Search Legislation

The Building Safety Act 2022 (Commencement No. 4, Transitional and Saving Provisions) (Wales) Regulations 2024

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Section 8

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Building Safety Act 2022 (Commencement No. 4, Transitional and Saving Provisions) (Wales) Regulations 2024, Section 8. Help about Changes to Legislation

Transitional provision: higher-risk building work not commenced by 1 October 2024E+W

8.  Where regulation 3(1) of these Regulations applies and higher-risk building work is not commenced before 1 October 2024, then—

(a)the initial notice related to the higher-risk building work will cease to be in force on 1 October 2024 for the purposes of section 47(4)(b)(ii) of the 1984 Act, and

(b)any plans certificate related to that initial notice will cease to be in force on 1 October 2024.

Back to top

Options/Help