- Latest available (Revised)
- Original (As enacted)
Town and Country Planning (Scotland) Act 1997, Section 239 is up to date with all changes known to be in force on or before 22 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)If any person—
(a)is aggrieved by any order to which this section applies and wishes to question the validity of that order on the grounds—
(i)that the order is not within the powers of this Act, or
(ii)that any of the relevant requirements have not been complied with in relation to that order, or
(b)is aggrieved by any action on the part of the Secretary of State [F1, or on the part of a planning authority,] to which this section applies and wishes to question the validity of that action on the grounds—
(i)that the action is not within the powers of this Act, or
(ii)that any of the relevant requirements have not been complied with in relation to that action,
he may make an application to the Court of Session under this section.
(2)Without prejudice to subsection (1), if the authority directly concerned with any order to which this section applies, or with any action on the part of the Secretary of State to which this section applies, wish to question the validity of that order or action on any of the grounds mentioned in subsection (1), the authority may make an application to the Court of Session under this section.
(3)An application under this section must be made within 6 weeks from the date on which the order is confirmed (or, in the case of an order under section 65 which takes effect under section 67 without confirmation, the date on which it takes effect) or, as the case may be, the date on which the action is taken.
(4)This section applies to any such order as is mentioned in subsection (2) of section 237 and to any such action on the part of the Secretary of State as is mentioned in subsection (3) of that section [F2or on the part of a planning authority as is mentioned in subsection (3A) of that section].
(5)On any application under this section the Court of Session—
(a)may, subject to subsection (6), by interim order suspend the operation of the order or action in question until the final determination of the proceedings;
(b)if satisfied that the order or action in question is not within the powers of this Act, or that the interests of the applicant have been substantially prejudiced by failure to comply with any of the relevant requirements in relation to it, may quash that order or action.
(6)Paragraph (a) of subsection (5) shall not apply to applications questioning the validity of tree preservation orders.
(7)In relation to a tree preservation order, or to an order made in pursuance of section 183(4), the powers conferred on the Court of Session by subsection (5) shall be exercisable by way of quashing or (where applicable) suspending the operation of the order either in whole or in part, as the court may determine.
(8)References in this section to the confirmation of an order include the confirmation of an order subject to modifications as well as the confirmation of an order in the form in which it was made.
(9)In this section “the relevant requirements”, in relation to any order or action to which this section applies, means any requirements of this Act or of the M1Tribunals and Inquiries Act 1992, or of any order, regulations or rules made under this Act or under that Act which are applicable to that order or action.
(10)Any reference in this section to the authority directly concerned with any order or action to which this section applies—
(a)in relation to any such decision as is mentioned in section 237(3)(e), where the Secretary of State confirms the notice in question, wholly or in part, with the substitution of another local authority or statutory undertakers for the planning authority, includes a reference to that local authority or those statutory undertakers;
(b)in any other case, is a reference to the planning authority.
Textual Amendments
F1Words in s. 239(1)(b) inserted (12.12.2008 for specified purposes, 3.8.2009 in so far as not already in force) by Planning etc. (Scotland) Act 2006 (asp 17), ss. 19(4)(a), 59(2); S.S.I. 2008/411, art. 2(2)(3)(a), S.S.I. 2009/219, art. 2, sch.
F2Words in s. 239(4) added (12.12.2008 for specified purposes, 3.8.2009 in so far as not already in force) by Planning etc. (Scotland) Act 2006 (asp 17), ss. 19(4)(b), 59(2); S.S.I. 2008/411, art. 2(2)(3)(a), S.S.I. 2009/219, art. 2, sch.
Modifications etc. (not altering text)
C1S. 239 applied (with modifications) (1.4.2010) by The Management of Extractive Waste (Scotland) Regulations 2010 (S.S.I. 2010/60), regs. 1(1), 10(5) (with regs. 4, 5)
C2S. 239 applied (with modifications) (1.6.2015) by The Town and Country Planning (Hazardous Substances) (Scotland) Regulations 2015 (S.S.I. 2015/181), regs. 1, 54(1)(3)
C3S. 239: power to apply conferred (27.5.1997) by 1997 c. 10, ss. 23(1)(b), 31, 40(2) (with ss. 9(3), 10(5), 38(6)
S. 239(1)(b),(2): extended (1.8.1999) by S.S.I. 1999/1, reg. 43
C4S. 239(1)(b) modified (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017 (S.S.I. 2017/102), regs. 1, 47 (with regs. 2(10), 38, 39, 40, 60(7))
C5S. 239(2) modified (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017 (S.S.I. 2017/102), regs. 1, 47 (with regs. 2(10), 38, 39, 40, 60(7))
Marginal Citations
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: