2.Amendment to the Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019
3.Amendments to the Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019
Amendments to Commission Regulation (EU) 2016/631
1.In Article 1 (subject matter)— (a) in the first paragraph—...
3.(1) Article 3 (scope of application) is amended as follows....
4.(1) Article 4 (application to existing power-generating modules) is amended...
5.(1) Article 5 (determination of significance) is amended as follows....
6.In Article 6 (application to power-generating modules etc.), in paragraph...
9.(1) Article 9 (recovery of costs) is amended as follows....
10.(1) Article 10 (public consultation) is amended as follows.
12.(1) Article 12 (confidentiality obligations) is amended as follows.
13.(1) Article 13 (general requirements for type A power-generating modules)...
14.(1) Article 14 (general requirements for type B power-generating modules)...
15.(1) Article 15 (general requirements for type C power-generating modules)...
16.(1) Article 16 (general requirements for type D power-generating modules)...
17.In Article 18 (requirements for type C synchronous power-generating modules),...
18.In Article 21 (requirements for type C power park modules)...
19.(1) Article 25 (voltage stability requirements applicable to AC-connected offshore...
20.In Article 30 (operational notification of type A power-generating modules),...
21.(1) Article 32 (procedure for type B and C power-generating...
22.(1) Article 38 (identification of costs and benefits of application...
23.In Article 39 (principles of cost-benefit analysis), in paragraph 2,...
24.In Article 40 (responsibility of the power-generating facility owner), in...
25.In Article 43 (common provisions on compliance simulation), in paragraph...
27.In Article 53 (compliance simulations for type D synchronous power-generating...
29.(1) Article 60 (power to grant derogations) is amended as...
30.(1) Article 61 (general provisions) is amended as follows.
31.In Article 62 (request for a derogation by a power-generating...
32.(1) Article 63 (request for a derogation by a relevant...
33.In Article 64 (register of derogations from the requirements of...
35.In Article 66 (emerging technologies), in paragraph 2, in point...
36.(1) Article 67 (establishment of thresholds for classification as emerging...
38.(1) Article 69 (assessment and approval of requests for classification...
39.(1) Article 70 (withdrawal of classification as an emerging technology)...
40.(1) Article 71 (amendment of contracts and general terms and...
41.In the text after Article 72, omit “This Regulation shall...
Amendments to Commission Regulation (EU) 2016/1388
2.(1) Article 3 (scope of application) is amended as follows....
3.(1) Article 4 (application to existing transmission-connected demand facilities etc.)...
6.(1) Article 8 (recovery of costs) is amended as follows....
7.(1) Article 9 (public consultation) is amended as follows.
8.(1) Article 11 (confidentiality obligations) is amended as follows.
9.In Article 13 (general voltage requirements), omit paragraphs 4 and...
10.(1) Article 15 (reactive power requirements) is amended as follows....
11.In Article 19 (demand disconnection and demand reconnection), in paragraph...
12.In Article 29 (specific provisions for demand units with demand...
13.In Article 42 (common provisions on compliance simulations), in paragraph...
14.(1) Article 48 (cost-benefit analysis) is amended as follows.
15.In Article 49 (principles of cost-benefit analysis), in paragraph 2,...
17.(1) Article 51 (general provisions) is amended as follows.
19.(1) Article 53 (request for a derogation by a relevant...
20.In Article 54 (register of derogations from the requirements of...
23.(1) Article 58 (amendment of contracts and general terms and...
24.In the text after Article 59, omit “This Regulation shall...
Amendments to Commission Regulation (EU) 2016/1447
1.In Article 1 (subject matter)— (a) for “the internal electricity...
2.In Article 2 (definitions)— (a) for “Regulation (EC) No 714/2009”...
3.(1) Article 3 (scope of application) is amended as follows....
4.(1) Article 4 (application to existing HVDC systems and DC-connected...
6.(1) Article 7 (recovery of costs) is amended as follows....
7.(1) Article 8 (public consultation) is amended as follows.
9.(1) Article 10 (confidentiality obligations) is amended as follows.
10.In Article 12 (rate-of-change-of-frequency withstand capability), for “2,5” (in both...
11.In Article 13 (active power controllability, control range and ramping...
13.In Article 20 (reactive power capability), in paragraph 2, in...
14.In Article 22 (reactive power control mode), in paragraph 3,...
15.In Article 29 (interaction between HVDC systems or other plants...
16.In Article 31 (subsynchronous torsional interaction damping capability), in paragraph...
17.In Article 39 (frequency stability requirements), in paragraph 1, in...
18.In Article 40 (reactive power and voltage requirements), in paragraph...
20.In Article 62 (ION for DC-connected power park modules), in...
21.(1) Article 65 (identification of costs and benefits of application...
22.In Article 66 (principles of cost-benefit analysis), in paragraph 2,...
23.In Article 68 (common provisions on compliance simulation), in paragraph...
24.In Article 71 (compliance testing for HVDC systems), in paragraph...
25.In Article 72 (compliance testing for DC-connected power park modules...
27.(1) Article 77 (power to grant derogations) is amended as...
28.(1) Article 78 (general provisions) is amended as follows.
29.(1) Article 79 (request for derogations by an HVDC system...
30.(1) Article 80 (request for a derogation by a relevant...
31.In Article 82 (register of derogations from the requirements of...
32.(1) Article 84 (amendment of contracts and general terms and...
33.In Article 85 (HVDC System or DC-connected power park modules...
34.In the text after Article 86, omit “This Regulation shall...
Amendments to Regulation (EU) 2019/943
2.For Article 2 (definitions) substitute— Article 2 Definitions In this...
3.(1) Article 3 (principles regarding the operation of electricity markets)...
5.(1) Article 5 (balance responsibility) is amended as follows.
7.(1) Article 7 (day-ahead and intraday markets) is amended as...
8.(1) Article 8 (trade on day-ahead and intraday markets) is...
10.(1) Article 10 (technical bidding limits) is amended as follows....
12.(1) Article 12 (dispatching of generation and demand response) is...
15.(1) Article 16 (general principles of capacity allocation and congestion...
17.(1) Article 18 (charges for access to networks, use of...
18.(1) Article 19 (congestion income) is amended as follows.
20.(1) Article 21 (general principles for capacity mechanisms) is amended...
21.(1) Article 22 (design principles for capacity mechanisms) is amended...
24.(1) Article 25 (reliability standard) is amended as follows.
26.(1) Article 50 (provision of information) is amended as follows....
29.For Article 60 substitute— Article 60 Amendments of network codes...
32.(1) Article 63 (new interconnectors) is amended as follows.
37.In the text after Article 71 omit “This Regulation shall...
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: