PART 3 acquisition and possession of land
SCHEDULES
LAND COMPRISING OPEN SPACE EXCLUDED FROM COMPULSORY ACQUISITION
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
3.(1) The 1965 Act shall have effect with the modifications...
4.For section 7 of the 1965 Act (measure of compensation)...
6.The following provisions of the 1965 Act (which state the...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
PART 2 protection of the environment agency
4.No dredging operations shall take place for the excavation of...
5.(1) Before beginning to construct any specified work, the undertaker...
6.Without prejudice to the generality of paragraph 5, the requirements...
7.(1) Subject to sub-paragraph (2), any specified work, and all...
8.(1) Before commencing the construction of a specified work the...
10.(1) The undertaker shall take all such measures as may...
11.The undertaker shall indemnify the Agency in respect of all...
12.(1) Without prejudice to the other provisions of this Part...
15.Any dispute arising between the undertaker and the Agency under...
PART 3 protection of the port of tyne authority
16.The provisions of this Part of this Schedule shall, unless...
17.The undertaker may with the written consent of the Port...
20.The undertaker shall allow the authorised representatives of the Port...
21.Nothing in this Order shall authorise or empower the undertaker...
22.Except so far as may be unavoidable in the construction...
23.The undertaker shall not, except for the purpose of constructing...
24.From the time when the construction of the tidal works...
25.(a) The undertaker shall consult with the Port Authority as...
26.The undertaker shall, at or near every tidal work exhibit...
28.Subject to paragraph 40 and to complying with paragraph 41,...
29.Nothing in this Order authorises the doing of anything prohibited...
30.The Port Authority shall not be liable, in the absence...
31.After the purpose of any temporary tidal work has been...
33.Should any such accumulation or erosion as is mentioned in...
35.In the event it is established that any accumulation or...
36.For the purposes of paragraph 32 the date of completion...
37.The undertaker shall— (a) pay to the Port Authority the...
38.Nothing in this Part of this Schedule shall impose any...
39.The Port Authority shall give to the undertaker notice of...
43.Unless otherwise agreed in writing, any difference which may arise...
44.In this Part of this Schedule— “accumulation” means any accumulation...
49.(1) The provisions of this Part of this Schedule shall,...
50.(1) The undertaker shall not exercise the powers conferred by...
51.(1) The undertaker shall, before commencing construction of any specified...
52.(1) Any specified work and any protective work specified pursuant...
53.The undertaker shall— (a) at all reasonable times afford reasonable...
54.Nexus shall at all times afford reasonable facilities to the...
55.(1) If any alterations or additions, either permanent or temporary,...
56.The undertaker shall repay to Nexus all reasonable fees, costs,...
58.(1) The undertaker shall pay to Nexus all reasonable costs,...
60.The undertaker and Nexus may enter into, and carry into...
PART 8 protection for sewerage and water undertakers
87.In this Part of this Schedule— “alteration” includes the provision...
Revision of toll levels between appointed day and the concession toll date
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: