Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

New principal contractor or principal designer etc: notificationE+W

This section has no associated Explanatory Memorandum

29.—(1) This paragraph applies where, at any time after building control approval for HRB work, a stage of HRB work or work to existing HRB is granted the client appoints a principal contractor (or sole contractor) or principal designer (or sole or lead designer).

(2) Where paragraph (1) applies, the client must give a notice, signed by the client, to the regulator containing—

(a)the name, address, telephone number and (if available) email address of the person appointed,

(b)a statement that the client—

(i)has complied with regulation 11E(2)(b) (consideration of past misconduct) of the 2010 Regulations,

(ii)is satisfied in the case of a principal contractor, that the person fulfils the requirements in regulations 11F(1) and (2) and 11H(1) of the 2010 Regulations,

(iii)is satisfied in the case of a principal designer, that the person fulfils the requirements in regulations 11F(1) and (2) and 11G(1) of the 2010 Regulations,

(iv)is satisfied in the case of a sole contractor, or sole or lead designer, that the person fulfils the requirements in regulations 11F(1) and (2) of the 2010 Regulations,

(c)in relation to each principal contractor or principal designer, a copy of the record, in respect of the person, that the client created under regulation 11D(8) or (9) (principal designer and principial contractor) of the 2010 Regulations, and

(d)a declaration as to the truth of the statement referred to in sub-paragraph (b) and of the record (if any) referred to in sub-paragraph (c).

(3) On request from the client, the person who was the principal contractor (or sole contractor) or principal designer (or sole or lead designer), as the case may be, before the appointment referred to in paragraph (1) must give the client a statement in writing, signed and dated by them, which sets out—

(a)their name, address, telephone number and (if available) email address,

(b)the dates of their appointment,

(c)subject to paragraph (d), a certificate that—

(i)in the case of a person who was a principal contractor (or sole contractor), that they have fulfilled their duties as a principal contractor under Part 2A (dutyholders and competence) of the 2010 Regulations,

(ii)in the case of a person who was principal designer (or sole or lead designer), that they have fulfilled their duties as a principal designer under Part 2A (dutyholders and competence) of the 2010 Regulations,

(d)where a person is unable to certify that they have fulfilled their duties, a statement explaining what duties they were unable to fulfil and the reasons for not being able to do so.

(4) The client must ensure the notice under paragraph (2) is accompanied by a copy of a statement provided to them under paragraph (3).

(5) Where, at the date a client gives the notice under paragraph (2), the client is unable to obtain the statement under paragraph (3), the notice under paragraph (2) must be accompanied by a statement by the client explaining the steps the client has taken to obtain the statement together with any reasons the person referred to in paragraph (3) has given for not providing the statement.

(6) The client must give the notice under paragraph (2) together with a copy of the statement referred to in paragraph (3) or, if applicable, a statement referred to in paragraph (5), to the regulator within the period of 14 days beginning with the date of the appointment.

(7) The client must ensure—

(a)a record is made of the change of principal contractor (or sole contractor) or principal designer (or sole or lead designer) in the change control log, and

(b)the construction control plan is revised, in accordance with regulation 18 (change control), to reflect the change.

(8) Where the client is a domestic client (DC), the following applies instead of paragraphs (2) to (7)—

(a)except where the person appointed (PA) is the first person appointed to the role, the person who held the role before PA (“outgoing dutyholder”) must, within five days of the date their appointment ends, give the DC a notice which sets out—

(i)their name, address, telephone number and (if available) email address;

(ii)the date their appointment ended;

(iii)subject to paragraph (b), a certificate that—

(aa)in the case of a person who was a principal contractor (or sole contractor), that they fulfilled their duties as a principal contractor under Part 2A (dutyholders and competence) of the 2010 Regulations;

(bb)in the case of a person who was principal designer (or sole or lead designer), that they fulfilled their duties as a principal designer under Part 2A (dutyholders and competence) of the 2010 Regulations;

(b)where the outgoing dutyholder is unable to certify that they fulfilled their duties, a statement explaining what duties they were unable to fulfil and the reasons for not being able to do so;

(c)DC must provide the information referred to under sub-paragraph (a) and, as the case may be, (b) to PA on the date of appointment of PA or as soon as practicable after that date;

(d)subject to paragraph (10), PA must give a notice to the regulator which includes—

(i)the location of the building work;

(ii)the name, address, telephone number and (if available) email address of PA and the date of appointment;

(iii)except where PA is the first person appointed to the role, the name, address, telephone number and (if available) email address of the outgoing dutyholder and the date their appointment ended;

(iv)a statement explaining the notice is given on behalf of a domestic client.

(9) PA must ensure the notice under paragraph (8)(d) is accompanied by a copy of a certificate provided to them under paragraph (8)(a) or a statement provided to them under paragraph (8)(b).

(10) Where PA has not received the information required to be provided under paragraph (8)(c) by the time the notice under paragraph (8)(d) is to be given, the statement given by PA under paragraph (8)(d)(iv) must also include an explanation to that effect.

(11) A notice required under paragraph (8)(d) must be given to the regulator within the period of 14 days beginning with the date of the appointment.

(12) PA must ensure—

(a)a record is made of the change of principal contractor (or sole contractor) or principal designer (or sole or lead designer) in the change control log, and

(b)the construction control plan is revised, in accordance with regulation 18 (change control), to reflect the change.

Commencement Information

I1Reg. 29 in force at 1.10.2023, see reg. 1(1)

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources