Search Legislation

The Environmental Liability (Scotland) Regulations 2009

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: The Environmental Liability (Scotland) Regulations 2009 (Schedules only)

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The Environmental Liability (Scotland) Regulations 2009. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulation 4(1)

SCHEDULE 1SACTIVITIES FOR THE PURPOSES OF REGULATION 4(1)

[F1A1.    InterpretationS

A reference in this schedule to an activity being authorised, prohibited or managed pursuant to, or subject to a permit, authorisation or registration under, a Directive includes, on or after exit day, any activity authorised, prohibited or managed pursuant to, or subject to a permit, authorisation or registration under, any [F2assimilated] law which transposed that Directive.]

[F31.  The operation of installations subject to permit in pursuance of—S

(a)Council Directive 96/61/EC of 24 September 1996 concerning the integrated pollution prevention and control in respect of all activities listed in Annex I to that Directive with the exception of installations or parts of installations used for research, development and testing of new products and processes,

(b)Directive 2008/1/EC of the European Parliament and of Council of 15 January 2008 concerning integrated pollution prevention and control in respect of all activities listed in Annex I to that Directive with the exception of installations or parts of installations used for research, development and testing of new products and processes, or

(c)Directive 2010/75/EU of the European Parliament and of the Council of 24 November 2010 on industrial emissions (integrated pollution prevention and control).]

[F32.(1) Waste management operations, including the collection, transport, recovery and disposal of waste and hazardous waste, including the supervision of such operations and after-care of disposal sites, subject to permit or registration in pursuance of—S

(a)Council Directive 91/689/EEC of 12 December 1991 on hazardous waste,

(b)Directive 2006/12/EC of the European Parliament and of Council of 5 April 2006 on waste,

(c)Directive 2008/98/EC of the European Parliament and of the Council of 19 November 2008 on waste.

(2) The operation of—

(a)landfill sites under Council Directive 1999/31/EC of 26 April 1999 on the landfill of waste, or

(b)incineration plants under—

(i)Directive 2000/76/EC of the European Parliament and of the Council of 4 December 2000 on the incineration of waste, or

(ii)Directive 2010/75/EU of the European Parliament and of the Council of 24 November 2010 on industrial emissions (integrated pollution prevention and control).

(3) Sub-paragraphs (1) and (2) do not apply to operations to the extent to which they include the spreading of sewage sludge from urban waste water treatment plants, treated to an approved standard, for the purposes of agriculture (within the meaning of regulation 2 of the Sludge (Use in Agriculture) Regulations 1989).]

3.  All discharges into inland surface water, which require prior authorisation in pursuance of Council Directive 2006/11/EC of 15th February 2006 on pollution caused by certain dangerous substances discharged into the aquatic environment of the Community M1.S

Marginal Citations

M1O.J. No. L 64, 4.3.2006, p.52.

[F44.  All discharges of substances into groundwater which require prior authorisation in pursuance of—S

(a)Council Directive 80/68/EEC of 17 December 1979 on the protection of groundwater against pollution caused by certain dangerous substances,

(b)Directive 2006/118/EC of the European Parliament and of the Council of 12 December 2006 on the protection of groundwater against pollution and deterioration.]

5.  The discharge or injection of pollutants into surface water or groundwater which require a permit, authorisation or registration in pursuance of Directive 2000/60/EC.S

6.  Water abstraction and impoundment of water subject to prior authorisation in pursuance of Directive 2000/60/EC.S

[F57.  Manufacture, use, storage, processing, filling, release into the environment and onsite transport of—S

(a)dangerous substances as defined in Article 2(2) of Council Directive 67/548/EEC of 27 June 1967 on the approximation of the laws, regulations and administrative provisions of the Member States relating to the classification, packaging and labelling of dangerous substances,

(b)hazardous substances as defined in Article 3 of Regulation (EC) No. 1272/2008 of the European Parliament and of the Council of 16 December 2008 on classification, labelling and packaging of substances and mixtures,

(c)dangerous preparations as defined in Article 2(2) of Directive 1999/45/EC of the European Parliament and of the Council of 31 May 1999 concerning the approximation of the laws, regulations and administrative provisions of the Member States relating to the classification, packaging and labelling of dangerous preparations,

(d)plant protection products which has the same meaning as in Article 2(1) of Regulation (EC) No 1107/2009 of the European Parliament and of the Council of 21 October 2009 concerning the placing of plant protection products on the market,

(e)biocidal products as defined in Article 2(1)(a) of Directive 98/8/EC of the European Parliament and of the Council of 16 February 1998 concerning the placing of biocidal products on the market or as defined in Article 3(1)(a) of Regulation (EU) No. 528/2012 of the European Parliament and of the Council of 22 May 2012 concerning the making available on the market and use of biocidal products.]

[F58.  Transport by road, rail, inland waterways, sea or air of dangerous goods or polluting goods as defined in—S

(a)Annex A to Council Directive 94/55/EC of 21 November 1994 on the approximation of the laws of the Member States with regard to the transport of dangerous goods by road,

(b)the Annex to Council Directive 96/49/EC of 23 July 1996 on the approximation of the laws of the Member States with regard to the transport of dangerous goods by rail,

(c)Council Directive 93/75/EEC of 13 September 1993 concerning minimum requirements for vessels bound for or leaving Community ports and carrying dangerous or polluting goods,

(d)Directive 2002/59/EC of the European Parliament and of the Council of 27th June 2002 establishing a Community vessel traffic monitoring and information system,

(e)Directive 2008/68/EC of the European Parliament and of the Council of 24th September 2008 on the inland transport of dangerous goods.]

9.  Any contained use, including transport, involving genetically modified micro‑organisms as defined by [F6Directive 2009/41/EC of the European Parliament and of the Council of 6 May 2009 on the contained use of genetically modified micro-organisms].S

10.  Any deliberate release into the environment, transport and placing on the market of genetically modified organisms as defined by Directive 2001/18/EC.S

11.  Transboundary shipment of waste within, into or out of the European Union [F7or into or out of the United Kingdom], requiring an authorisation or prohibited in the meaning of Council Regulation (EC) No. 1013/2006 of 14th June 2006 on shipments of waste M2.S

Textual Amendments

Marginal Citations

M2O.J. No. L 190, 12.7.2006, p.1, as last amended by Commission Regulation (EC) No. 669/2008 (O.J. No. L 188, 16.7.2008, p.7).

12.  The management of extractive waste pursuant to Directive 2006/21/EC of the European Parliament and of the Council of 15th March 2006 on the management of waste from extractive industries M3.S

Marginal Citations

M3O.J. No. L 102, 11.4.2006, p.15.

[F813.  The operation of storage sites pursuant to Directive 2009/31/EC of the European Parliament and of the Council on the geological storage of carbon dioxide and amending Council Directive 85/337/EEC, European Parliament and Council Directives 2000/60/EC, 2001/80/EC, 2004/35/EC, 2006/12/EC, 2008/1/EC and Regulation (EC) No 1013/2006.]S

Regulation 9

SCHEDULE 2SSUPPLEMENTARY PROVISIONS IN RESPECT OF POWERS OF ENTRY AND INSPECTION

[F3InterpretationS

1.  The operation of installations subject to permit in pursuance of—

(a)Council Directive 96/61/EC of 24 September 1996 concerning the integrated pollution prevention and control in respect of all activities listed in Annex I to that Directive with the exception of installations or parts of installations used for research, development and testing of new products and processes,

(b)Directive 2008/1/EC of the European Parliament and of Council of 15 January 2008 concerning integrated pollution prevention and control in respect of all activities listed in Annex I to that Directive with the exception of installations or parts of installations used for research, development and testing of new products and processes, or

(c)Directive 2010/75/EU of the European Parliament and of the Council of 24 November 2010 on industrial emissions (integrated pollution prevention and control).]

[F3WarrantsS

2.(1) Waste management operations, including the collection, transport, recovery and disposal of waste and hazardous waste, including the supervision of such operations and after-care of disposal sites, subject to permit or registration in pursuance of—

(a)Council Directive 91/689/EEC of 12 December 1991 on hazardous waste,

(b)Directive 2006/12/EC of the European Parliament and of Council of 5 April 2006 on waste,

(c)Directive 2008/98/EC of the European Parliament and of the Council of 19 November 2008 on waste.

(2) The operation of—

(a)landfill sites under Council Directive 1999/31/EC of 26 April 1999 on the landfill of waste, or

(b)incineration plants under—

(i)Directive 2000/76/EC of the European Parliament and of the Council of 4 December 2000 on the incineration of waste, or

(ii)Directive 2010/75/EU of the European Parliament and of the Council of 24 November 2010 on industrial emissions (integrated pollution prevention and control).

(3) Sub-paragraphs (1) and (2) do not apply to operations to the extent to which they include the spreading of sewage sludge from urban waste water treatment plants, treated to an approved standard, for the purposes of agriculture (within the meaning of regulation 2 of the Sludge (Use in Agriculture) Regulations 1989).]

Evidence of authorityS

3.  A person designated as the person who may exercise a relevant power shall produce evidence of that designation and other authority before exercising the power.

Admissibility of informationS

4.—(1) Subject to regulation 9(7), information obtained in consequence of the exercise of a relevant power, with or without the consent of any person, shall be admissible in evidence against that or any other person.

(2) Without prejudice to the generality of sub-paragraph (1), information obtained by means of monitoring or other apparatus installed on any premises in the exercise of a relevant power, with or without the consent of any person in occupation of the premises, shall be admissible in evidence in any proceedings against that or any other person.

Securing of premisesS

5.  A person who, in the exercise of a relevant power, enters on any premises which are unoccupied or whose occupier is temporarily absent shall leave the premises as effectually secured against trespassers as they were on entry.

CompensationS

6.—(1) Where any person exercises any power conferred by regulation 9(2)(a) or (b), it shall be the duty of the competent authority under whose authorisation that person acts to make full compensation to any person who has sustained loss or damage by reason of—

(a)the exercise by that person of that power; or

(b)the performance of, or failure of that person to perform, the duty imposed by paragraph 5.

(2) Compensation shall not be payable by virtue of sub-paragraph (1) in respect of any loss or damage if compensation is payable in respect of that loss or damage by virtue of any other enactment.

(3) A person exercising any power conferred by regulation 9(2)(a) or (b) shall not be liable in any civil or criminal proceedings for anything done in the purported exercise of any relevant power if the court is satisfied that the person acted in good faith.

Regulation 11(2)

SCHEDULE 3SREMEDIATION OF ENVIRONMENTAL DAMAGE

PART I S

Application of Part IS

1.  This Part applies to remediation of damage to natural resources other than land.

DefinitionsS

2.  In this Part—

(a)primary remediation” means any remedial measure which returns the damaged natural resources or impaired services to, or towards, baseline condition;

(b)complementary remediation” means any remedial measure taken in relation to natural resources or services to compensate for the fact that primary remediation does not result in fully restoring the damaged natural resources or services;

(c)compensatory remediation” means any action taken to compensate for interim losses of natural resources or services that occur from the date of damage occurring until primary remediation has achieved its full effect; and

(d)interim losses” means losses which result from the fact that the damaged natural resources or services are not able to perform their ecological functions or provide services to other natural resources or to the public until the primary or complementary measures have taken effect; and does not include financial compensation to the public.

ObjectivesS

3.—(1) Environmental damage, in relation to water, protected species or natural habitats, shall be effected by the restoration of the environment to its baseline condition by—

(a)primary remediation;

(b)complementary remediation; and

(c)compensatory remediation.

(2) Where primary remediation does not result in the restoration of the environment to its baseline condition, then complementary remediation will be undertaken, and compensatory remediation will be undertaken to compensate for the interim losses.

Risk to human healthS

4.  The remedying of environmental damage, in relation to damage to water, protected species or natural habitats, shall result in the removal of any significant risk of human health being adversely affected.

Identification of remedial measuresS

5.—(1) In relation to primary remediation, actions to restore the natural resources and services towards baseline condition on an accelerated time‑frame, or through natural recovery, shall be considered.

(2) In relation to complementary and compensatory remediation—

(i)if possible, complementary and compensatory remedial measures must provide natural resources or services of the same type, quality and quantity as those damaged;

(ii)where this is not possible, similar but different natural resources or services must be provided (for example, by offsetting a reduction in the quality of natural resources or services by increasing their quantity);

(iii)where this is not possible, different natural resources or services may be provided, and the remedial measures must have the same monetary valuation as the lost natural resources or services;

(iv)if valuation of the lost natural resources or services is practicable, but valuation of the remedial measures cannot be made within a reasonable time or at a reasonable cost, then remedial measures may be provided whose cost is equivalent to the estimated monetary value of the lost natural resources or services;

(v)in the case of complementary remediation at a new site, where possible and appropriate this site should be geographically linked to the damaged site.

Choice of remediationS

6.—(1) The reasonable remedial options should be evaluated, using best available technologies, based on the following criteria—

(a)the effect of each option on public health and safety;

(b)the cost of implementing the option;

(c)the likelihood of success of each option;

(d)the extent to which each option will prevent future damage, and avoid collateral damage as a result of implementing the option;

(e)the extent to which each option benefits to each component of the natural resource or service;

(f)the extent to which each option takes account of relevant social, economic and cultural concerns and other relevant factors specific to the locality;

(g)the length of time it will take for the restoration of the environmental damage to be effective;

(h)the extent to which each option achieves the restoration of the site of the environmental damage; and

(i)the geographical linkage to the damaged site.

(2) When evaluating the different identified remedial options, primary remedial measures that do not fully restore the damaged water or protected species or natural habitat to baseline or that restore it more slowly can be chosen. This decision can be taken only if the natural resources or services foregone at the primary site as a result of the decision are compensated for by increasing complementary actions to provide a similar level of natural resources or services as were foregone. This will be the case, for example, when the equivalent natural resources or services could be provided elsewhere at a lower cost. These additional remedial measures shall be determined in accordance with the rules set out in paragraph 5(2).

(3) The competent authority may at any time decide that no further remedial measures should be taken if—

(a)the remedial measures already taken secure that there is no longer any significant risk of adversely affecting human health, water or protected species and natural habitats; and

(b)the cost of the remedial measures that should be taken to reach baseline condition or similar level would be disproportionate to the environmental benefits to be obtained.

PART II S

1.  This Part applies to damage to land.S

2.  The necessary measures shall be taken to ensure, as a minimum, that the relevant contaminants are removed, controlled, contained or diminished so that the contaminated land, taking account of its current use or approved future use at the time of the damage, no longer poses any significant risk of adversely affecting human health.S

3.  The presence of such risks shall be assessed through risk‑assessment procedures taking into account the characteristic and function of the soil, the type and concentration of the harmful substances, preparations, organisms or micro‑organisms, their risk and the possibility of their dispersion.S

4.  Use shall be ascertained on the basis of any enactment relating to land use, or other relevant enactments, in force, when the damage occurred.S

5.  If the use of the land is changed, all necessary measures shall be taken to prevent any adverse effects on human health.S

6.  If there are no enactments which are relevant for the purposes of paragraph 4, the nature of the relevant area where the damage occurred, taking into account its expected development, shall determine the use of the specific area.S

7.  A natural recovery option, that is to say an option in which no direct human intervention in the recovery process would be taken, shall be considered.S

Regulation 16

SCHEDULE 4SCOMPENSATION

InterpretationS

1.  In this Schedule—

the Act” means the Land Compensation (Scotland) Act 1963 M4;

the grantor” means the person who grants, or joins in granting, any rights under regulation 16, and

relevant interest” means an interest in land in respect of which rights are granted in terms of regulation 16.

Marginal Citations

Period for making an applicationS

2.  An application for compensation shall be made before the expiry of a period of 12 months beginning with the date of completion of the measures required to be carried out in respect of which compensation is claimed.

Manner of making an applicationS

3.—(1) An application for compensation must be made in writing to the person to whom the right was granted.

(2) The application must contain—

(a)a copy of the grant of rights in respect of which the grantor is applying for compensation;

(b)a description of the exact nature of any interest in land in respect of which compensation is applied for; and

(c)a statement of the amount of compensation applied for, distinguishing the amounts applied for under each of sub-paragraphs (a) to (c) of paragraph 4 and showing how the amount applied for under each sub-paragraph has been calculated.

Loss and damage for which compensation payableS

4.  Compensation shall be payable for loss and damage of the following descriptions—

(a)any depreciation in the value of any relevant interest to which the grantor is entitled which results from the grant of the right;

(b)any loss or damage sustained by the grantor which is attributable to the grant of the right or the exercise of it; and

(c)the amount of any valuation and legal costs reasonably incurred by the grantor in granting the right and in the preparation of the application for and the negotiation of the amount of compensation.

Basis on which compensation assessedS

5.—(1) The rules set out in section 12 of the Act (rules for assessing compensation) M5 shall, so far as applicable and subject to any necessary modifications, have effect for the purpose of assessing any compensation as they have effect for the purpose of assessing compensation for the compulsory acquisition of an interest in land.

(2) Where the relevant interest in respect of which any compensation is to be assessed is subject to a standard security (within the meaning of section 9 of the Conveyancing and Feudal Reform (Scotland) Act 1970 M6)—

(a)the compensation must be assessed as if the interest were not subject to that security; and

(b)no compensation shall be payable in respect of the interest of the creditor (as distinct from the interest which is subject to the security).

Marginal Citations

M5Section 12 has been amended by Schedules 17 and 19 to the Planning and Compensation Act 1991 (c.34).

M61970 c.35. Section 9 has been amended by paragraph 30(6) of and Schedule 13 to the Abolition of Feudal Tenure etc. (Scotland) Act 2000 (asp 5) and by paragraph 4(2) of Schedule 14 to the Title Conditions (Scotland) Act 2003 (asp 9).

Determination of disputesS

6.  Any question of disputed compensation shall be referred to and determined by the Lands Tribunal for Scotland.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources