Works on Company cables E+W

157.—(1) Subject to sub-paragraphs (2) and (3), the Company is entitled, at the Company’s expense, to carry out any operation required to re-lay, maintain, renew or remove the Company cables within 250 metres of the undertaker cables if such work becomes necessary for any reason.

(2) [F1When the Company proposes to undertake work under sub-paragraph (1) they must follow the procedure set out in paragraphs 154 to 156 which applies with the following modifications to the relevant paragraphs and defined terms]

(a)the references to the “the undertaker” must be read as references to “the Company”;

(b)the references to “the Company” must be read as references to “the undertaker”; and

(c)[F2the references to “future specified work” must be read as “work permitted under paragraph 157.]”.

(3) [F3When the Company undertakes works under sub-paragraph (1) they are subject to paragraphs 158 to 167 which apply with the following modifications to the relevant paragraphs and defined terms]

(a)[F4the references to the “undertaker” must be read as references to “the Company]”;

(b)the references to “the Company” must be read as references to “the undertaker”;

(c)the references to “undertaker cables” must be read as references to “Company cables”;

(d)the references to “Company cables” must be read as references to “undertaker cables”; and

(e)[F5the references to “specified work” must be read as “work permitted under paragraph 157]”.