies or services by the original contractor that have become necessary and were not included in the initial procurement, where a change of contractor—

(i)cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, services or installations procured under the initial procurement; and

(ii)would cause significant inconvenience or substantial duplication of costs for the contracting authority,

provided that any increase in price does not exceed 50% of the initial contract value;

(c)where all of the following conditions are fulfilled—

(i)the need for modification has been brought about by circumstances which a diligent contracting authority could not have foreseen;

(ii)the modification does not alter the overall nature of the contract or framework;

(iii)any increase in price does not exceed 50 % of the initial contract value or framework agreement;

(d)where a new contractor replaces one to which the contracting authority had initially awarded the contract or framework as a consequence of—

(i)an unequivocal review clause or option in conformity with sub-paragraph (a); or

(ii)complete or partial succession into the position of the initial contractor, following corporate restructuring, including takeover, merger, acquisition or insolvency, by another economic operator that fulfils the criteria for qualitative selection initially established, provided that this does not entail other substantial modifications to the contract or framework and is not aimed at circumventing the application of this Part;

(e)where the modifications, irrespective of their value, are not substantial (as defined in paragraph (8)); or

(f)where paragraph (5) applies.

(2) Where several successive modifications are made—

(a)the limitations imposed by the proviso at the end of paragraph (1)(b) and in paragraph (1)(c)(iii) shall apply to the value of each modification; and

(b)such successive modifications must not be aimed at circumventing these Regulations.

(3) A contracting authority which has modified a contract or framework in either of the cases described in paragraph (1)(b) and (c) must [F1submit] a notice to that effect for publication in accordance with regulation 52 ([F2publication on the UK e-notification service]).

(4) Such a notice must contain the information set out in Part G of Annex V to the Directive [F3, but as if—

(a)paragraph 9 (financing by EU funds) were omitted,

(b)in paragraph 11, “in the Official Journal of the European Union” read “on the UK e-notification service (within the meaning of the Public Contracts (Scotland) Regulations 2015)”, and

(c)in paragraph 12, “date of dispatch” were a reference to the date on which the notice is submitted to the UK e-notification service for the purposes of these Regulations].

(5) This paragraph applies where the value of the modification is below both of the following values—

(a)the relevant threshold mentioned in regulation 5 (thresholds); and

(b)10 % of the initial contract value for service and supply contracts or frameworks and 15% of the initial contract value for works contracts or frameworks,

provided that the modification does not alter the overall nature of the contract or framework agreement.

(6) For the purposes of paragraph (5), where several successive modifications are made, the value must be the net cumulative value of the successive modifications.

(7) For the purpose of the calculation of—

(a)the price mentioned in paragraph (1)(b) and (c); and

(b)the values mentioned in paragraph (5)(b),

the updated figure shall be the reference figure when the contract or framework includes an indexation clause.

(8) A modification of a contract or a framework agreement during its term must be considered substantial for the purpose of paragraph (1)(e) where—

(a)the modification renders the contract or the framework agreement materially different in character from the one initially concluded;

(b)the modification introduces conditions which, had they been part of the initial procurement procedure, would have—

(i)allowed for the admission of candidates other than those initially selected;

(ii)allowed for the acceptance of a tender other than that originally accepted; or

(iii)attracted additional participants in the procurement procedure;

(c)the modification changes the economic balance of the contract or the framework agreement in favour of the contractor in a manner which was not provided for in the initial contract or framework agreement;

(d)the modification extends the scope of the contract or framework agreement considerably; or

(e)a new contractor replaces one to which the contracting authority had initially awarded the contract or framework in cases other than those provided for in paragraph (1)(d).

(9) A new procurement procedure in accordance with these Regulations is required for modifications of the provisions of a public contract or a framework agreement during its term other than those provided for in this regulation.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Policy Note

Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources