Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
15(1)In Schedule 9, in paragraph 1(1) for paragraph (a) there is substituted—E+W
“(a)that any use of land for—
(i)development consisting of the winning and working of minerals; or
(ii)the depositing of refuse or waste materials,
should be discontinued or that any conditions should be imposed on the continuance of the winning and working or the depositing;”.
(2)For paragraph (c) of that sub-paragraph there is substituted—
“(c)that any plant or machinery used for the winning and working or the depositing should be altered or removed,”.
(3)For sub-paragraphs (2) and (3) of that paragraph there is substituted—
“(2)An order under this paragraph may grant planning permission for any development of the land to which the order relates, subject to such conditions as may be—
(a)required by paragraph 1 of Schedule 5; or
(b)specified in the order.
(3)Subsections (3) to (5) and (7) of section 102 and section 103 apply to orders under this paragraph as they apply to orders under section 102, but as if—
(a)references to the local planning authority were references to the mineral planning authority; and
(b)the reference in section 103(2)(a) to subsection (2) of section 102 were a reference to sub-paragraph (2).”
(4)In paragraph 2 of that Schedule for sub-paragraph (1) there is substituted—
“(1)An order under paragraph 1 may impose a restoration condition”.
(5)In sub-paragraph (4)(b) of that paragraph for the words from “before” to “under it” there is substituted “ before the development began ”.
(6)For paragraph 3(1) to (3) of that Schedule there is substituted—
“(1)Where it appears to the mineral planning authority—
(a)that development of land—
(i)consisting of the winning and working of minerals; or
(ii)involving the depositing of mineral waste,
has occurred; but
(b)the winning and working or depositing has permanently ceased,
the mineral planning authority may by order—
(i)prohibit the resumption of the winning and working or the depositing; and
(ii)impose, in relation to the site, any such requirement as is specified in sub-paragraph (3).
(2)The mineral planning authority may assume that the winning and working or the depositing has permanently ceased only when—
(a)no winning and working or depositing has occurred, to any substantial extent, at the site for a period of at least two years; and
(b)it appears to the mineral planning authority, on the evidence available to them at the time when they make the order, that resumption of the winning and working or the depositing to any substantial extent at the site is unlikely.
(3)The requirements mentioned in sub-paragraph (1) are—
(a)a requirement to alter or remove plant or machinery which was used for the purpose of the winning and working or the depositing or for any purpose ancillary to that purpose;
(b)a requirement to take such steps as may be specified in the order, within such period as may be so specified, for the purpose of removing or alleviating any injury to amenity which has been caused by the winning and working or depositing, other than injury due to subsidence caused by underground mining operations;
(c)a requirement that any condition subject to which planning permission for the development was granted or which has been imposed by virtue of any provision of this Act shall be complied with; and
(d)a restoration condition.”
(7)At the end of paragraph 4(8) of that Schedule there is inserted “ or involving the depositing of mineral waste ”.
(8)For paragraph 5(1) of that Schedule there is substituted—
“(1)Where it appears to the mineral planning authority—
(a)that development of land—
(i)consisting of the winning and working of minerals; or
(ii)involving the depositing of mineral waste,
has occurred; but
(b)the winning and working or depositing has been temporarily suspended,
the mineral planning authority may by order require that steps be taken for the protection of the environment.”
(9)For sub-paragraphs (3) and (4) there is substituted—
“(3)The mineral planning authority may assume that the winning and working or the depositing has been temporarily suspended only when—
(a)no such winning and working or depositing has occurred, to any substantial extent, at the site for a period of at least twelve months; but
(b)it appears to the mineral planning authority, on the evidence available to them at the time when they make the order, that a resumption of such winning and working or depositing to a substantial extent is likely.
(4)In this Act “steps for the protection of the environment” means steps for the purpose—
(a)of preserving the amenities of the area in which the land in, on or under which the development was carried out is situated during the period while the winning and working or the depositing is suspended;
(b)of protecting that area from damage during that period; or
(c)of preventing any deterioration in the condition of the land during that period.”
(10)In paragraph 10(1) of that Schedule for “in, on or under the land” there is substituted “ or involving the depositing of mineral waste at the site ”.
(11)In sub-paragraph (3) of that paragraph for “development consisting of the winning and working of minerals” there is substituted “ the development ”.
(12)For sub-paragraph (4) of that paragraph there is substituted—
“(4)The mineral planning authority shall revoke the order if the winning and working of minerals or the depositing of mineral waste has recommenced to a substantial extent at the site in relation to which the order has effect.”
(13)For sub-paragraph (8) there is substituted—
“(8)If the Secretary of State is satisfied that the winning and working of minerals or the depositing of mineral waste has recommenced to a substantial extent at the site in relation to which the order has effect, he shall revoke the order.”
(14)At the end of that Schedule there is inserted—
12In this Schedule any reference to a mineral planning authority shall be construed, in relation to the exercise of functions with respect to the depositing of refuse or waste materials (other than mineral waste), as a reference to the authority entitled to discharge such functions.”
Commencement Information
I1Sch. 1 para. 15 wholly in force at 25.9.1991, see s. 84(2)(3) and S.I. 1991/2067, art. 3
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: