Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
[F2[F3(1)Where a planning permission to which this section applies is granted or deemed to be granted, it must be granted or, as the case may be, is to be deemed to be granted subject to the condition that the development to which it relates must be begun not later than the expiration of—
(a)3 years beginning with the date on which the permission is granted or, as the case may be, deemed to be granted, or
(b)such other period (whether longer or shorter) as the authority concerned may specify when granting the permission or, as the case may be, in making a direction under section 57.
(2)If planning permission is granted or is deemed to be granted without the condition required by subsection (1), the permission is deemed to be subject to the condition that the development to which it relates must be begun not later than the expiration of 3 years beginning with the date on which the permission is granted or, as the case may be, deemed to be granted.
(3)If development has not begun at the expiration of the period mentioned in paragraph (a) or (b) of subsection (1) or, as the case may be, subsection (2), the planning permission lapses.]
(3A)A period specified under subsection [F4(1)(b)] is to be a period—
[F5(a)beginning with the date on which the planning permission is granted or deemed to be granted, and]
(b)which the authority concerned consider appropriate having regard to the provisions of the development plan and to any other material considerations.]
[F6(3B)During the emergency period, a planning permission which otherwise would lapse under subsection (1) or (2) lapses at the end of the extended period, unless, before the end of the extended period, the development to which the permission relates is begun.
(3C)In subsection (3B)—
“emergency period” means the period F7... beginning with the date on which paragraph 9 of schedule 7 of the Coronavirus (Scotland) Act 2020 came into force [F8and ending at the end of [F930 September 2022]],
“extended period” means the period F10... beginning with [F11the date that paragraph came into force and ending at the end of [F1231 March 2023]].
(3D)The Scottish Ministers may, by regulations, amend the definition of “emergency period” or “extended period” in subsection (3C).
(3E)Regulations under subsection (3D) are subject to the negative procedure.]
(4)[F13This section applies to every planning permission with the exception of]—
(a)any planning permission granted by a development order,
(b)any planning permission for any development carried out before the grant of planning permission,
F14(c). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F14(ca). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(d)any planning permission for development consisting of the winning and working of minerals or involving the depositing of mineral waste which is granted (or deemed to be granted) subject to a condition that the development to which it relates must be begun before the expiration of a specified period after—
(i)the completion of other development consisting of the winning and working of minerals already being carried out by the applicant for the planning permission, or
(ii)the cessation of depositing of mineral waste already being carried out by the applicant for the planning permission,
(e)any planning permission granted by an enterprise zone scheme,
(f)any planning permission granted by a simplified planning zone scheme, or
(g)any [F15planning permission in principle], within the meaning of section 59.
Textual Amendments
F1S. 58 heading substituted (12.12.2008 for specified purposes, 3.8.2009 in so far as not already in force) by Planning etc. (Scotland) Act 2006 (asp 17), ss. 20(2), 59(2) (with S.S.I. 2009/222, art. 10(2)(b)); S.S.I. 2008/411, art. 2(2)(3)(a), S.S.I. 2009/219, art. 2, sch.
F2S. 58(1)-(3A) substituted for s. 58(1)-(3) (12.12.2008 for specified purposes, 3.8.2009 in so far as not already in force) by Planning etc. (Scotland) Act 2006 (asp 17), ss. 20(1)(a), 59(2) (as amended (2.8.2009) by S.S.I. 2009/256, arts. 1(2), 5(2)) (with S.S.I. 2009/222, art. 10(2)(b)); S.S.I. 2008/411, art. 2(2)(3)(a), S.S.I. 2009/219, art. 2, sch.
F3S. 58(1)-(3) substituted (1.10.2022) by Planning (Scotland) Act 2019 (asp 13), ss. 32(3)(a), 63(2); S.S.I. 2022/275, reg. 2(2)(b) (with reg. 3)
F4Word in s. 58(3A) substituted (1.10.2022) by Planning (Scotland) Act 2019 (asp 13), ss. 32(3)(b)(i), 63(2); S.S.I. 2022/275, reg. 2(2)(b) (with reg. 3)
F5S. 58(3A)(a) substituted (1.10.2022) by Planning (Scotland) Act 2019 (asp 13), ss. 32(3)(b)(ii), 63(2); S.S.I. 2022/275, reg. 2(2)(b) (with reg. 3)
F6S. 58(3B)-(3E) inserted (temp.) (7.4.2020) by virtue of Coronavirus (Scotland) Act 2020 (asp 7), s. 17(1), sch. 7 para. 9 (with ss. 11-13)
F7Words in s. 58(3C) omitted (5.10.2020) by virtue of The Town and Country Planning (Emergency Period and Extended Period) (Coronavirus) (Scotland) Regulations 2020 (S.S.I. 2020/254), regs. 1(1), 2(1)(a)
F8Words in s. 58(3C) inserted (5.10.2020) by The Town and Country Planning (Emergency Period and Extended Period) (Coronavirus) (Scotland) Regulations 2020 (S.S.I. 2020/254), regs. 1(1), 2(1)(b)
F9Words in s. 58(3C) substituted (30.3.2022) by The Town and Country Planning (Miscellaneous Temporary Modifications) (Coronavirus) (Scotland) Regulations 2022 (S.S.I. 2022/66), regs. 1(1), 2(1) (with reg. 4(2))
F10Words in s. 58(3C) omitted (5.10.2020) by virtue of The Town and Country Planning (Emergency Period and Extended Period) (Coronavirus) (Scotland) Regulations 2020 (S.S.I. 2020/254), regs. 1(1), 3(1)(a)
F11Words in s. 58(3C) substituted (5.10.2020) by The Town and Country Planning (Emergency Period and Extended Period) (Coronavirus) (Scotland) Regulations 2020 (S.S.I. 2020/254), regs. 1(1), 3(1)(b)
F12Words in s. 58(3C) substituted (30.3.2022) by The Town and Country Planning (Miscellaneous Temporary Modifications) (Coronavirus) (Scotland) Regulations 2022 (S.S.I. 2022/66), regs. 1(1), 3(1) (with reg. 4(2))
F13Words in s. 58(4) substituted (12.12.2008 for specified purposes, 3.8.2009 in so far as not already in force) by Planning etc. (Scotland) Act 2006 (asp 17), ss. 20(1)(b)(i), 59(2) (with S.S.I. 2009/222, art. 10(2)(b)); S.S.I. 2008/411, art. 2(2)(3)(a), S.S.I. 2009/219, art. 2, sch.
F14S. 58(4)(c)(ca) repealed (1.10.2022) by Planning (Scotland) Act 2019 (asp 13), ss. 32(3)(c), 63(2); S.S.I. 2022/275, reg. 2(2)(b) (with reg. 3)
F15Words in s. 58(4)(g) substituted (12.12.2008 for specified purposes, 3.8.2009 in so far as not already in force) by Planning etc. (Scotland) Act 2006 (asp 17), ss. 20(1)(b)(iii), 59(2) (with S.S.I. 2009/222, art. 10(2)(b)); S.S.I. 2008/411, art. 2(2)(3)(a), S.S.I. 2009/219, art. 2, sch.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: