Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
3.—(1) Subject to the provisions of this Order and [F1regulations 75 to 78 of the Conservation of Habitats and Species Regulations 2017] (general development orders), planning permission is hereby granted for the classes of development described as permitted development in Schedule 2.
(2) Any permission granted by paragraph (1) is subject to any relevant exception, limitation or condition specified in Schedule 2.
(3) References in this Order to permission granted by Schedule 2 or by any Part, Class or paragraph of that Schedule are references to the permission granted by this article in relation to development described in that Schedule or that provision of that Schedule.
(4) Nothing in this Order permits development contrary to any condition imposed by any planning permission granted or deemed to be granted under Part 3 of the Act otherwise than by this Order.
(5) The permission granted by Schedule 2 does not apply if—
(a)in the case of permission granted in connection with an existing building, the building operations involved in the construction of that building are unlawful;
(b)in the case of permission granted in connection with an existing use, that use is unlawful.
(6) The permission granted by Schedule 2 does not, except in relation to development permitted by Classes A, B, D and E of Part 9 and Class A of Part 18 of that Schedule, authorise any development which requires or involves the formation, laying out or material widening of a means of access to an existing highway which is a trunk road or classified road, or creates an obstruction to the view of persons using any highway used by vehicular traffic, so as to be likely to cause danger to such persons.
(7) Any development falling within Class A of Part 18 of Schedule 2 authorised by an Act or order subject to the grant of any consent or approval is not to be treated for the purposes of this Order as authorised unless and until that consent or approval is obtained, except where the Act was passed or the order made after 1st July 1948 and it contains provision to the contrary.
(8) Schedule 2 does not grant permission for the laying or construction of a notifiable pipe-line, except in the case of the laying or construction of a notifiable pipe-line by a gas transporter in accordance with Class A of Part 15 of that Schedule.
(9) Except as provided in Classes B and C of Part 11, Schedule 2 does not permit any development which requires or involves the demolition of a building, but in this paragraph “building” does not include part of a building.
[F2(9A) Schedule 2 does not grant permission for, or authorise any development of, any new dwellinghouse—
(a)where the gross internal floor area is less than 37 square metres in size; or
(b)that does not comply with the nationally described space standard issued by the Department for Communities and Local Government on 27th March 2015.
(9B) The reference in paragraph (9A) to the nationally described space standard is to that standard read together with the notes dated 19th May 2016 which apply to it.]
(10) Subject to paragraph (12), Schedule 1 development or Schedule 2 development within the meaning of [F3the Town and Country Planning (Environmental Impact Assessment) Regulations 2017] (“the EIA Regulations”) is not permitted by this Order unless—
(a)the local planning authority has adopted a screening opinion under [F4regulation 6] of those Regulations that the development is not EIA development [F5within the meaning of those Regulations];
(b)the Secretary of State has made a screening direction under [F6regulation 5(3)] of those Regulations that the development is not EIA development [F5within the meaning of those Regulations]; or
(c)the Secretary of State has given a direction under [F7regulation 63(1)] of those Regulations that the development is exempted from the application of those Regulations.
(11) Where—
(a)the local planning authority has adopted a screening opinion under [F8regulation 6] of the EIA Regulations that development is EIA development [F9within the meaning of those Regulations] and the Secretary of State has in relation to that development neither made a screening direction to the contrary under [F10regulation 5(3)] of those Regulations nor directed under [F11regulation 63(1)] of those Regulations that the development is exempted from the application of those Regulations; or
(b)the Secretary of State has directed that development is EIA development [F12within the meaning of those Regulations],
that development is treated, for the purposes of paragraph (10), as development which is not permitted by this Order.
(12) Paragraph (10) does not apply to—
(a)development which consists of the carrying out by a drainage body, within the meaning of the Land Drainage Act 1991 M1, of improvement works within the meaning of the Environmental Impact Assessment (Land Drainage Improvement Works) Regulations 1999 M2;
(b)development for which permission is granted by Class E of Part 6, Class K of Part 7, Class B of Part 12, Class A(a) of Part 15, Class D, E or I of Part 17 or Class A of Part 18 of Schedule 2;
(c)development for which permission is granted by Class F, H or K of Part 17 of Schedule 2 where the land in, on or under which the development is to be carried out is—
(i)in the case of Class F of Part 17, on the same authorised site,
(ii)in the case of Class H of Part 17, on the same premises or, as the case may be, the same ancillary mining land,
(iii)in the case of Class K of Part 17, on the same land or, as the case may be, on land adjoining that land,
as that in, on or under which development of any description permitted by the same Class has been carried out before 14th March 1999;
(d)the completion of any development begun before 14th March 1999;
(e)development for which permission is granted by Class B of Part 9 of Schedule 2.
(13) Where a person uses electronic communications for making any application required to be made under any of Part of Schedule 2, that person is taken to have agreed—
(a)to the use of electronic communications for all purposes relating to that person's application which are capable of being effected using such communications;
(b)that the address for the purpose of such communications is the address incorporated into, or otherwise logically associated with, that person's application; and
(c)that the deemed agreement under this paragraph subsists until that person gives notice in writing revoking the agreement (and such revocation is final and takes effect on a date specified by the person but not less than 7 days after the date on which the notice is given).
Textual Amendments
F1Words in art. 3(1) substituted (30.11.2017) by The Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012), reg. 1(2), Sch. 6 para. 52
F2Art. 3(9A)(9B) inserted (6.4.2021) by The Town and Country Planning (General Permitted Development) (England) (Amendment) Regulations 2020 (S.I. 2020/1243), regs. 1(3), 3 (with reg. 12(1)(2))
F3Words in art. 3(10) substituted (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (S.I. 2017/571), regs. 1(1), 73(2)(a) (with regs. 47, 70)
F4Words in art. 3(10) substituted (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (S.I. 2017/571), regs. 1(1), 73(4)(a) (with regs. 47, 70)
F5Words in art. 3(10)(a)(b) inserted (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (S.I. 2017/571), regs. 1(1), 73(2)(b) (with regs. 47, 70)
F6Words in art. 3(10) substituted (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (S.I. 2017/571), regs. 1(1), 73(4)(b) (with regs. 47, 70)
F7Words in art. 3(10) substituted (1.10.2018) by The Town and Country Planning and Infrastructure Planning (Environmental Impact Assessment) (Amendment) Regulations 2018 (S.I. 2018/695), regs. 1, 4(2)
F8Words in art. 3(11) substituted (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (S.I. 2017/571), regs. 1(1), 73(4)(a) (with regs. 47, 70)
F9Words in art. 3(11)(a) inserted (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (S.I. 2017/571), regs. 1(1), 73(3) (with regs. 47, 70)
F10Words in art. 3(11)(a) substituted (1.10.2018) by The Town and Country Planning and Infrastructure Planning (Environmental Impact Assessment) (Amendment) Regulations 2018 (S.I. 2018/695), regs. 1, 4(3)
F11Words in art. 3(11) substituted (1.10.2018) by The Town and Country Planning and Infrastructure Planning (Environmental Impact Assessment) (Amendment) Regulations 2018 (S.I. 2018/695), regs. 1, 4(2)
F12Words in art. 3(11)(b) inserted (16.5.2017) by The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (S.I. 2017/571), regs. 1(1), 73(3) (with regs. 47, 70)
Modifications etc. (not altering text)
C1Art. 3 applied (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 9(4) (with arts. 35, 36)
C2Art. 3(10) excluded (23.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(1), Sch. 32 para. 1
C3Art. 3(10) excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 31 para. 1(1)
Marginal Citations
M11991 c. 59. See section 72 for the definition of “drainage body”, was amended by Schedule 22 to the Environment Act 1995 (c. 25); there is another amendment which is not relevant to this Order.
M2S.I. 1999/1783. See regulation 2 for the definition of “improvement works”; the definition was amended by S.I. 2005/1399. There are other amendments not relevant to this Order.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: