10.—(1) Subject to sub paragraph (4)—
(a)the reception and treatment within the curtilage of a water treatment works of any of the wastes listed in Table 4 if the total quantity of waste which is treated in any period of 12 months does not exceed 100,000 cubic metres; and
(b)the secure storage within the curtilage of a water treatment works of waste intended to be treated in reliance on the exemption conferred by paragraph (a).
(2) Subject to the following provisions of this paragraph—
(a)any recovery operation carried on within the curtilage of a sewage treatment works of any of the wastes listed in Table 4;
(b)the secure storage within the curtilage of a sewage treatment works of waste intended to be submitted to the activity mentioned in paragraph (a).
Codes (1) | Types of waste |
---|---|
(1) Codes referred to in the European Waste Catalogue. | |
Waste from waste water treatment plants not otherwise specified (19 08) | |
19 08 01 | Screenings |
19 08 05 | Sludges from treatment of urban waste water |
Wastes from the preparation of water intended for human consumption or water for industrial use (19 09) | |
19 09 02 | Sludges from water clarification |
19 09 03 | Sludges from decarbonation |
19 09 06 | Solutions and sludges from regeneration of ion exchangers |
Other municipal wastes (20 03) | |
20 03 04 | Septic tank sludge |
20 03 99 | Municipal waste not otherwise specified |
(3) The total quantity of waste brought to a sewage treatment works for the purposes of a recovery operation in reliance upon the exemption covered by sub paragraph (2) in any period of 12 months shall not exceed 100,000 cubic metres.
(4) The area where a treatment or recovery operation takes place shall have an impermeable pavement capable of containing any spillage of waste received and connected to a drainage system with impermeable components which does not leak and which will ensure that—
(a)no liquid will run off the pavement otherwise than via that system; and
(b)except where they may be lawfully discharged, all liquids entering the system are collected in a sealed sump.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Executive Note sets out a brief statement of the purpose of a Draft Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: