The A63 (Castle Street Improvement, Hull) Development Consent Order 2020

 Help about what version

What Version

 Help about opening options

Opening OptionsExpand opening options

Changes to legislation:

There are currently no known outstanding effects for the The A63 (Castle Street Improvement, Hull) Development Consent Order 2020. Help about Changes to Legislation

  1. Introductory Text

  2. Expand +/Collapse -

    PART 1 PRELIMINARY

    1. 1.Citation and commencement

    2. 2.Interpretation

  3. Expand +/Collapse -

    PART 2 PRINCIPAL POWERS

    1. 3.Development consent etc. granted by the Order

    2. 4.Maintenance of authorised development

    3. 5.Maintenance of drainage works

    4. 6.Limits of deviation

    5. 7.Benefit of Order

    6. 8.Consent to transfer benefit of Order

  4. Expand +/Collapse -

    PART 3 STREETS

    1. 9.Application of the 1991 Act

    2. 10.Construction and maintenance of new, altered or diverted streets and other structures

    3. 11.Classification of roads, etc.

    4. 12.Temporary stopping up and restriction of use of streets

    5. 13.Permanent stopping up and restriction of use of streets and private means of access

    6. 14.Access to works

    7. 15.Clearways

    8. 16.Traffic regulation

  5. Expand +/Collapse -

    PART 4 SUPPLEMENTAL POWERS

    1. 17.Discharge of water

    2. 18.Protective work to buildings

    3. 19.Authority to survey and investigate the land

  6. Expand +/Collapse -

    PART 5 POWERS OF ACQUISITION AND POSSESSION

    1. 20.Compulsory acquisition of land

    2. 21.Compulsory acquisition of land – incorporation of the mineral code

    3. 22.Time limit for exercise of authority to acquire land compulsorily

    4. 23.Compulsory acquisition of rights and restrictive covenants

    5. 24.Private rights over land

    6. 25.Modification of Part 1 of the 1965 Act

    7. 26.Application of the 1981 Act

    8. 27.Acquisition of subsoil or airspace only

    9. 28.Rights under or over streets

    10. 29.Temporary use of land for carrying out the authorised development

    11. 30.Temporary use of land for maintaining the authorised development

    12. 31.Statutory undertakers

    13. 32.Apparatus and rights of statutory undertakers in stopped up streets

    14. 33.Recovery of costs of new connections

    15. 34.Special category land

  7. Expand +/Collapse -

    PART 6 OPERATIONS

    1. 35.Felling or lopping of trees and removal of hedgerows

  8. Expand +/Collapse -

    PART 7 MISCELLANEOUS AND GENERAL

    1. 36.Removal of human remains

    2. 37.Application of landlord and tenant law

    3. 38.Operational land for purposes of the 1990 Act

    4. 39.Defence to proceedings in respect of statutory nuisance

    5. 40.Protection of interests

    6. 41.Certification of documents, etc.

    7. 42.Service of notices

    8. 43.Arbitration

    9. 44.Crown rights

  9. Signature

  10. SCHEDULES

    1. Expand +/Collapse -

      SCHEDULE 1

      AUTHORISED DEVELOPMENT

      1. A nationally significant infrastructure project as defined in sections 14...

      2. In the administration area of East Riding of Yorkshire

      3. Work No.1 — The construction of Livingstone Road materials compound...

      4. In the administration area of Kingston upon Hull

      5. Work No.2 — Eastbound vehicle recovery lay-by located on north...

      6. Work No.3 — The diversion of statutory undertakers' apparatus (BT)...

      7. Work No.4 — Improvement of access and land at Neptune...

      8. Work No.5 — The improvement and realignment of the existing...

      9. Work No.6 — The diversion of statutory undertakers' apparatus (BT)...

      10. Work No.7 — The construction of St James' Street turning...

      11. Work No.8 — The diversion of statutory undertakers' apparatus (KCOM)...

      12. Work No.9 — The demolition of the Arco premises and...

      13. Work No 10. — The diversion of statutory undertakers' apparatus...

      14. Work No.11. — The diversion of statutory undertakers' apparatus (BT...

      15. Work No.12 — The construction of a new bridge over...

      16. Work No.13 — The demolition of the existing Myton Centre,...

      17. Work No.14 — The construction of a new eastbound A63...

      18. Work No.15 — The construction of a new westbound A63...

      19. Work No.16 — The construction of a new access road...

      20. Work No.17 — The construction of a new turning head...

      21. Work No.18 — Not used.

      22. Work No.18A — Working room for construction.

      23. Work No.18B — Alterations to Kingston Retail Park Car Park....

      24. Work No.19 — The improvement of the existing dual carriageway...

      25. Work No.20 — The construction of a new eastbound A63...

      26. Work No.21 — Not used.

      27. Work No.22 — Replacing existing potable water main along the...

      28. Work No.23 — The diversion of statutory undertakers' apparatus (YW...

      29. Work No.24 — Trinity Burial Ground compound location, construction of...

      30. Work No.25 — Statutory undertakers (KCOM) diversion works along Myton...

      31. Work No.26 — Alterations to Holiday Inn car park, access,...

      32. Work No.27 — The construction of a new westbound A63...

      33. Work No.28 — Works to Trinity Burial Ground – archaeology,...

      34. Work No.29 — Construction of main office compound at Wellington...

      35. Work No.30 — Work to listed buildings – Castle buildings...

      36. Work No.31 — The construction of a new bridge over...

      37. Work No.32 — Offset archaeological investigation works at Princes Dock...

      38. Work No.33 — Minor improvement works to the existing Old...

      39. Work No.34 — Construction of turning head and improvements to...

      40. Work No.35 — The construction of a new westbound A63...

      41. Work No.36 — The construction of a new eastbound A63...

      42. Work No.37 — The improvement of Queen Street to the...

      43. Work No.38 — The improvement of Market Place to the...

      44. Work No.39 — The construction of a new eastbound A63...

      45. Work No.40 — The construction of a new westbound A63...

      46. Work No.41 — The improvement of Myton Bridge underpass on...

      47. Work No.42 — Westbound vehicle recovery lay-by located on south...

      48. Work No.43 — Not used.

      49. Work No.44 — Not used.

      50. Work No.45 — Not used.

      51. Work No.46 — Construction of a surface water rising main...

      52. In connection with the construction of any of those works,...

    2. Expand +/Collapse -

      SCHEDULE 2

      REQUIREMENTS

      1. Expand +/Collapse -

        PART 1 REQUIREMENTS

        1. 1.Interpretation

        2. 2.Time limits

        3. 3.Detailed design

        4. 4.Construction and handover environmental management plan

        5. 5.Landscaping

        6. 6.Contaminated land and groundwater

        7. 7.Protected species

        8. 8.Surface and foul water drainage

        9. 9.Archaeological remains

        10. 10.Traffic management

        11. 11.Amendments to approved details

        12. 12.Fencing and barriers

        13. 13.Pumping station

        14. 14.Earl de Grey public house

        15. 15.Replacement green space

        16. 16.Beverley Gate Scheduled Monument

        17. 17.High Street underpass works

      2. Expand +/Collapse -

        PART 2 PROCEDURE FOR DISCHARGE OF REQUIREMENTS

        1. 18.Applications made under requirements

        2. 19.Further information

        3. 20.Register of requirements

        4. 21.Anticipatory steps towards compliance with any requirement

    3. Expand +/Collapse -

      SCHEDULE 3

      CLASSIFICATION OF ROADS, ETC.

      1. PART 1 TRUNK ROADS

      2. PART 2 OTHER ROAD CLASSIFICATIONS

      3. PART 3 ROADS SUBJECT TO 30 MILES PER HOUR LIMIT

      4. PART 4 ROADS SUBJECT TO 40 MILES PER HOUR LIMIT

      5. PART 5 ROAD SUBJECT TO ONE WAY RESTRICTIONS

      6. PART 6 ROADS SUBJECT TO TWO WAY TRAFFIC

      7. PART 7 ROADS SUBJECT TO PROHIBITION OF PARKING – NO WAITING OR LOADING AT ANY TIME

      8. PART 8 CYCLE TRACKS AND FOOTWAYS

      9. PART 9 PRIVATE MEANS OF ACCESS

      10. PART 10 PUBLIC RIGHTS OF WAY

      11. PART 11 UNCONTROLLED CROSSING

    4. Expand +/Collapse -

      SCHEDULE 4

      PERMANENT STOPPING UP OF STREETS AND PRIVATE MEANS OF ACCESS

      1. PART 1 STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

      2. PART 2 STREETS FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED

      3. PART 3 PUBLIC RIGHTS OF WAY TO BE STOPPED UP AND FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

      4. PART 4 PUBLIC RIGHTS OF WAY TO BE STOPPED UP AND FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED

    5. Expand +/Collapse -

      SCHEDULE 5

      LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED

    6. Expand +/Collapse -

      SCHEDULE 6

      MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF RESTRICTIVE COVENANTS

      1. Expand +/Collapse -

        Compensation enactments

        1. 1.The enactments for the time being in force with respect...

        2. 2.(1) Without limitation on the scope of paragraph 1, the...

        3. 3.(1) Without limitation on the scope of paragraph 1, the...

      2. Expand +/Collapse -

        Application of Part 1 of the 1965 Act

        1. 4.Part 1 (compulsory purchase under Acquisition of Land Act 1946)...

        2. 5.(1) The modification referred to in paragraph 4(a) are as...

    7. Expand +/Collapse -

      SCHEDULE 7

      LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

    8. Expand +/Collapse -

      SCHEDULE 8

      PROTECTIVE PROVISIONS

      1. Expand +/Collapse -

        PART 1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWAGE UNDERTAKERS

        1. 1.For the protection of the utility undertakers referred to in...

        2. 2.In this Part of this Schedule— “alternative apparatus” means alternative...

        3. On street apparatus

          1. 3.This Part of this Schedule does not apply to apparatus...

        4. Apparatus in stopped up streets

          1. 4.(1) Where any street is stopped up under article 13...

        5. Protective works to buildings

          1. 5.The undertaker, in the case of the powers conferred by...

        6. Acquisition of land

          1. 6.Regardless of any provision in this Order or anything shown...

        7. Removal of apparatus

          1. 7.(1) If, in the exercise of the powers conferred by...

        8. Facilities and rights for alternative apparatus

          1. 8.(1) Where, in accordance with the provisions of this Part...

        9. Retained apparatus

          1. 9.(1) Not less than 28 days before starting the execution...

        10. Expenses and costs

          1. 10.(1) Subject to the following provisions of this paragraph, the...

          2. 11.(1) Subject to sub-paragraphs (2) and (3), if by reason...

        11. Cooperation

          1. 12.Where in consequence of the proposed construction of any of...

          2. 13.Nothing in this Part of this Schedule affects the provisions...

      2. Expand +/Collapse -

        PART 2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS

        1. 14.For the protection of any operator, the following provisions have...

        2. 15.In this Part of this Schedule— “the 2003 Act” means...

        3. 16.The exercise of the powers conferred by article 31 (statutory...

        4. 17.(1) Subject to sub-paragraphs (2) to (4), if as the...

    9. Expand +/Collapse -

      SCHEDULE 9

      DOCUMENTS TO BE CERTIFIED

  11. Explanatory Note

Back to top

Options/Help

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?