The Electricity Capacity Regulations 2014

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Section 4

 Help about opening options

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Electricity Capacity Regulations 2014. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Regulation 4:

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

“Generating CMU”E+W+S

This section has no associated Explanatory Memorandum

4.—(1) A “generating CMU” is—

(a)an existing generating unit which meets the conditions in paragraph (2);

(b)a prospective generating unit which, when commissioned, will meet the conditions in paragraph (2);

(c)a combination of two or more existing generating units which meet the conditions in paragraph (3); or

(d)a combination of two or more prospective generating units which, when all of the generating units have been commissioned, will meet the conditions in paragraph (3).

(2) The conditions referred to in paragraph (1)(a) and (b) are that—

(a)the generating unit provides electricity;

(b)the generating unit is capable of being controlled independently from any other generating unit;

(c)the net output of the generating unit is measured by one or more half hourly meters in accordance with capacity market rules; and

(d)the generating unit has a connection capacity not less than the minimum capacity threshold.

(3) The conditions referred to in paragraph (1)(c) and (d) are that—

(a)the generating units meet at least one of Conditions 1 to 4 in paragraph (4);

(b)the generating units are all of the same type F1...;

[F2(ba)subject to paragraph (4A), the generating units are all owned by the same person;]

(c)subject to paragraph (5), each generating unit is capable of being controlled independently from any other generating unit not forming part of the generating CMU;

(d)the net output of all the generating units is measured by one or more half hourly meters in accordance with capacity market rules; and

(e)the aggregate connection capacity of all the generating units is not less than the minimum capacity threshold.

(4) For the purposes of paragraph (3)(a)—

(a)Condition 1 is that the generating units all form part of a single registered trading unit;

(b)Condition 2 is that—

(i)the generating units are all connected to the total system at the same boundary point; and

(ii)none of the generating units form part of a registered trading unit;

(c)Condition 3 is that—

(i)the generating units have an aggregate connection capacity not exceeding 50 MW; and

(ii)none of the generating units form part of a registered trading unit;

(d)Condition 4 is that—

(i)the generating units are all hydro generating units which are registered as a single BM unit under the Balancing and Settlement Code; and

(ii)there are not more than 10 such generating units.

[F3(4A) The condition in paragraph (3)(ba) does not apply where the aggregate connection capacity of all the generating units is less than 50 MW.]

(5) The condition in paragraph (3)(c) does not apply where the generating units meet Condition 4 in paragraph (4).

(6) In paragraph (1)(b) and (d), references to a prospective generating unit being commissioned are to be treated, in the case of a unit falling within paragraph (b) of the definition of “prospective generating unit” in paragraph (8), as references to the unit being recommissioned following an improvements programme.

(7) For the purposes of paragraph (3)(b), generating units are of the same type if—

(a)they are all CMRS distribution units;

(b)they are all non-CMRS distribution units; or

(c)they are all transmission units.

(8) In this regulation—

boundary point” means any point at which any plant or apparatus not forming part of the total system is connected to the total system;

CMRS distribution unit” means a generating unit which exports electricity to a distribution network, where the metering system of that generating unit is registered in the central meter registration service;

existing generating unit” means a generating unit that has been commissioned;

hydro generating unit” means a generating unit driven by water, other than one driven by tidal flows, waves, ocean currents or geothermal sources;

non-CMRS distribution unit” means a generating unit which exports electricity to a distribution network, which is not a CMRS distribution unit;

prospective generating unit” means a generating unit or proposed generating unit that—

(a)

has not been commissioned; or

(b)

is to be subject to an improvements programme and has not been recommissioned following that improvements programme;

registered trading unit” means a trading unit, other than a base trading unit [F4or sole trading unit], registered in accordance with the Balancing and Settlement Code; and

transmission unit” means a generating unit which exports electricity to the GB transmission system.

(9) In this regulation the following expressions have the same meanings as in the Balancing and Settlement Code as it was in force on [F58th September 2014]

  • “base trading unit”;

  • “BM unit”;

  • “central meter registration service”;

  • “metering system”; F6...

  • [F7“sole trading unit”;]

  • “trading unit”.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources