5.—(1) Nothing in these Regulations affects any procurement commenced before these Regulations come into force.
(2) For the purposes of paragraph (1), a procurement is commenced before these Regulations come into force if, before that date, in accordance with the applicable Procurement Regulations—
(a)a notice has been submitted to the UK e-notification service in order to—
(i)invite offers or requests to be selected to tender for or to negotiate in respect of a proposed contract, framework agreement or dynamic purchasing system, or
(ii)publicise an intention to hold a design contest;
(b)the contracting authority or utility has had published any form of advertisement seeking offers or expressions of interest in a proposed contract, framework agreement or dynamic purchasing system; or
(c)the contracting authority or utility has contacted any economic operator in order to—
(i)seek expressions of interest or offers in respect of a proposed contract, framework agreement or dynamic purchasing system, or
(ii)respond to an unsolicited expression of interest or offer received from that economic operator in relation to a proposed contract, framework agreement or dynamic purchasing system.
(3) For the purposes of this regulation, a procurement covers the whole of the procedures which, in accordance with the applicable Procurement Regulations, stem from that commencement.
(4) Procedures taken for the purpose of modifying a contract or framework agreement are not to be regarded, for the purposes of paragraph (3), as stemming from the commencement of the procurement from which the award of that contract or framework agreement had itself stemmed.
(5) A procedure commenced as described in paragraph (2)(a)(i), (b) or (c) is not to be regarded, for the purposes of paragraph (3), as stemming from the commencement of any design contest that had previously been held in relation to the subject-matter of the procurement.
(6) In this regulation—
(a)“Procurement Regulations” means the following and, in relation to any procedure, means whichever of the following applies to that procedure—
(i)the Public Contracts Regulations 2015;
(ii)the Concession Contracts Regulations 2016;
(iii)the Utilities Contracts Regulations 2016;
(b)the following have the same meaning as in the applicable Procurement Regulations—
(i)contracting authority;
(ii)design contest;
(iii)dynamic purchasing system;
(iv)economic operator;
(v)framework agreement;
(vi)procurement;
(vii)UK e-notification service;
(viii)utility.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: