Consent to transfer benefit of the OrderE+W

9.—(1) Subject to paragraph (4) the undertaker may, with the consent of the Secretary of State—

(a)transfer to another person (“the transferee”) all or any part of the benefit of the provisions of this Order (including any part of the authorised development) and such related statutory rights as may be agreed in writing between the undertaker and the transferee; or

(b)grant to another person (“the lessee”), for a period agreed between the undertaker and the lessee, all or any part of the benefit of the provisions of this Order (including any part of the authorised development) and such related statutory rights as may be agreed between the undertaker and the lessee.

(2) Where an agreement has been made in accordance with paragraph (1)(a) or (1)(b) references in this Order to the undertaker, except paragraph (3), include references to the transferee or the lessee.

(3) The exercise by a person of any benefits or rights conferred in accordance with any transfer or grant under paragraph (1) is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by the undertaker.

(4) The consent of the Secretary of State is required for the exercise of the powers under paragraph (1) except where—

(a)the transfer or grant is made to Riverside Energy Park Limited [F1(and in circumstances where Riverside Energy Park Limited is a Cory group company)]; or

(b)the transferee or lessee holds a licence under section 6 (licences authorising supply, etc.) of the Electricity Act 1989; or

(c)the time limits for all claims for compensation in respect of the acquisition of land or effects upon land under this Order have elapsed and—

(i)no such claims have been made;

(ii)any such claims that have been made have all been compromised or withdrawn;

(iii)compensation has been paid in final settlement of any claims made;

(iv)payment of compensation into court in lieu of settlement of all such claims has take place; or

(v)it has been determined by a tribunal or court of competent jurisdiction in respect of all claims that no compensation is payable.

(5) Where the consent of the Secretary of State is not required under paragraph (4), the undertaker must notify the Secretary of State in writing before transferring or granting all or any part of the benefit of the provisions of this Order and such related statutory rights referred to in paragraph (1).

(6) The notification referred to in paragraph (5) must state—

(a)the name and contact details of the person to whom the benefit of the powers will be transferred or granted;

(b)subject to paragraph (7), the date on which the transfer will take effect;

(c)the powers to be transferred or granted;

(d)pursuant to paragraph (3), the restrictions, liabilities and obligations that will apply to the person exercising the powers transferred or granted; and

(e)where relevant, a plan showing the works or areas to which the transfer or grant relates.

(7) The date specified under paragraph (6)(b) must not be earlier than the expiry of five working days from the date of the receipt of the notice.

(8) The notice given under paragraph (5) must be signed by the undertaker and the person to whom the benefit of the powers will be transferred or granted as specified in that notice.

Textual Amendments

Commencement Information

I1Art. 9 in force at 1.5.2020, see art. 1

Back to top

Options/Help

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?