Town and Country Planning Act 1990, Section 62E is up to date with all changes known to be in force on or before 28 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)A person who proposes to make an application to the Welsh Ministers under section 62D must notify the following of the proposed application—
(a)the Welsh Ministers, and
(b)the local planning authority to which, but for section 62D, the application would be made.
(2)The notification must comply with any requirements specified in a development order.
(3)Those requirements may include requirements as to—
(a)the form and content of a notification;
(b)information that is to accompany the notification (including information about secondary consents in respect of which the person considers a decision should be made by the Welsh Ministers under section 62F, or otherwise relating to secondary consents);
(c)the way in which and time in which the notification is to be given.
(4)On receiving notification of an application from a person in accordance with this section, the Welsh Ministers must give notice to the person that the notification has been accepted.
(5)Any step taken in respect of an application that is proposed to be made under section 62D, if taken before the date on which notice is given under subsection (4) in respect of the application, is not to be treated for the purposes of this Act as constituting consultation with any person about the application.
(6)A development order may make provision about the giving of notice by the Welsh Ministers under subsection (4).
(7)That provision may include provision—
(a)about the form and content of the notice to be given under subsection (4);
(b)about the way in which it is to be given;
(c)about the period within which it is to be given (including provision about circumstances in which the Welsh Ministers may extend that period in a particular case).
(8)In this section and sections 62F and 62G, “secondary consent” has the meaning given in section 62H.]
Textual Amendments
F1Ss. 62D, 62E and cross-heading inserted (6.9.2015 for specified purposes, 1.3.2016 in so far as not already in force) by Planning (Wales) Act 2015 (anaw 4), ss. 19, 58(2)(b)(4)(b); S.I. 2016/52, art. 2(a) (with art. 7)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: