Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
42.—(1) The following applications for a section 36 or 37 consent or a section 36 variation must be dealt with under the 2000 Regulations as if they had not been revoked (and not under these Regulations)—
(a)an application received by a relevant authority before 16th May 2017 if an environmental statement (within the meaning of the 2000 Regulations) is also received by the relevant authority before that date;
(b)an application for development in respect of which the relevant authority receives a request for a scoping opinion under regulation 7 of the 2000 Regulations before 16th May 2017.
(2) Where a relevant authority receives a request for a screening opinion under regulation 5 of the 2000 Regulations before 16th May 2017, the request must be dealt with under those Regulations as if they had not been revoked.
(3) Where, before 16th May 2017, a relevant authority receives an application for a section 36 or 37 consent or a section 36 variation and the question of whether or not the application is for EIA development (within the meaning of the 2000 Regulations) falls to be determined under regulation 6 of those Regulations, that question must be determined under those Regulations as if they had not been revoked.
(4) Where a relevant authority receives a request for a scoping opinion under regulation 7 of the 2000 Regulations before 16th May 2017, the request must be dealt with under those Regulations as if they had not been revoked.
[F1(4A) For the purposes of this regulation, the 2000 Regulations must be treated as if, immediately before being revoked, they had been amended as follows—
(a)in regulations 4(2)(b) and 12(1)(i) and in the heading of regulation 12, omit “other”;
(b)in regulation 9(2)(a) and both places it occurs in regulation 12(1), for “another EEA State” substitute “an EEA State”;
(c)in regulation 12(3), for “referred to in Article 6(1) of Council Directive 85/337/EEC” substitute “designated by the EEA State concerned to be consulted about the project”;
(d)in Schedule 3—
(i)in paragraph 2(c)(v), for “EEA States’ legislation” substitute “domestic legislation or legislation of EEA States;”;
(ii)in paragraph 2(c)(vi), for the words after “designated by” to the end substitute “national legislation or Natura 2000 as defined in regulation 3(1) of the Conservation of Habitats and Species Regulations 2017;”;
(iii)in paragraph 2(c)(vii), for “legislation of the European Union” substitute “retained EU law”]
(5) For the purposes of these Regulations, a determination under regulation 5 or 6 of the 2000 Regulations that an application for a section 36 or 37 consent, or a section 36 variation, is for EIA development (within the meaning of the 2000 Regulations) must be treated as a screening decision under these Regulations that the application is for EIA development (within the meaning of these Regulations).
(6) In this regulation, “2000 Regulations” means the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2000.
(7) This regulation is subject to—
(a)regulation 38 (exemptions for defence and civil emergencies);
(b)regulation 39 (exemptions where EIA development requires marine licence, etc. for which environmental impact assessment is also required).
Textual Amendments
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: