  1. Introductory Text

  2. PART 1 PRELIMINARY

    1. 1.Citation and commencement

    2. 2.Interpretation

  3. PART 2 PRINCIPAL POWERS

    1. 3.Development consent etc. granted by the Order

    2. 4.Maintenance of authorised development

    3. 5.Limits of deviation

    4. 6.Benefit of Order

    5. 7.Consent to transfer benefit of Order

    6. 8.Application of the 1990 Act

    7. 9.Application of the Community Infrastructure Levy Regulations 2010

    8. 10.Planning Permission

  4. PART 3 STREETS

    1. 11.Street works

    2. 12.Application of the Permit Schemes

    3. 13.Application of the 1991 Act

    4. 14.Power to alter layout, etc. of streets

    5. 15.Temporary closure of streets and public rights of way

    6. 16.Access to works

    7. 17.Construction, alteration and maintenance of streets

    8. 18.Agreements with street authorities

  5. PART 4 SUPPLEMENTAL POWERS

    1. 19.Discharge of water

    2. 20.Protective works

    3. 21.Authority to survey and investigate the land

  6. PART 5 ACQUISITION AND POSSESSION OF LAND

    1. Powers of acquisition

      1. 22.Compulsory acquisition of land

      2. 23.Compulsory acquisition of rights

      3. 24.Acquisition of subsoil or airspace only

    2. Temporary possession of land

      1. 25.Temporary use of land by National Grid

      2. 26.Temporary use of land by UKPN

      3. 27.Temporary use of land for maintaining the authorised development

      4. 28.Use of subsoil under or airspace over streets

    3. Compensation

      1. 29.Disregard of certain interests and improvements

      2. 30.Set-off for enhancement in value of retained land

    4. Supplementary

      1. 31.Compulsory acquisition of land – incorporation of the mineral code

      2. 32.Time limit for exercise of authority to acquire land and rights compulsorily

      3. 33.Acquisition of part of certain properties

      4. 34.Application of the 1981 Act

      5. 35.Application of Part 1 of the 1965 Act

      6. 36.Extinguishment and suspension of private rights

      7. 37.Power to override easements and other rights

      8. 38.Statutory authority to override easements and other rights

      9. 39.Extinguishment of private rights and restrictive covenants relating to apparatus belonging to National Grid or UKPN removed from land subject to temporary possession

      10. 40.Crown rights

      11. 41.Special category land

      12. 42.Statutory undertakers

      13. 43.Recovery of costs of new connections

  7. PART 6 MISCELLANEOUS AND GENERAL

    1. 44.Application of landlord and tenant law

    2. 45.Defence to proceedings in respect of statutory nuisance

    3. 46.Traffic regulation

    4. 47.Felling or lopping

    5. 48.Trees subject to Tree Preservation Orders

    6. 49.Temporary closure of, and works in, the River Stour

    7. 50.Protection of interests

    8. 51.Procedure regarding certain approvals etc.

    9. 52.Safeguarding

    10. 53.No double recovery

    11. 54.Application, disapplication and modification of legislative provisions

    12. 55.Amendment of local legislation

    13. 56.Certification of documents

    14. 57.Service of notices

    15. 58.Arbitration

  8. Signature

  9. SCHEDULES

    1. SCHEDULE 1

      AUTHORISED DEVELOPMENT

      1. TRANSMISSION ELECTRIC LINE

        1. In the Districts of Mid-Suffolk and Babergh

          1. Work No. 1 — Bramford Substation line entries and Route 4YL

          2. Work No. 2 — overhead transmission electric lines from Bramford Substation to the Dedham Vale East Cable Sealing End Compound

        2. In the District of Babergh

          1. Work No. 3 — underground transmission electric line from the Dedham Vale East Cable Sealing End Compound to the Dedham Vale West Cable Sealing End Compound

          2. Work No. 4 — overhead transmission electric line from Dedham Vale West Cable Sealing End Compound to the Stour Valley East Cable Sealing End Compound

        3. In the Districts of Babergh and Braintree

          1. Work No. 5 — underground transmission electric line from the Stour Valley East Cable Sealing End Compound to the Stour Valley West Cable Sealing End Compound

        4. In the District of Braintree

          1. Work No. 6 — overhead transmission electric line from the Stour Valley West Cable Sealing End Compound to the existing 4YLA overhead transmission electric line (Route 4YLA) southwest of Alphamstone

          2. Work No. 7 — removal of existing overhead transmission electric line (Route 4YLA) between the Twinstead Tee and a point to the southwest of Alphamstone

      2. DISTRIBUTION ELECTRIC LINE

        1. In the Districts of Mid-Suffolk, Babergh and Braintree

          1. Work No. 8 — removal of existing overhead distribution electric line (Route PCB) between Burstall Bridge and the Twinstead Tee

      3. GRID SUPPLY POINT SUBSTATION

        1. In the District of Braintree

          1. Work No. 9 — Grid Supply Point Substation to the east of Wickham St. Paul

          2. Work No. 10 — modifications to the transmission electric line and connection to the Grid Supply Point Substation

          3. Work No. 11 — modifications to the distribution electric line and connection to the Grid Supply Point Substation

      4. CONSTRUCTION, MAINTENANCE AND USE

        1. In the Districts of Mid-Suffolk, Babergh and Braintree

          1. Work No. 12 — Temporary Site Compounds

      5. ASSOCIATED DEVELOPMENT

    2. SCHEDULE 2

      PLANS

      1. PART 1 ACCESS, RIGHTS OF WAY AND PUBLIC RIGHTS OF NAVIGATION PLANS

      2. PART 2 LAND PLANS

      3. PART 3 SPECIAL CATEGORY LAND PLANS

      4. PART 4 TRAFFIC REGULATION ORDER PLANS

      5. PART 5 TREES AND HEDGEROWS TO BE REMOVED OR MANAGED PLANS

      6. PART 6 WORK PLANS

    3. SCHEDULE 3

      REQUIREMENTS

      1. Interpretation

        1. 1.(1) In this Schedule unless the context requires otherwise— “biodiversity...

      2. Time Limits

        1. 2.(1) The authorised development must commence no later than the...

      3. Stages of authorised development

        1. 3.(1) Unless otherwise agreed with the relevant planning authority, written...

      4. Management Plans

        1. 4.(1) No stage of the authorised development may commence until,...

      5. Approval and implementation of Drainage Management Plan

        1. 5.(1) No stage of the authorised development may be brought...

      6. Archaeology

        1. 6.(1) The authorised development must be undertaken in accordance with...

      7. Construction hours

        1. 7.(1) Subject to sub-paragraphs (2) to (4), work may only...

      8. Retention and removal of trees, woodlands and hedgerows

        1. 8.(1) Unless otherwise agreed with the relevant planning authority, no...

      9. Reinstatement planting plan

        1. 9.(1) Unless otherwise agreed with the relevant planning authority, no...

      10. Reinstatement planting plan– implementation, compliance and replacement planting

        1. 10.(1) Unless otherwise agreed with the relevant planning authority, all...

      11. Highway works

        1. 11.(1) No work to construct, alter or temporarily alter any...

      12. Decommissioning

        1. 12.(1) In the event that, at some future date, the...

      13. Biodiversity Net Gain

        1. 13.Unless otherwise agreed with the relevant planning authority, written evidence...

      14. Approval and implementation of Soil Management Plan

        1. 14.(1) Unless otherwise agreed with the relevant planning authority, no...

    4. SCHEDULE 4

      DISCHARGE OF REQUIREMENTS

      1. Applications made under Requirements

        1. 1.(1) Where an application has been made to a relevant...

      2. Further information

        1. 2.(1) Where an application has been made under paragraph 1...

      3. Fees

        1. 3.(1) Where an application is made to a relevant authority...

      4. Appeals

        1. 4.(1) The undertaker may appeal if— (a) the relevant authority...

      5. Outcome of appeals

        1. 5.(1) On an appeal under paragraph 4, the appointed person...

      6. Interpretation of Schedule 4

        1. 6.In this Schedule— “the appeal parties” means the relevant authority,...

    5. SCHEDULE 5

      STREETS SUBJECT TO STREET WORKS

    6. SCHEDULE 6

      STREETS SUBJECT TO ALTERATION OF LAYOUT

      1. PART 1 STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT

      2. PART 2 STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT

    7. SCHEDULE 7

      STREETS OR PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED

      1. PART 1 STREETS OR PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED FOR WHICH A DIVERSION IS TO BE PROVIDED

      2. PART 2 STREETS OR PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED FOR WHICH NO DIVERSION IS TO BE PROVIDED

    8. SCHEDULE 8

      ACCESS TO WORKS

    9. SCHEDULE 9

      MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

      1. 1.Compensation enactments

      2. 2.(1) Without limitation on the scope of paragraph 1, the...

      3. 3.(1) Without limitation on the scope of paragraph 1, the...

      4. 4.Application of the 1965 Act

      5. 5.For section 7 of the 1965 Act (measure of compensation...

      6. 6.For section8 of the 1965 Act (provisions as to divided...

      7. 7.The following provisions of the 1965 Act (which state the...

      8. 8.Section 11 of the 1965 Act (powers of entry) is...

      9. 9.Section 20 of the 1965 Act (protection for interests of...

      10. 10.Section 22 of the 1965 Act (interests omitted from purchase)...

      11. 11.In section 22(2) (expiry of time limit for exercise of...

      12. 12.For Schedule 2A of the 1965 Act substitute— SCHEDULE 2A...

      13. 13.In this Schedule, references to entering on and taking possession...

    10. SCHEDULE 10

      LAND OF WHICH ONLY TEMPORARY POSSESSION MAY BE TAKEN

    11. SCHEDULE 11

      EXTINGUISHMENT OF PRIVATE RIGHTS AND RESTRICTIVE COVENANTS RELATING TO APPARATUS BELONGING TO NATIONAL GRID OR UKPN REMOVED FROM LAND SUBJECT TO TEMPORARY POSSESSION

    12. SCHEDULE 12

      TRAFFIC REGULATION ORDERS

      1. PART 1 TEMPORARY RESTRICTION OF WAITING AND RESTRICTION OF SPEED

      2. PART 2 TEMPORARY RESTRICTION OF ACCESS

      3. PART 3 TEMPORARY RESTRICTION OF MOVEMENT

      4. PART 4 TEMPORARY NO OVERTAKING ORDER

    13. SCHEDULE 13

      TREES SUBJECT TO TREE PRESERVATION ORDERS

    14. SCHEDULE 14

      PROTECTIVE PROVISIONS

      1. PART 1 PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS

        1. 1.For the protection of the statutory undertakers referred to in...

        2. 2.In this Part of this Schedule— “alternative apparatus” means alternative...

        3. 3.This Part of this Schedule does not apply to apparatus...

        4. 4.Regardless of any provision in this Order or anything shown...

        5. 5.(1) If, in the exercise of the powers conferred by...

        6. 6.(1) Not less than 28 days before starting the execution...

        7. 7.(1) Subject to the following provisions of this paragraph, the...

      2. PART 2 PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS

        1. 8.(1) For the protection of any operator, the following provisions,...

        2. 9.The exercise of the powers of article42 (statutory undertakers) is...

        3. 10.(1) Subject to sub-paragraphs (2) to (3), if as the...

        4. 11.This Part of this Schedule does not apply to—

        5. 12.Nothing in this Part of this Schedule affects the provisions...

      3. PART 3 FOR THE PROTECTION OF ANGLIAN WATER SERVICES LIMITED

        1. 13.Application

        2. 14.Interpretation

        3. 15.Apparatus in closed streets

        4. 16.Protective works

        5. 17.Acquisition of land

        6. 18.Removal of apparatus

        7. 19.Facilities and rights for alternative apparatus

        8. 20.Retained apparatus

        9. 21.Expenses and costs

        10. 22.(1) Subject to sub-paragraphs (2) and (3), if by reason...

        11. 23.Cooperation

        12. 24.Where the undertaker identifies any apparatus which may belong to...

        13. 25.Nothing in this Part of this Schedule affects the provisions...

        14. 26.The undertaker and Anglian Water may by written agreement substitute...

      4. PART 4 FOR THE PROTECTION OF NETWORK RAIL INFRASTRUCTURE LIMITED

        1. 27.The provisions of this Part of this Schedule have effect,...

        2. 28.In this Part of this Schedule— “asset protection agreement” means...

        3. 29.(1) Where under this Part of this Schedule Network Rail...

        4. 30.(1) The undertaker must not exercise the powers conferred by—...

        5. 31.(1) The undertaker must before commencing construction of any specified...

        6. 32.(1) Any specified work and any protective works to be...

        7. 33.The undertaker must— (a) at all times afford reasonable facilities...

        8. 34.Network Rail must at all times afford reasonable facilities to...

        9. 35.(1) If any permanent or temporary alterations or additions to...

        10. 36.The undertaker must repay to Network Rail all reasonable fees,...

        11. 37.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...

        12. 38.If at any time after the completion of a specified...

        13. 39.The undertaker must not provide any illumination or illuminated sign...

        14. 40.Any additional expenses which Network Rail may reasonably incur in...

        15. 41.(1) The undertaker must pay to Network Rail all reasonable...

        16. 42.Network Rail must, on receipt of a request from the...

        17. 43.In the assessment of any sums payable to Network Rail...

        18. 44.The undertaker and Network Rail may, subject in the case...

        19. 45.Nothing in this Order, or in any enactment incorporated with...

        20. 46.The undertaker must give written notice to Network Rail if...

        21. 47.The undertaker must no later than 28 days from the...

        22. 48.In relation to any dispute arising under this part of...

      5. PART 5 FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS UNDERTAKER

        1. 49.Application

        2. 50.Interpretation

        3. 51.On Street Apparatus

        4. 52.Apparatus of Cadent in stopped up streets

        5. 53.Protective works to buildings

        6. 54.Acquisition of land

        7. 55.Removal of apparatus

        8. 56.Facilities and rights for alternative apparatus

        9. 57.Retained apparatus: protection of Cadent

        10. 58.Expenses

        11. 59.Indemnity

        12. 60.Enactments and agreements

        13. 61.Co-operation

        14. 62.Access

        15. 63.Arbitration

        16. 64.Notices

    15. SCHEDULE 15

      PUBLIC GENERAL LEGISLATION

      1. 1.Hedgerow Regulations 1997

      2. 2.Local Government (Miscellaneous Provisions) Act 1976

      3. 3.Neighbourhood Planning Act 2017

      4. 4.Building Act 1984

    16. SCHEDULE 16

      AMENDMENT OF LOCAL LEGISLATION

    17. SCHEDULE 17

      CERTIFIED DOCUMENTS

  10. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources