  1. Introductory Text

  2. PART 1

    1. 1.Citation and commencement

    2. 2.Interpretation

    3. 3.Electronic communications

  3. PART 2

    1. 4.Development consent granted by this Order

    2. 5.Limits of deviation

    3. 6.Authorisation of the operation of the authorised development

    4. 7.Power to maintain the authorised development

    5. 8.Transfer of the benefit of this Order

  4. PART 3

    1. 9.Street works

    2. 10.Access to works

    3. 11.Agreements with street authorities

    4. 12.Discharge of water

    5. 13.Authority to survey and investigate the land

    6. 14.Felling or lopping of trees

    7. 15.Rights under or over streets

    8. 16.Statutory undertakers

    9. 17.Recovery of costs of new connections

  5. PART 4

    1. 18.Defence to proceedings in respect of statutory nuisance constituted by noise emitted from premises

    2. 19.Procedures for approvals etc. required by the requirements

    3. 20.Removal of human remains

    4. 21.Application of landlord and tenant law

    5. 22.Operational land for the purposes of the Town and Country Planning Act 1990

    6. 23.Certification of documents

    7. 24.Arbitration

  6. Signature

    1. SCHEDULE 1

      AUTHORISED DEVELOPMENT

      1. Nationally significant infrastructure project

      2. Associated development

    2. SCHEDULE 2

      REQUIREMENTS

      1. 1.Commencement of the authorised development

      2. 2.Commercial use

      3. 3.Fuel type

      4. 4.Detailed design

      5. 5.Design of fuel storage bunker

      6. 6.Pre-development groundwater table level survey

      7. 7.Provision of landscaping

      8. 8.Implementation and maintenance of landscaping

      9. 9.External lighting

      10. 10.Highway accesses

      11. 11.Fencing – A1(M)

      12. 12.Fencing and other means of enclosure

      13. 13.Surface and foul water drainage

      14. 14.Flood risk mitigation

      15. 15.Contaminated land and groundwater

      16. 16.Archaeology

      17. 17.Biodiversity enhancement and management plan

      18. 18.Construction environmental management plan

      19. 19.Construction traffic routing and management plan

      20. 20.Construction hours

      21. 21.Piling and penetrative foundation design

      22. 22.Construction – A1(M)

      23. 23.Control of noise during construction

      24. 24.Control of operational noise

      25. 25.Control of odour emissions

      26. 26.Control of dust emissions

      27. 27.Control of smoke emissions

      28. 28.Control of steam emissions

      29. 29.Control of insects and vermin

      30. 30.Accumulations and deposits

      31. 31.Restoration of land used temporarily for construction

      32. 32.Operational traffic routing and management plan

      33. 33.Travel plan – operational staff

      34. 34.Operational deliveries

      35. 35.Sustainable fuel transport management plan

      36. 36.Enclosure of loads

      37. 37.Air quality – emissions reduction

      38. 38.Air quality monitoring

      39. 39.Fire prevention

      40. 40.Combined heat and power (“CHP”)

      41. 41.Waste hierarchy scheme

      42. 42.Waste management – construction and operational waste

      43. 43.Decommissioning

      44. 44.Aviation warning lighting

      45. 45.Air safety

      46. 46.Site security

      47. 47.Local liaison committee

      48. 48.Employment, skills and training plan

      49. 49.Interpretation

    3. SCHEDULE 3

      MAXIMUM BUILDING DIMENSIONS

    4. SCHEDULE 4

      MINIMUM BUILDING DIMENSIONS

    5. SCHEDULE 5

      STREETS SUBJECT TO STREET WORKS

    6. SCHEDULE 6

      ACCESS TO WORKS

    7. SCHEDULE 7

      PROCEDURES FOR APPROVALS ETC. REQUIRED BY THE REQUIREMENTS

      1. 1.Application of this Schedule

      2. 2.Decision period

      3. 3.Further information

      4. 4.Fees

      5. 5.Appeal to the Secretary of State (procedure)

      6. 6.Appeal to the Secretary of State (powers of the appointed person)

      7. 7.Appeal to the Secretary of State (supplementary)

  7. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources