Gas Act 1986, Section 19C is up to date with all changes known to be in force on or before 24 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
[F2(1)Section 19D applies to an LNG import or export facility, except as provided in subsections (1A) and (1B).
(1A)Section 19D does not apply to an LNG import or export facility if, or to the extent that, it is exempt under this section.
(1B)Section 19D does not apply to an LNG import or export facility if it is exempt under section 19DZA.]
(2)[F3A person who is or expects to be an owner of an [F4LNG import or export facility]] may apply in writing to the Director for an exemption [F5under this section] [F6with respect to the facility].
[F7(2A)An application under subsection (2) must relate to—
(a)a facility (or proposed facility) which is not yet operational; or
(b)a modification (or proposed modification) which falls within subsection (2B) and is not yet operational.
(2B)A modification (or proposed modification) falls within this subsection if it is—
(a)a modification of an LNG import or export facility to provide for a significant increase in the capacity of the facility; or
(b)a modification of an LNG import or export facility to enable the development of new sources of gas supply.
F8(2C). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .]
[F9(3)An exemption under this section must be given in writing and on the following terms—
(a)a term specifying the period of the exemption, or specifying how that period is to be determined;
(b)a term as to whether the exemption applies to all of the capacity of the facility or part of that capacity only;
(c)a term that the owner must comply with the capacity allocation mechanism approved in accordance with section 19DB; and
(d)such other terms regarding non-discriminatory access to the facility or any other matter as the Authority considers appropriate.
(3A)When determining a term under subsection (3) the Authority must take into account—
(a)the capacity of the facility or (as the case may be) the increase in capacity of the facility;
(b)the length of time required to recover the investment in the facility or (as the case may be) the investment in the modification; and
(c)the implications of the exemption for the operation of the gas market in Great Britain.]
F10(4). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
[F11(5)The Authority shall give an exemption with respect to a facility where it is satisfied that the requirements of subsection (7) are met.
[F12(5A)An exemption given in accordance with subsection (5) may apply to all of the capacity of the facility concerned or to part of that capacity only, regardless of the extent of the exemption applied for; but this is subject to subsection (6).]
(6)In respect of a facility which is or is to be modified to provide for a significant increase in its capacity, an exemption by virtue of subsection (5) may only be given in relation to that increase in its capacity [F13or part of that increase in its capacity].
[F14(6A)When deciding whether the requirements of subsection (7)(a), (d) and (e) are met, the Authority must take into account the way in which capacity is to be allocated under the capacity allocation mechanism approved in accordance with section 19DB.]
(7)The requirements of this subsection are that—
(a)the facility or (as the case may be) the [F15modification] will promote security of supply;
(b)the level of risk is such that the investment to construct the facility or (as the case may be) to modify the facility F16... would not be or would not have been made without the exemption;
(c)the facility is or is to be owned by a person other than the gas transporter who operates or will operate the pipeline system connected or to be connected to the facility;
(d)charges will be levied on users of the facility or (as the case may be) the increase in its capacity; [F17and]
[F18(e)the exemption will not be detrimental to competition, the operation of an economically efficient gas market or the efficient functioning of the pipeline system connected or to be connected to the facility.]
F19(f). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(8)Subject to [F20subsections (8A) and (9)], an exemption may not be given by virtue of subsection (5) more than once in respect of the same facility.
[F21(8A)Subsection (8) does not prevent a further exemption being given by virtue of subsection (5) in respect of a facility if the previous exemption given by virtue of that subsection in respect of the facility has been revoked under section 19CA(3).]
(9)Subsection (8) does not prevent a further exemption being given by virtue of subsection (5) in respect of a facility if—
the facility is or is to be modified to provide for significant increase in its capacity [F22or to enable the development of new sources of gas supply];
the exemption has effect only in relation to [F23modification]; and
no previous exemption has been given by virtue of subsection (5) in relation to [F23modification].
(10)The Authority shall publish its decision to give or refuse to give an exemption [F24under this section, together with the reasons for its decision,] in such manner as it considers appropriate.]
F25(11). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .]
Textual Amendments
F1Ss. 19A-19E inserted (10.8.2000) by S.I. 2000/1937, reg. 2(2), Sch. 2 para. 1
F2S. 19C(1)-(1B) substituted for s. 19C(1) (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(2)
F3Words in s. 19C(2) substituted (26.8.2004) by The Gas (Third Party Access) Regulations 2004 (S.I. 2004/2043), reg. 1, Sch. 2 para. 3(b)
F4Words in s. 19C(2) substituted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(3)(a)
F5Words in s. 19C(2) inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(3)(b)
F6Words in s. 19C(2) substituted (26.8.2004) by The Gas (Third Party Access) Regulations 2004 (S.I. 2004/2043), reg. 1, Sch. 2 para. 3(c)
F7S. 19C(2A)-(2C) inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(4)
F8S. 19C(2C) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 26; 2020 c. 1, Sch. 5 para. 1(1)
F9S. 19C(3)(3A) substituted for s. 19C(3) (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(5)
F10S. 19C(4) omitted (10.11.2011) by virtue of The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(6)
F11S. 19C(5)-(10) substituted for s. 19C(5) (26.8.2004) by The Gas (Third Party Access) Regulations 2004 (S.I. 2004/2043), reg. 1, Sch. 2 para. 3(f)
F12S. 19C(5A) inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(7)
F13Words in s. 19C(6) inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(8)
F14S. 19C(6A) inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(9)
F15Word in s. 19C(7)(a) substituted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(10)(a)
F16Words in s. 19C(7)(b) omitted (10.11.2011) by virtue of The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(10)(b)
F17Word in s. 19C(7)(d) inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(10)(c)
F18S. 19C(7)(e) substituted (31.12.2020 immediately before IP completion day) by The Gas (Internal Markets) Regulations 2020 (S.I. 2020/625), regs. 1(2), 10(6)(a)
F19S. 19C(7)(f) and word omitted (10.11.2011) by virtue of The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(10)(d)
F20Words in s. 19C(8) substituted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(11)
F21S. 19C(8A) inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(12)
F22Words in s. 19C(9) inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(13)(a)
F23Word in s. 19C(9) substituted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(13)(b)
F24Words in s. 19C(10) substituted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 11(14)
F25S. 19C(11) omitted (31.12.2020 immediately before IP completion day) by virtue of The Gas (Internal Markets) Regulations 2020 (S.I. 2020/625), regs. 1(2), 10(6)(b)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: