Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Conditions of approvalU.K.

This section has no associated Explanatory Memorandum

57.  Approval of a scheme will be subject to the following conditions—

(a)that the operator of that scheme [F1must] comply with his obligations under Part 4;

(b)that where the operator of that scheme collects WEEE from a designated collection facility he [F1must] comply with the code of practice;

(c)that the operator of that scheme [F1must] provide any information reasonably requested by the appropriate authority with regard to the obligations referred to in paragraph (a);

F2(d). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(e)that the operator of that scheme [F1must] inform the appropriate authority in writing, either in hardcopy, by email or online of—

(i)any change in the person who is the operator of the scheme and, in the case where the operator of the scheme is a partnership, any change of partners,

(ii)any material change in—

(aa)the information provided in accordance with regulation 26 or 27;

(bb)the information provided in accordance with regulation 55(4)(b)(i);

(cc)the constitution submitted in accordance with regulation 55(4)(b)(ii), or

(iii)a conviction of the operator of that scheme for an offence under these Regulations, within 28 days of their conviction,

(f)that—

(i)where the appropriate authority is the Environment Agency, the Natural Resources Body for Wales or SEPA, the operator of that scheme, pays the annual producer charge specified in regulation 59(2) to the appropriate authority on receipt of an invoice for such a charge issued by that appropriate authority under regulation 79(3), and

(ii)where the appropriate authority is the [F3Department of Agriculture, Environment and Rural Affairs], the operator of that scheme pays the annual producer charge specified in [F4The Waste Electrical and Electronic Equipment (Charges) Regulations (Northern Ireland) 2014] on receipt of an invoice for such a charge issued by that appropriate authority under regulation 79(3);

(g)that the operator of that scheme will provide records and reports to the appropriate authority in compliance with—

(i)regulations 35 and 37 during the transitional period; or

(ii)from 1st January 2019 regulations 36 and 38;

(h)that the operator of that scheme will accept WEEE from private households free of charge from—

(i)a distributor in accordance with regulation 43, and

(ii)a final holder in accordance with regulation 52; and

(i)that the operator of that scheme continues to meet the requirements for approval of a scheme set out in Part 3 of Schedule 10.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources