- Latest available (Revised)
- Original (As enacted)
There are currently no known outstanding effects for the Channel Tunnel Rail Link Act 1996, Part IV.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Textual Amendments
F1Sch. 15 Pt. IV heading substituted (28.12.2017) by Digital Economy Act 2017 (c. 30), s. 118(6), Sch. 3 para. 38(2); S.I. 2017/1286, reg. 2(d)
Modifications etc. (not altering text)
C1Sch. 15 Pt. IV (paras. 1-6) applied (with modifications) (19.2.1999) by S.I. 1999/537, art. 13(1), Sch. 3 paras. 1-8
Sch. 15 Pt. IV (paras. 1-6) applied (with modifications) (22.3.2001) by S.I. 2001/1451, art. 15(1), Sch. 3 paras. 1(j), 3(9)
Sch. 15 Pt. IV applied (with modifications) (12.8.2002) by S.I. 2002/1943, art. 15(1)(d)
1(1)The following provisions of this Part of this Schedule shall, unless otherwise agreed in writing between the nominated undertaker and [F2an operator of an electronic communications code network], have effect.U.K.
(2)In this Part of this Schedule—
“the authorised works” means the works authorised by Part I of this Act;
“construction” includes installation and “construct” shall be construed accordingly;
F3...
F3...
F3...
Textual Amendments
F2Words in Sch. 15 Pt. 4 para. 1(1) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), Sch. 17 para. 139(2) (with Sch. 18); S.I. 2003/1900, Sch. 1.
F3Words in Sch. 15 Pt. 4 para. 1(2) repealed (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), Sch. 19(1) (with Sch. 18); S.I. 2003/1900, Sch. 1.
2(1)[F4Part 6 of Schedule 3A to the Communications Act 2003 (the electronic communications code)] shall not apply for the purposes of the authorised works to the extent that such works are regulated by Part XI of the M1Town and Country Planning Act 1990, sections 84 and 85 of the M2New Roads and Street Works Act 1991 (or regulations made under section 85 of that Act) or sub-paragraphs (3) to (8) of paragraph 4 below.U.K.
(2)[F5Part 10] of the [F6electronic communications code] shall apply for the purposes of the authorised works, save—
(a)insofar as such works are regulated by the M3New Roads and Street Works Act 1991 or any regulation made under that Act; or
(b)where the nominated undertaker exercises a right under subsection (4)(b) of section 272 of the M4Town and Country Planning Act 1990 or under an order made under that section to remove telecom- munications apparatus.
Textual Amendments
F4Words in Sch. 15 Pt. IV para. 2(1) substituted (28.12.2017) by Digital Economy Act 2017 (c. 30), s. 118(6), Sch. 3 para. 38(3); S.I. 2017/1286, reg. 2(d)
F5Words in Sch. 15 Pt. IV para. 2(2) substituted (28.12.2017) by Digital Economy Act 2017 (c. 30), s. 118(6), Sch. 3 para. 38(4); S.I. 2017/1286, reg. 2(d)
F6Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(a) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
Marginal Citations
3U.K.The temporary stopping up or diversion of any highway under paragraph 6 of Schedule 3 to this Act shall not affect any right of [F7an operator] under [F8Part 8] of the [F6electronic communications code] in respect of any apparatus which at the time of the stopping up or diversion is in the highway.
Textual Amendments
F6Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(a) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
F7Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(c) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
F8Words in Sch. 15 Pt. IV para. 3 substituted (28.12.2017) by Digital Economy Act 2017 (c. 30), s. 118(6), Sch. 3 para. 38(5); S.I. 2017/1286, reg. 2(d)
4(1)Where a highway is stopped up under paragraph 1 or 2 of Schedule 3 to this Act, [F9any operator of an electronic communications code network] whose [F10electronic communications apparatus] is under, over, in, on, along or across that highway may exercise the same rights of access in order to inspect, maintain, adjust, repair or alter that apparatus as if this Act had not been passed, but nothing in this sub-paragraph shall affect any right of the nominated undertaker or [F11the operator] to require removal of that apparatus under this Part of this Schedule or the power of the nominated undertaker to alter apparatus in accordance with [F12Part 10] of the [F6electronic communications code].U.K.
(2)The nominated undertaker shall give not less than 28 days’ notice in writing of its intention to stop up any highway under paragraph 1 or 2 of Schedule 3 to this Act to [F9any operator of an electronic communications code network] whose apparatus is under, over, in, on, along or across the highway.
(3)Where a notice under sub-paragraph (2) above has been given, [F11the operator], if it reasonably considers that it is necessary for the safe and efficient operation and maintenance of the apparatus, may, and if reasonably requested so to do by the nominated undertaker in the notice, shall, as soon as reasonably practicable after the service of the notice—
(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as [F11the operator] may reasonably determine and have power to place it, or
(b)provide other apparatus in substitution for the existing apparatus and place it in such other position as aforesaid.
(4)Subject to the following provisions of this paragraph the nominated undertaker shall pay to [F9any operator of an electronic communications code network] an amount equal to the cost reasonably incurred by [F11the operator] in or in connection with—
(a)the execution of relocation works required in consequence of the stopping up of the highway, and
(b)the doing of any other work or thing rendered necessary by the execution of relocation works.
(5)If in the course of the execution of relocation works under sub-paragraph (3) above—
(a)apparatus of better type, greater capacity or greater dimensions is placed in substitution for existing apparatus of worse type, smaller capacity or smaller dimensions, except where this has been solely due to using the nearest currently available type, capacity or dimension, or
(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which existing apparatus was,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the nominated undertaker, or, in default of agreement, is not determined by arbitration to be necessary in consequence of the construction of the authorised works in order to ensure the continued efficient operation of the [F13electronic communications code network] of [F11the operator] then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this paragraph would be payable to [F11the operator] by virtue of sub-paragraph (4) above shall be reduced by the amount of that excess.
(6)For the purposes of sub-paragraph (5) above—
(a)an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus except in a case where the apparatus as so extended provides more than an equivalent service, and
(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole (in either case of such type, capacity and dimensions as shall reasonably be appropriate) shall be treated as if it also had been agreed or had been so determined.
(7)The amount which apart from this sub-paragraph would be payable to [F7an operator] in respect of works by virtue of sub-paragraph (4) above (and having regard, where relevant, to sub-paragraph (5) above) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7½ years earlier so as to confer on the telecom- munications operator any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
(8)Sub-paragraphs (4) to (7) above shall not apply where the authorised works constitute major transport works or major highway works for the purpose of Part III of the M5New Roads and Street Works Act 1991 (including that provision as applied by paragraph 8 of Schedule 3 to this Act), but instead—
(a)the allowable costs of any relocation works shall be determined in accordance with section 85 of that Act (sharing of costs of necessary measures) and any regulations for the time being having effect under that section, and
(b)the allowable costs shall be borne by the nominated undertaker and [F11the operator] in such proportions as may be prescribed by any such regulations.
Textual Amendments
F6Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(a) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
F7Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(c) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
F9Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(d) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
F10Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(b) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
F11Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(e) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
F12Words in Sch. 15 Pt. IV para. 4(1) substituted (28.12.2017) by Digital Economy Act 2017 (c. 30), s. 118(6), Sch. 3 para. 38(6); S.I. 2017/1286, reg. 2(d)
F13Words in Sch. 15 paras. 2-4 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 139(3)(f) (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3))
Marginal Citations
5(1)Subject to sub-paragraphs (2) to (4) below, if by reason or in consequence of the construction of the authorised works or any subsidence resulting from any of those works, any damage is caused to any [F14electronic communications apparatus], other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works, or property of the [F15operator of an electronic communications code network], or there is any interruption in the supply of the service provided by the [F16operator], the nominated undertaker shall bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and shall—U.K.
(a)make reasonable compensation to the [F16operator] for loss sustained by it, and
(b)indemnify the [F16operator] against claims, demands, proceedings, costs, damages and expenses which may be made or taken against, or recovered from, or incurred by, the operator, by reason or in consequence of any such damage or interruption.
(2)Sub-paragraph (1) above shall not apply to any apparatus in respect of which the relations between the nominated undertaker and the [F16operator] are regulated by the provisions of Part III of the New Roads and Street Works Act 1991 or to any damage, or any interruption, caused by electro-magnetic interference arising from the construction or use of the authorised works.
(3)Nothing in sub-paragraph (1) above shall impose any liability on the nominated undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of the [F16operator], its officers, servants, contractors or agents.
(4)The [F16operator] shall give the nominated undertaker reasonable notice of any such claim or demand and no settlement or compromise thereof shall be made without the consent of the nominated undertaker which, if it withholds such consent, shall have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
Textual Amendments
F14Words in Sch. 15 Pt. 4 para. 5 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), Sch. 17 para. 139(4)(a), (with Sch. 18);S.I. 2003/1900, Sch. 1
F15Words in Sch. 15 Pt. 4 para. 5 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), Sch. 17 para. 139(4)(b), (with Sch. 18); S.I. 2003/1900, Sch. 1.
F16Words in Sch. 15 Pt. 4 para. 5 substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), Sch. 17 para. 139(4)(c), (with Sch. 18; S.I. 2003/1900, Sch. 1.
6U.K.Any dispute arising under this Part of this Schedule shall be determined by an arbitrator who shall be appointed by agreement between the parties or, in default of such agreement, shall be the Secretary of State.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: