Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
2.—(1) In these Regulations—
“air source heat pump” means a plant(1) which generates heat using a thermodynamic cycle by transferring energy stored in the form of heat in the ambient air outside a property and uses that energy to heat a liquid;
[F1“boiler upgrade grant” means the grant, the value of which has been published under regulation 13(1), (4) or (5) which is payable by the Authority to an installer under these Regulations;]
“boiler upgrade voucher” has the meaning given in regulation 15(1);
“biomass boiler” means a plant which—
is designed and installed to burn solid biomass(2) to provide heat,
is designed to minimise direct heat loss to the immediate area in which it is installed,
is not capable of providing heat to a property without using a liquid to deliver that heat, and
is not designed to generate heat for the purpose of cooking food [F2where that function is not able to be controlled independently of the heating or hot water];
“building” means a roofed construction having walls, for which energy is used to condition the indoor climate, and reference to a building includes reference to a building unit in that building;
“building unit” means a section, floor or apartment within a building which is designed or altered to be used separately;
“commencement date” means the day on which these Regulations come into force;
“commissioned”, in relation to a plant, means the completion of such procedures and tests as constitute, at the time they are undertaken, the usual industry standards and practices for that type of plant which demonstrate that it is capable of operating and generating heat;
“connected person”, in relation to an installer, means any person connected to them within the meaning of section 1122 of the Corporation Tax Act 2010(3);
“consumer code” means a code of practice [F3for the purpose of consumer protection approved by the Secretary of State under regulation 4(1)(j);]
“eligible plant” has the meaning given in regulation 8;
“eligible property” has the meaning given in regulation 5;
“energy performance certificate” has the meaning given in regulation 2(1) of the EPB Regulations;
“the EPB Regulations” means the Energy Performance of Buildings (England and Wales) Regulations 2012(4);
“financial year” means—
the period beginning with the commencement date and ending with 31st March 2023, or
any subsequent 12 month period beginning with 1st April and ending with the following 31st March;
“grant application” has the meaning given in regulation 14(1);
“grant change notice” has the meaning given in regulation 13(4);
[F4“grant from public funds” means a grant made by a public authority or by any person distributing funds on behalf of a public authority;]
“ground source heat pump” means a plant which generates heat using a thermodynamic cycle by transferring energy stored in the form of heat from the ground, including water in the ground or surface water or both, and uses that energy to heat a liquid;
[F4“heat network” means a network that, by distributing a liquid or a gas, enables the transfer of thermal energy for the purpose of supplying heating, cooling or hot water to two or more properties (and includes any appliance the main purpose of which is to heat or cool the liquid or gas);]
“heat pump” means a plant which is an air source heat pump or a ground source heat pump [F5or both];
“installer” means a person who is certified by the Microgeneration Certification Scheme(5) or a scheme—
which is equivalent to the Microgeneration Certification Scheme, and
under which installers are certified to standards equivalent to the Microgeneration Certification Scheme’s standards by a certification body or organisation accredited by UKAS to the standard approved by the Secretary of State under regulation 4(1)(a);
“installer obligation” means an obligation specified in regulation 17;
“mains gas” means a supply of the kind mentioned in section 5(1)(b) of the Gas Act 1986(6);
[F4“new-build property” means an eligible property that meets the requirements set out in regulation 7;]
“NOx” means oxides of nitrogen;
[F4“off-gas grid property” means a property that is not attached to a heat network and—
is not fuelled by mains gas,
there is no record of a gas meter point at the property, and
is not a new-build property;]
“original heating system” has the meaning given in regulation 5(1)(c)(ii);
“PM” means particulate matter;
“properly made”—
in the case of a grant application, means an application which provides the information required by regulation 14(3), and in relation to which any information specified in a notice issued in accordance with regulation 14(4) or (5) has been received by the Authority,
in relation to a redemption application, means an application which provides the information required by regulation 16(3), and in relation to which any information required by a notice issued in accordance with regulation 16(4) has been received by the Authority;
“quarter” means a period of three months beginning with 1st January, 1st April, 1st July, or 1st October;
“recommendation report” has the meaning given in regulation 4(1) of the EPB Regulations;
“redemption application” has the meaning given in regulation 16(1);
“F6... means any building or swimming pool which is used by, or available for the use of, an owner or occupier of that property and where the building, building unit or swimming pool is not covered by the valid energy performance certificate for that property;
”, in relation to an eligible property,“relevant installation standard” has the meaning given in paragraph 2 of Schedule 4;
“relevant financial year” means a financial year beginning with—
the commencement date,
[F71st April 2023,
1st April 2024,
1st April 2025,
1st April 2026, or
1st April 2027;]
“the Scheme” has the meaning given in regulation 3;
“UKAS” means the United Kingdom Accreditation Service, a company limited by guarantee and incorporated in England and Wales under number 3076190;
“urban area” means an area classified as urban in the “2011 rural-urban classification of output areas” published by the Office for National Statistics in August 2013(7).
(2) For the purposes of these Regulations, an energy performance certificate for a property is “valid” if—
(a)it was entered on the register required to be maintained under regulation 27(1) of the EPB Regulations no more than 10 years before the date on which it is relied on for the purposes of a grant application in relation to that property, and
(b)no other energy performance certificate for the property has since been entered on the register.
(3) Where there is more than one owner of a property, then any reference in these Regulations to the owner of the property includes any person who is an owner of the property.
(4) For the purposes of these Regulations, a scheme is equivalent to the Microgeneration Certification Scheme if it is approved as equivalent by the Secretary of State.
(5) For the purposes of these Regulations, a property does not cease to be “fuelled by mains gas” if the supply meter point in relation to the property is capped or clamped, where “supply meter point” has the meaning given in the Uniform Network Code (as defined in section 36C(7) of the Gas Act 1986)(8).
Textual Amendments
F1Words in reg. 2(1) substituted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 3(3) (with reg. 25)
F2Words in reg. 2(1) inserted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 3(4) (with reg. 25)
F3Words in reg. 2(1) substituted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 3(5) (with reg. 25)
F4Words in reg. 2(1) inserted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 3(2) (with reg. 25)
F5Words in reg. 2(1) substituted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 3(6) (with reg. 25)
F6Words in reg. 2(1) omitted (8.5.2024) by virtue of The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 3(7) (with reg. 25)
F7Words in reg. 2(1) substituted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 3(8) (with reg. 25)
Commencement Information
I1Reg. 2 in force at 23.5.2022, see reg. 1(1)
And see section 100(3) of the 2008 Act for the definition of “plant”.
And see section 100(3) of the 2008 Act for the definition of “biomass”.
S.I. 2012/3118, as amended by S.I. 2013/10, 181 and 603, 2014/880, 2015/609 and 1681, 2016/284 and 888, 2017/368, 2018/362, 2020/1422, and 2021/370 and 439.
Details of the scheme are available at www.mscertified.com.
1986 c. 44. Section 5 was substituted by section 3 of the Gas Act 1995, and sub-section (1)(b) was amended by S.I. 2012/2400.
ISBN 978 0 580 78472 9. This international standard was published by the British Standards Institution on 31st October 2012; which defines an urban area as one with a population of 10,000 people or more.
Section 36C(7) was inserted by section 81(1) of the Energy Act 2011 (c. 16). See paragraph A4.1.1 of the Transportation Principal Document of the Uniform Network Code, issued on 24th July 2020, for the definition of “supply meter point”. Copies of that document are available at www.gasgovernance.co.uk/TPD. Hard copies are not available.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: