- Latest available (Revised)
- Original (As enacted)
Town and Country Planning Act 1990, Section 174 is up to date with all changes known to be in force on or before 24 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)A person having an interest in the land to which an enforcement notice relates or a relevant occupier may appeal to the Secretary of State against the notice, whether or not a copy of it has been served on him.
[F1(2)An appeal may be brought on any of the following grounds—
(a)that, in respect of any breach of planning control which may be constituted by the matters stated in the notice, planning permission ought to be granted or, as the case may be, the condition or limitation concerned ought to be discharged;
(b)that those matters have not occurred;
(c)that those matters (if they occurred) do not constitute a breach of planning control;
(d)that, at the date when the notice was issued, no enforcement action could be taken in respect of any breach of planning control which may be constituted by those matters;
(e)that copies of the enforcement notice were not served as required by section 172;
(f)that the steps required by the notice to be taken, or the activities required by the notice to cease, exceed what is necessary to remedy any breach of planning control which may be constituted by those matters or, as the case may be, to remedy any injury to amenity which has been caused by any such breach;
(g)that any period specified in the notice in accordance with section 173(9) falls short of what should reasonably be allowed.
[F2(2A)An appeal may not be brought on the ground specified in subsection (2)(a) if—
(a)the land to which the enforcement notice relates is in England, and
(b)the enforcement notice was issued at a time after the making of an application for planning permission that was related to the enforcement notice.
(2AA)For the purposes of subsection (2A)—
(a)an application for planning permission for the development of any land is related to an enforcement notice if granting planning permission for the development would involve granting planning permission in respect of the matters specified in the enforcement notice as constituting a breach of planning control;
(b)an application for planning permission that the local planning authority or the Secretary of State declined to determine under section 70A, 70B or 70C is to be ignored.
(2AB)But subsection (2A) does not apply if—
(a)the application for planning permission has ceased to be under consideration, and
(b)the enforcement notice was issued after the end of the period of two years beginning with the day on which the application ceased to be under consideration.
(2AC)For the purposes of subsection (2AB), an application for planning permission has ceased to be under consideration if—
(a)the application was refused, or granted subject to conditions, and, in the case of an application determined by the local planning authority, the applicant did not appeal under section 78(1)(a);
(b)the applicant did not appeal in the circumstances mentioned in section 78(2) and the application was not subsequently refused;
(c)the applicant appealed under section 78(1)(a) or section 78(2) and—
(i)the appeal was dismissed,
(ii)the application was on appeal granted subject to conditions, or subject to different conditions, or
(iii)the Secretary of State declined under section 79(6) to determine the appeal.
(2B)For the purposes of subsection (2AB), the day on which the application ceased to be under consideration is—
(a)in a case within subsection (2AC)(a), the day on which the right to appeal arose;
(b)in a case within subsection (2AC)(b), the day after the end of the prescribed period referred to in section 78(2);
(c)in a case within subsection (2AC)(c)(i), the day on which the appeal was dismissed;
(d)in a case within subsection (2AC)(c)(ii), the day on which the appeal was determined;
(e)in a case within subsection (2AC)(c)(iii) relating to an appeal under section 78(1)(a), the day on which the right to appeal arose;
(f)in a case within subsection (2AC)(c)(iii) relating to an appeal under section 78(2), the day after the end of the prescribed period referred to in section 78(2).]
[F3(2C)Where any breach of planning control constituted by the matters stated in the notice relates to relevant demolition (within the meaning of section 196D), an appeal may also be brought on the grounds that—
(a)the relevant demolition was urgently necessary in the interests of safety or health;
(b)it was not practicable to secure safety or health by works of repair or works for affording temporary support or shelter; and
(c)the relevant demolition was the minimum measure necessary.]
[F4(2D)An appeal against an enforcement notice may not be brought on the ground that planning permission ought to be granted in respect of a breach of planning control constituted by a matter stated in the notice, as specified in subsection (2)(a), if—
(a)the land to which the enforcement notice relates is in Wales, and
(b)the enforcement notice was issued after a decision to refuse planning permission for a related development was upheld on an appeal under section 78 (and for this purpose development is “related” if granting planning permission for it would involve granting planning permission in respect of the matter concerned).
(2E)An appeal may not be brought on the ground that a condition or limitation ought to be discharged, as specified in subsection (2)(a), if—
(a)the land to which the enforcement notice relates is in Wales, and
(b)the enforcement notice was issued after a decision to grant planning permission subject to the condition or limitation was upheld on an appeal under section 78.
(2F)For the purposes of subsections (2D) and (2E), references to a decision that has been upheld on an appeal include references to a decision in respect of which—
(a)the Welsh Ministers have, under section 79(6), declined to determine an appeal or to proceed with the determination of an appeal;
(b)an appeal has been dismissed under section 79(6A).]
(3)An appeal under this section shall be made F5. . . —
(a)by giving written notice of the appeal to the Secretary of State before the date specified in the enforcement notice as the date on which it is to take effect; or
(b)by sending such notice to him in a properly addressed and pre-paid letter posted to him at such time that, in the ordinary course of post, it would be delivered to him before that date [F6; or
(c)by sending such notice to him using electronic communications at such time that, in the ordinary course of transmission, it would be delivered to him before that date.]]
(4)A person who gives notice under subsection (3) shall submit to the Secretary of State, either when giving the notice or within the prescribed time, a statement in writing—
(a)specifying the grounds on which he is appealing against the enforcement notice; and
(b)giving such further information as may be prescribed.
(5)If, where more than one ground is specified in that statement, the appellant does not give information required under subsection (4)(b) in relation to each of those grounds within the prescribed time, the Secretary of State may determine the appeal without considering any ground as to which the appellant has failed to give such information within that time.
(6)In this section “relevant occupier” means a person who—
(a)on the date on which the enforcement notice is issued occupies the land to which the notice relates by virtue of a licence [F7. . .; and
(b)continues so to occupy the land when the appeal is brought.
Textual Amendments
F1S. 174(2)(3) substituted (2.1.1992) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 6(1) (with s. 84(5)); S.I. 1991/2905, art.3 (subject to art. 5)
F2S. 174(2A)-(2B) substituted for s. 174(2A)(2B) (25.4.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 118, 255(3)(b) (with s. 247); S.I. 2024/452, reg. 3(e) (with reg. 7)
F3S. 174(2C) inserted (1.10.2013) by Enterprise and Regulatory Reform Act 2013 (c. 24), s. 103(3), Sch. 17 para. 5; S.I. 2013/2227, art. 2(m)
F4S. 174(2D)-(2F) inserted (6.9.2015 for specified purposes, 16.3.2016 in so far as not already in force) by Planning (Wales) Act 2015 (anaw 4), ss. 46, 58(2)(b)(4)(b); S.I. 2016/52, art. 5(c) (with art. 14)
F5Word in s. 174(3) repealed (E.) (31.3.2003) by The Town and Country Planning (Electronic Communications) (England) Order 2003 (S.I. 2003/956), art. 3 and (W.) (1.1.2005) by The Town and Country Planning (Electronic Communications) (Wales) Order 2004 (S.I. 2004/3156), arts. 3, 14
F6Word and s. 174(3)(c) inserted (E.) (31.3.2003) by The Town and Country Planning (Electronic Communications) (England) Order 2003 (S.I. 2003/956), art. 3 and added (W.) (1.1.2005) by The Town and Country Planning (Electronic Communications) (Wales) Order 2004 (S.I. 2004/3156), arts. 3, 14
F7Words in s. 174(6) omitted (2.1.1992) by virtue of Planning and Compensation Act 1991 (c. 34, SIF 123:1),s. 32, Sch. 7 para. 22 (with s. 84(5)); S.I. 1991/2905, art.3, Sch. 1 (subject to art. 5)
Modifications etc. (not altering text)
C1S. 174: power to apply conferred (11.3.1992 so far as to confer on the Secretary of State a power or impose on him a duty to make regulations, or make provision with respect to the exercise of any such power or duty, 1.6.1992 so far not already in force) by Planning (Hazardous Substances) Act 1990 (c. 10, SIF 123:1), s. 25(1)(b); S.I. 1992/725, arts. 2, 3
C2S. 174 applied (with modifications) (1.6.1992) by S.I. 1992/656, reg. 18(1), Sch. 4 Pt. I
S. 174: power to apply conferred (10.11.1993) by 1993 c. 28, s. 171(4)(a); S.I. 1993/2762, art. 3
C3S. 174 applied (with modifications) (E.) (1.6.2015) by The Planning (Hazardous Substances) Regulations 2015 (S.I. 2015/627), regs. 1(1), 15, Sch. 4 Pt. 1 (with reg. 34)
C4S. 174(1)(2) applied (with modifications) (W.) (4.9.2015) by The Planning (Hazardous Substances) (Wales) Regulations 2015 (S.I. 2015/1597), regs. 1(1), 16, Sch. 4 Pt. 1 (with reg. 36)
C5S. 174(2C) transitional provisions for effects of 2003 c. 24, s. 63, Sch. 17 paras. 1-6 (2.10.2013) by The Town and Country Planning (Isles of Scilly) Order 2013 (S.I. 2013/2148), arts. 1(1), 5(4)(b)
C6S. 174(3)-(6) applied (with modifications) (W.) (4.9.2015) by The Planning (Hazardous Substances) (Wales) Regulations 2015 (S.I. 2015/1597), regs. 1(1), 16, Sch. 4 Pt. 1 (with reg. 36)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: