Search Legislation

The Network Rail (Kings Mill No. 1 Level Crossing) (Land Acquisition and Closure) Order 2018

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Cranes

10.—(1) Network Rail may enter upon and use airspace above the surface of land specified in paragraph (8) for the oversailing of cranes used by Network Rail in connection with the development or the creation of the new public right of way.

(2) The power under paragraph (1) is exercisable on giving at least 7 days’ notice to the owners and occupiers of the land.

(3) Network Rail may not, without the agreement of the owners of the land, use airspace above the surface of the land as mentioned in paragraph (1) after the end of 7 days beginning with the date of completion of the activities for which the crane has been used.

(4) Network Rail must pay compensation to the owners and occupiers of land above which the power under paragraph (1) is exercised for any loss which they may suffer by reason of the exercise of that power.

(5) Any dispute as to a person’s entitlement to compensation under paragraph (4), or as to the amount of compensation, must be determined under and in accordance with Part 1 of the 1961 Act.

(6) Nothing in this article affects any liability to pay compensation under section 10(2) of the 1965 Act (as applied by article 6(1) to the acquisition of land under article 5(1)) or under any other enactment, otherwise than for loss for which compensation is payable under paragraph (4).

(7) The powers of compulsory acquisition of land conferred by this Order do not apply in relation to the land referred to in paragraph (1) except that Network Rail is not precluded from—

(a)acquiring new rights over any part of that land under article 8 (power to acquire new rights); or

(b)the temporary use of land under article 9 (temporary use of land in connection with the development).

(8) This is the land referred to in paragraph (1)—

AreaNumber of land shown on the deposited plan

County of Nottinghamshire

District of Ashfield

7, 11 to 17 and 22

County of Nottinghamshire

Districts of Mansfield and Ashfield

1 to 4 and 10

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources