Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
15.—(1) From such a date as the undertaker may determine, the application of the traffic regulation order listed in column 3 of Schedule 3 will be suspended until the completion of the authorised development.
(2) The undertaker must notify the chief officer of police and the traffic authority in whose area the road is situated of the commencement of suspension under paragraph 1 not less than 14 days before the date to be determined under paragraph (1), and 14 days prior to completion of the authorised development of the date of completion for the purposes of paragraph (1).
(3) Without limitation on the scope of paragraph (1), and subject to the provisions of this article, and the consent of the traffic authority in whose area the road concerned is situated, which consent must not be unreasonably withheld, the undertaker may, for the purposes of the authorised development revoke, amend or suspend in whole or in part any order not listed in Schedule 3 made, or having effect as if made, under the 1984 Act, either at all times or at times, on days or during such periods as may be specified by the undertaker.
(4) The power conferred by paragraph (3) may be exercised at any time prior to the expiry of 12 months from the commencement of operation of the authorised development but subject to paragraph (8) any prohibition, restriction or other provision made under this article may have effect both before and after the expiry of that period.
(5) The undertaker must consult the chief officer of police and the traffic authority in whose area the road is situated before complying with the provisions of paragraph (6).
(6) The undertaker must not exercise the powers conferred by this article unless it has—
(a)given not less than—
(i)12 weeks’ notice in writing of its intention so to do in the case of a prohibition, restriction or other provision intended to have effect permanently; or
(ii)4 weeks’ notice in writing of its intention so to do in the case of a prohibition, restriction or other provision intended to have effect temporarily,
to the chief officer of police and to the traffic authority in whose area the road is situated; and
(b)advertised its intention in such manner as the traffic authority may specify in writing within 28 days of its receipt of notice of the undertaker’s intention in the case of sub-paragraph (a)(i), or within 7 days of its receipt of notice of the undertaker’s intention in the case of sub-paragraph (a)(ii).
(7) Any prohibition, restriction or other provision made by the undertaker under this article—
(a)has effect as if duly made by, as the case may be—
(i)the traffic authority in whose area the road is situated, as a traffic regulation order under the 1984 Act; or
(ii)the local authority in whose area the road is situated, as an order under section 32 (power of local authorities to provide parking places) of the 1984 Act,
and the instrument by which it is effected may specify savings and exemptions to which the prohibition, restriction or other provision is subject; and
(b)is deemed to be a traffic order for the purposes of Schedule 7 (road traffic contraventions subject to civil enforcement) to the Traffic Management Act 2004(1).
(8) Any prohibition, restriction or other provision made under this article may be suspended, varied or revoked by the undertaker from time to time by subsequent exercise of the powers conferred by this article within a period of 24 months from the opening of the authorised development.
(9) Before exercising the powers conferred by this article the undertaker must consult such persons as it considers necessary and appropriate and must take into consideration any representations made to it by any such person.
(10) Expressions used in this article and in the 1984 Act have the same meaning in this article as in that Act.
(11) The powers conferred on the undertaker by this article with respect to any road have effect subject to any agreement entered into by the undertaker with any person with an interest in (or who undertakes activities in relation to) premises served by the road.
(12) Save for any application made to Highways England, if the traffic authority fails to notify the undertaker of its decision within 28 days of receiving an application for consent under paragraph (2) the traffic authority is deemed to have granted consent.
Commencement Information
I1Art. 15 in force at 10.3.2022, see art. 1
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: