- Latest available (Revised)
- Original (As made)
There are currently no known outstanding effects for the The Millbrook Gas Fired Generating Station Order 2019, SCHEDULE 4.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Article 9
Commencement Information
I1Sch. 4 in force at 3.4.2019, see art. 1
(1)Area | (2)Street Subject to Street Works | (3)Description of the street works |
---|---|---|
Central Bedfordshire Council | Green Lane | Works to enable the creation of an access and to place and maintain apparatus (comprising numbered work 2A) for use during construction and operation between the points marked A and B and C and D on the rights of way, streets and access plan. |
Bedford Borough Council | Green Lane | Works to enable the creation of an access and to place and maintain apparatus (comprising numbered work 2A) for use during construction and operation between the points marked A and B on the rights of way, streets and access plan. |
Central Bedfordshire Council | Access Road serving Rookery North and South Pits | Works to enable the creation of an access and to place and maintain apparatus (comprising numbered work 2A) for use during construction and operation between the points marked E and F on the rights of way, streets and access plan. |
Central Bedfordshire Council | Access Road serving Rookery North and South Pits | Works to maintain the existing access and to place and maintain apparatus (comprising numbered work 2A) for use during construction and operation between the points marked F and G on the rights of way, streets and access plan. |
Central Bedfordshire Council | Established agricultural access tracks between South Pillinge Farm and Rookery South Pit | Works for numbered work 5 to be installed in the street between the points marked J and K on the rights of way, streets and access plan. |
Central Bedfordshire Council | Established agricultural access tracks between South Pillinge Farm and Rookery South Pits | Works for numbered work 5 to be installed in the street between the points marked L and M on the rights of way, streets and access plan. |
Central Bedfordshire Council | Public Footpath 65 | Works for numbered work 4A to be installed in the street between the points marked O and P on the rights of way, streets and access plan. |
Central Bedfordshire Council | Houghton Lane | Works for numbered work 4A to be installed under the street between the points marked GG and HH on the rights of way, streets and access plan. |
Central Bedfordshire Council | Public Footpath 7 | Works for numbered work 4A to be installed in the street between the points marked JJ and KK on the rights of way, streets and access plan. |
Central Bedfordshire Council | Access track leading from Houghton Lane to Park Farm | Works to upgrade the existing access (comprising numbered work 3B) and to place and maintain apparatus for use during construction and operation and works for numbered work 4A to be installed in the street between the points marked MM and NN on the rights of way, streets and access plan. |
Central Bedfordshire Council | Houghton Lane | Works to upgrade the existing junction (comprising numbered work 3B) for use during construction and operation between the points marked OO and PP on the rights of way, streets and access plan. |
Central Bedfordshire Council | Access track leading from Houghton Lane to Park Farm | Works to enable the creation of an access (comprising numbered work 3B) for use during operation between the points marked QQ and RR on the rights of way, streets and access plan. |
Central Bedfordshire Council | Access track leading from Houghton Lane to Park Farm | Works to enable the creation of an access (comprising numbered work 3B) for use during construction between the points marked RR and NN on the rights of way, streets and access plan. |
Central Bedfordshire Council | low level restoration scheme secondary access track | Works for numbered work 4A to be installed in the street between the points marked BB and CC on the rights of way, streets and access plan. |
Central Bedfordshire Council | low level restoration scheme secondary access track | Works for numbered work 4A to be installed in the street between the points marked CC and DD on the rights of way, streets and access plan. |
Central Bedfordshire Council | low level restoration scheme secondary access track | Works to enable the creation of an access (comprising part of numbered work 6) within the area shown on the rights of way, streets and access plan with orange hatching to provide permanent accesses to numbered work 6(a). |
Central Bedfordshire Council | Houghton Lane | Works to enable the creation of an access (comprising part of numbered work 4A) for use during construction between the points marked GG and HH on the rights of way, streets and access plan. |
Central Bedfordshire Council | Station Lane | Works to enable the creation of an access (comprising part of numbered work 6) between the points marked SS and TT on the rights of way, streets and access plan to provide permanent accesses to numbered work 6(a).] |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: