Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)The person for the time being entitled to the benefit of a section 36 consent may make an application to the appropriate authority for the consent to be varied.
(2)Regulations may make provision about the variation of a section 36 consent, including in particular provision about—
(a)the making and withdrawal of applications;
(b)fees;
(c)publicity and consultation requirements;
(d)rights to make representations;
(e)public inquiries;
(f)consideration of applications.
(3)Regulations under subsection (2) may provide for any statutory provision applicable to the grant of a section 36 consent to apply with specified modifications to the variation of a section 36 consent.
(4)On an application for a section 36 consent to be varied, the appropriate authority may make such variations to the consent as appear to the authority to be appropriate, having regard (in particular) to—
(a)the applicant's reasons for seeking the variation;
(b)the variations proposed;
(c)any objections made to the proposed variations, the views of consultees and the outcome of any public inquiry.
(5)Regulations may make provision treating, for prescribed purposes, a section 36 consent varied under this section as granted in its varied form when the original consent was granted (rather than when the variation was made).
[F2(5A)Regulations may provide that, where the Welsh Ministers are the appropriate authority, applications under this section are to be determined by a person appointed by the Welsh Ministers for that purpose.]
(6)In this section—
“the appropriate authority” means—
the Scottish Ministers, in a case where the section 36 consent relates to a generating station (or proposed generating station) in Scotland;
[F3the Welsh Ministers, in a case where the section 36 consent relates to a generating station (or proposed generating station) in Welsh waters that does not or will not when constructed or extended exceed 350 megawatts;]
the Marine Management Organisation, in a case where the section 36 consent was granted by it [F4and does not relate to a generating station (or proposed generating station) in Welsh waters that does not or will not when constructed or extended exceed 350 megawatts];
the Secretary of State, in any other case;
“regulations” means regulations made by—
the Scottish Ministers, in the case of section 36 consents relating to generating stations (or proposed generating stations) in Scotland;
[F5the Welsh Ministers, in the case of section 36 consents relating to generating stations (or proposed generating stations) in Welsh waters that do not or will not when constructed or extended exceed 350 megawatts;]
the Secretary of State, in any other case;
“Scotland” has the same meaning as in section 32(2) (see section 32(3));
“section 36 consent” means a consent granted under section 36 (construction, extension or operation of generating station), whenever granted;
“statutory provision” means a provision of or made under an Act, whenever passed or made; and for this purpose “Act” includes an Act of the Scottish Parliament [F6and an Act of the Assembly].
[F7"Welsh waters” has the meaning given in section 36.]]
Textual Amendments
F1S. 36C inserted (19.6.2013 for specified purposes, 31.7.2013 in relation to E.W. so far as it is not already in force, 1.12.2013 in relation to S. so far as it is not already in force) by Growth and Infrastructure Act 2013 (c. 27), ss. 20(2), 35(1); S.I. 2013/1488, arts. 2, 5(a), 7
F2S. 36C(5A) inserted (1.4.2019) by Wales Act 2017 (c. 4), s. 71(4), Sch. 6 para. 48 (with Sch. 7 paras. 1, 6); S.I. 2017/1179, reg. 5(b)
F3Words in s. 36C(6) inserted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(12)(a)(i), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F4Words in s. 36C(6) inserted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(12)(a)(ii), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F5Words in s. 36C(6) inserted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(12)(b), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F6Words in s. 36C(6) inserted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(12)(c), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F7Words in s. 36C(6) inserted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(12)(d), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Part you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Part you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: